IO I SYSTEMS, INC. v. City of Cleveland, Tex.

615 S.W.2d 786, 1980 Tex. App. LEXIS 4254
CourtCourt of Appeals of Texas
DecidedDecember 18, 1980
Docket17638
StatusPublished
Cited by31 cases

This text of 615 S.W.2d 786 (IO I SYSTEMS, INC. v. City of Cleveland, Tex.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
IO I SYSTEMS, INC. v. City of Cleveland, Tex., 615 S.W.2d 786, 1980 Tex. App. LEXIS 4254 (Tex. Ct. App. 1980).

Opinion

DOYLE, Justice.

I.O.I. Systems, Inc. (IOI) brought suit to recover $96,891.70 allegedly owed pursuant to a construction contract. IOI and the City of Cleveland, Texas (City) had entered into said contract for the construction of sanitary sewer improvements in Cleveland. Bayshore Engineers, Inc. (BEI) and C. Dieter Ufer (Ufer) designed the plans for this project and served in a supervisory capacity although they did not act as resident inspectors for the project. There was never any contract executed between BEI, Ufer and IOI.

For clarity, IOI’s cause of action must be divided into two parts: 1) suit on the contract with City for which it sought the unpaid balance of $2,500; and 2) suit for extra work required because of alleged negligence on the part of City, BEI and Ufer in supplying IOI with incorrect specifications and plans which resulted in its constructing a defective sewer system. IOI subsequently corrected these defects for a cost of $91,500. Additionally, IOI also sought payment for extra material not included in the price of the original contract in the amount of $2,891.70.

The City filed a counterclaim against IOI alleging breach of contract, an accord and satisfaction between the parties, as to $91,-500 claimed by IOI for extra work, and sought damages in excess of $90,000.00. Trial was to a jury, which found IOI did not substantially comply with the contract; that IOI was not entitled to any recovery except $2,891.70 for the additional cost of steel casing and fences; and that appellee City was damaged in the amount of $46,-523.88. Issues regarding the negligence of Bayshore and Ufer were not answered, due to their conditional submission based on previous answers.

At the close of IOI’s case and again at the close of all the evidence, IOI requested a directed verdict against City on its counterclaim based on the statute of limitations. The court overruled IOI’s motion, but prior to the rendition of judgment, at IOI’s request, the court disregarded the jury’s answers to the special issues awarding damages to the City on its counterclaim. The court rendered judgment in favor of IOI for $2,891.70 plus interest, totaling $3,422.97. The judgment recited that IOI take nothing against BEI and Ufer, and that the City take nothing against IOI on its counterclaim. The court adjudged all court costs in City’s suit against IOI against City.

*788 The facts in this case can be simply stated. In 1973 IOI and City executed a contract to construct sanitary sewer improvements for City. During construction IOI encountered water in the trench where the pipes were to be laid. At this time, IOI realized there might be problems with this construction and requested Ufer and the City to remedy the problem. In order to correct the situation, additional fill material was needed for which neither City nor IOI would agree to pay. After pumping the visible water out of the trench, but without adding the fill material, IOI continued the project. Subsequently six breaks resulted in this pipeline. IOI fixed these breaks, receiving approximately $4,000.00 from City to pay for liners to repair the pipes. However, IOI alone spent an additional $91,000 on these repairs.

When the City agreed to pay the additional $4,000.00 it considered this to be an accord and satisfaction of all costs and claimed surprise regarding the additional $91,000.00. This project was finally certified as completed in May 1975. In August 1975, IOI filed this suit for the monetary damages.

IOI brings this appeal asserting nineteen points of error. City, Bayshore and Ufer, jointly, filed reply briefs in which they assert several cross-points of error.

