Barnard Construction Co. v. City of Lubbock

457 F.3d 425, 2006 WL 2023109
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 7, 2006
Docket05-10582
StatusPublished
Cited by6 cases

This text of 457 F.3d 425 (Barnard Construction Co. v. City of Lubbock) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barnard Construction Co. v. City of Lubbock, 457 F.3d 425, 2006 WL 2023109 (5th Cir. 2006).

Opinions

PER CURIAM:

I

Barnard Construction Co. (“Barnard”) sued the City of Lubbock, Texas (“City”) for breach of contract in the Northern District of Texas. The district court granted the City’s motion for summary judgment, and Barnard appeals.

Barnard submitted the lowest bid for a pipeline construction contract to the City. The City hired an independent engineering company to act as “Engineer” for the project. The Engineer was responsible for, inter alia, the bid form for the pipeline construction project. The bid form included a line item for rock excavation, but only for one of the fifteen pipelines (Line Al), because the Engineer’s data suggested that rock excavation was needed only in the one pipeline. Prior to the bidding process, the City expressly stated that the Engineer’s data was for informational purposes only, and that bidders had the opportunity to drill their own test holes. The City also offered a question and answer session prior to bidding and made changes to the pipeline construction contract via addenda as a result of the question and answer session. Barnard did not drill its own test holes.

Barnard and the City entered into a written contract. The City estimated that 410 cubic yards of rock would need excavating from Line Al; but whatever quantity of rock was excavated from Line Al, the City would pay Barnard at the unit price for which they bid ($200). In performance of the contract, Barnard discovered lines other than Line Al required rock excavation as well. Barnard excavated rock from several lines other than Line Al. After Barnard billed the City for all rock excavated, the City initially paid, but later offset payment for rock excavated outside of Line Al. Barnard sued for breach of contract and on appeal argues for reversal of summary judgment. First, Barnard argues that the City’s decision to pay for all rock excavated is a final, conclusive decision pursuant to the contract. In response, the City maintains it had communicated to Barnard before or at the time of payment that it might later offset payment for rock excavated outside of Line Al.1 In addition, Barnard argues that the contract [427]*427is unambiguous in its terms requiring payment of all rock excavated, or alternatively, that it is ambiguous thereby warranting reversal of summary judgment.

II

We review an appeal from summary judgment de novo, applying the same standard as the district court. Degan v. Ford Motor Co., 869 F.2d 889, 892 (5th Cir.1989). Summary judgment is appropriate if there is “no genuine issue as to any material fact and ... the moving party is entitled to a judgment as a matter of law.” FED. R. CIV. P. 56(c). Because this suit is based on diversity jurisdiction, we apply Texas substantive law to determine whether the City was entitled to summary judgment. Fireman’s Fund Ins. Co. v. Murchison, 937 F.2d 204, 207 (5th Cir.1991).

We review the interpretation of a contract, including the question of whether the contract is ambiguous, de novo. Constitution State Ins. Co. v. Iso-Tex Inc., 61 F.3d 405, 407 (5th Cir.1995) (citation omitted).

III

Barnard’s first argument, that the City’s decision to pay for all rock excavated is a final, conclusive decision pursuant to the contract, fails because the contract grants the City authority to make a final determination regarding the amount and quantity of work done by Barnard in excavating rock. Paragraph 47 of the General Conditions reads, in pertinent part:

Any decision by the Owner’s Representative, or deemed denial by the Owner’s Representative, shall be final and conclusive in the absence of fraud.

Paragraph 14 of the “General Conditions of the Agreement,” clearly states, in pertinent part:

Unless otherwise specified, it is mutually agreed between the parties to this Agreement that the Owner’s Representative has the authority to review all work included herein. The Owner’s Representative has the authority to stop the work whenever such stoppage may be necessary to ensure the proper execution of the contract. The Owner’s Representative shall, in all cases, determine the amounts and quantities of the several kinds of work which are to be paid under the contract documents, and shall determine all questions in relation to said work and the construction thereof, and shall, in all cases, decide every question which may arise relative to the execution of this contract on the part of said Contractor.

The record is clear that the City, via the Owner’s Representative, told Barnard that it was only considering Barnard’s request to pay for rock outside of Line Al.2 Barnard does not allege the City has committed fraud in making this decision. The Owner’s Representative made a final decision as to the amount and quantity of excavated rock for which Barnard was to be paid when it determined under the contract that it need not pay for rock excavated outside of Line Al.

IV

Barnard’s second argument also fails. First, it argues that the contract is [428]*428unambiguous thereby requiring payment for rock excavated outside of Line Al. Alternatively, Barnard argues the contract is ambiguous and therefore creates a genuine issue of material fact, requiring reversal and remand. Whether a contract is ambiguous is a question of law for the court to decide. Coker v. Coker, 650 S.W.2d 391, 394 (Tex.1983). If the written contract is worded such that it can be given a certain or definite legal meaning or interpretation, then it is not ambiguous and the court will construe the contract as a matter of law. J.M. Davidson, Inc. v. Webster, 128 S.W.3d 223, 229 (Tex.2003); Coker, 650 S.W.2d at 393. The court must give meaning to each of its provisions, in light of the circumstances surrounding the contract’s execution, excluding statements of the parties as to what they intended. Davidson, 128 S.W.3d at 229; see also Universal C.I.T. Credit Corp. v. Daniel, 150 Tex. 513, 243 S.W.2d 154, 157 (1951).

First, Barnard argues that the following circumstances, which they contend were not taken into account by the district court, existing at the time of execution, support its interpretation that the contract is unambiguous: (1) the City provided all the forms for the bidding process and did not allow any alteration of the form or negotiation of the terms; (2) no bidder could bid on a unit price for rock anticipated to be encountered except on the blank provided for rock excavation on Line Al; and (3) no bidder could increase an amount for work performed on one line in order to “pad” or “cover” unpaid work performed on another line. As the argument goes, because Barnard could not bid on rock outside of Line Al, it was irrelevant whether it took the opportunity to investigate the sub-surface conditions outside of Line Al.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mieco, L.L.C. v. Pioneer
Fifth Circuit, 2024
United States v. Mwalumba
688 F. Supp. 2d 565 (N.D. Texas, 2010)
Xtria LLC v. Tracking Systems Inc.
345 F. App'x 940 (Fifth Circuit, 2009)
Lennox v. Hallmark Capital Group, LLC
314 F. App'x 710 (Fifth Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
457 F.3d 425, 2006 WL 2023109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barnard-construction-co-v-city-of-lubbock-ca5-2006.