By the first six points of error, IOI essentially asserts that the trial court erred by not itself interpreting the contract for the jury, establishing the obligations of the engineer and the contractor with regard to laying the pipe foundation in natural ground where such, ground was unsuitable; that the trial court erred by not instructing the jury that only the engineer could determine whether the pipe should be installed other than on natural ground; that the trial court erred in refusing to disregard the jury’s answer to special issue 8; and finally that the trial court erred in predicating special issues 2, 3, 4 and 5 upon an affirmative answer to special issue 1, as such issue 1 did not properly instruct the jury regarding the contract between the parties.

As a matter of law the trial court has the responsibility of interpreting an unambiguous contract from the language used therein. Tower Contracting Company, Inc. v. Flores, 157 Tex. 297, 302 S.W.2d 396 (1957); Myers v. Gulf Coast Minerals Management Corporation, 361 S.W.2d 193 (Tex.1962). IOI alleges that pursuant to Article 3271a, Section 19, V.A.T.S., in order for any political subdivision of the State of Texas to enter into any public works contract, construction plans for such work must be “prepared by, and the engineering construction is to be executed under the direct supervision of a registered professional engineer. ...” Therefore, IOI continues, pursuant to this contract and statute, the duty of the engineer is to determine if the trench bottom is unsuitable as a sewer line foundation and, if so, prescribe the “approved” material to be used in stabilizing it. The contractor, on the other hand, is only required to comply strictly with the contract and the plans; perform additional excavation as needed; and remove water or other unsuitable material which may enter the trench.

The case of Kansas Turnpike Authority v. Abramson, 275 F.2d 711 (1960) is cited for the proposition that where plans and specifications have been supplied for the contractor as in the instant case, he is responsible only for following such plans and specifications. In arriving at the decision in that case, the court first construed all the provisions of the contract therein involved and concluded that even though the problems occurring in that situation resulted from the elements, the contract did not provide that the contractor should bear the unforeseen risk of the elements. In that case there were no contractual provisions “imposing some other or further obligation,” on the contractor.

In the case at bar the contract imposed a greater liability on the contractor than the contract in the Kansas case. More than simply requiring IOI to follow plans and specifications, the instant contract made the contractor liable for conditions at the site; for conditions due to unforeseen *789 circumstances; and for supplying all necessary materials to install a completed sewer system. Relevant provisions of the contract are set out as follows:

NOTICE TO BIDDERS
9. Conditions of Site and Work
Bidders should carefully examine the Plans, Specifications and other documents, visit the site of the work, and fully inform themselves as to all conditions and matters which can in any way affect the work or costs thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dukes v. Philip Johnson/Alan Ritchie Architects, P.C.
252 S.W.3d 586 (Court of Appeals of Texas, 2008)
Dukes v. PHILIP JOHNSON/ALAN RITCHIE ARCH., PC
252 S.W.3d 586 (Court of Appeals of Texas, 2008)
Cleveland Franklin v. Robert C. Banks
Court of Appeals of Texas, 2007
Barnard Construction Co. v. City of Lubbock
457 F.3d 425 (Fifth Circuit, 2006)
Eastern Steel Constructors, Inc. v. City of Salem
549 S.E.2d 266 (West Virginia Supreme Court, 2001)
CBI Na-Con, Inc. v. UOP, Inc.
961 S.W.2d 336 (Court of Appeals of Texas, 1998)
IT Corp. v. Motco Site Trust Fund
903 F. Supp. 1106 (S.D. Texas, 1994)
Romero v. Parkhill, Smith & Cooper, Inc.
881 S.W.2d 522 (Court of Appeals of Texas, 1994)
Parkway Co. v. Woodruff
857 S.W.2d 903 (Court of Appeals of Texas, 1993)
Prellwitz v. Cromwell, Truemper, Levy, Parker & Woodsmale, Inc.
802 S.W.2d 316 (Court of Appeals of Texas, 1990)
Getzschman v. Miller Chemical Co., Inc.
443 N.W.2d 260 (Nebraska Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
615 S.W.2d 786, 1980 Tex. App. LEXIS 4254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/io-i-systems-inc-v-city-of-cleveland-tex-texapp-1980.