Barnard Const Co Inc v. City of Lubbock

CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 20, 2006
Docket05-10582
StatusUnpublished

This text of Barnard Const Co Inc v. City of Lubbock (Barnard Const Co Inc v. City of Lubbock) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barnard Const Co Inc v. City of Lubbock, (5th Cir. 2006).

Opinion

United States Court of Appeals Fifth Circuit F I L E D IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT July 19, 2006 _____________________ Charles R. Fulbruge III No. 05-10582 Clerk _____________________

BARNARD CONSTRUCTION CO.,

Plaintiff - Appellant,

v.

CITY OF LUBBOCK,

Defendant - Appellee.

_________________________________________________________________

Appeal from the United States District Court for the Southern District of Texas No. 5:03-CV-269 _________________________________________________________________

Before JONES, Chief Judge, WIENER, and PRADO, Circuit Judges.

PER CURIAM:*

I

Barnard Construction Co. (“Barnard”) sued the City of

Lubbock, Texas (“City”) for breach of contract in the Northern

District of Texas. The district court granted the City’s motion

for summary judgment, and Barnard appeals.

Barnard submitted the lowest bid for a pipeline construction

contract to the City. The City hired an independent engineering

company to act as “Engineer” for the project. The Engineer was

* Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4.

1 responsible for, inter alia, the bid form for the pipeline

construction project. The bid form included a line item for rock

excavation, but only for one of the fifteen pipelines (Line A1),

because the Engineer’s data suggested that rock excavation was

needed only in the one pipeline. Prior to the bidding process,

the City expressly stated that the Engineer’s data was for

informational purposes only, and that bidders had the opportunity

to drill their own test holes. The City also offered a question

and answer session prior to bidding and made changes to the

pipeline construction contract via addenda as a result of the

question and answer session. Barnard did not drill its own test

holes.

Barnard and the City entered into a written contract. The

City estimated that 410 cubic yards of rock would need excavating

from Line A1; but whatever quantity of rock was excavated from

Line A1, the City would pay Barnard at the unit price for which

they bid ($200). In performance of the contract, Barnard

discovered lines other than Line A1 required rock excavation as

well. Barnard excavated rock from several lines other than Line

A1. After Barnard billed the City for all rock excavated, the

City initially paid, but later offset payment for rock excavated

outside of Line A1. Barnard sued for breach of contract and on

appeal argues for reversal of summary judgment. First, Barnard

argues that the City’s decision to pay for all rock excavated is

a final, conclusive decision pursuant to the contract. In

2 response, the City maintains it had communicated to Barnard

before or at the time of payment that it might later offset

payment for rock excavated outside of Line A1.1 In addition,

Barnard argues that the contract is unambiguous in its terms

requiring payment of all rock excavated, or alternatively, that

it is ambiguous thereby warranting reversal of summary judgment.

II

We review an appeal from summary judgment de novo, applying

the same standard as the district court. Degan v. Ford Motor

Co., 869 F.2d 889, 892 (5th Cir. 1989). Summary judgment is

appropriate if there is “no genuine issue as to any material fact

and . . . the moving party is entitled to a judgment as a matter

of law.” FED. R. CIV. P. 56(c). Because this suit is based on

diversity jurisdiction, we apply Texas substantive law to

determine whether the City was entitled to summary judgment.

Fireman’s Fund Ins. Co. v. Murchison, 37 F.2d 204, 207 (5th Cir.

1991).

We review the interpretation of a contract, including the

question of whether the contract is ambiguous, de novo.

Constitution State Ins. Co. v. Iso-Tex Inc., 61 F.3d 405, 407

(5th Cir. 1995) (citation omitted).

III

1 Barnard contests the date this communication was made.

3 Barnard’s first argument, that the City’s decision to pay

for all rock excavated is a final, conclusive decision pursuant

to the contract, fails because the contract grants the City

authority to make a final determination regarding the amount and

quantity of work done by Barnard in excavating rock. Paragraph

47 of the General Conditions reads, in pertinent part:

Any decision by the Owner’s Representative, or deemed denial by the Owner’s Representative, shall be final and conclusive in the absence of fraud.

Paragraph 14 of the “General Conditions of the Agreement,”

clearly states, in pertinent part:

Unless otherwise specified, it is mutually agreed between the parties to this Agreement that the Owner’s Representative has the authority to review all work included herein. The Owner’s Representative has the authority to stop the work whenever such stoppage may be necessary to ensure the proper execution of the contract. The Owner’s Representative shall, in all cases, determine the amounts and quantities of the several kinds of work which are to be paid under the contract documents, and shall determine all questions in relation to said work and the construction thereof, and shall, in all cases, decide every question which may arise relative to the execution of this contract on the part of said Contractor.

The record is clear that the City, via the Owner’s

Representative, told Barnard that it was only considering

Barnard’s request to pay for rock outside of Line A1.2 Barnard

2 While Barnard disputes the date on which the City informed Barnard that it would only consider the payment, the date is not dispositive; nor is the fact that the communication was made. The fact that Barnard was initially paid for the rock excavated outside of Line A1 is also irrelevant. The contract places authority over final decisions on the Owner’s Representative. After reviewing the City’s obligations under the contract, the City and the Owner’s Representative correctly determined that it

4 does not allege the City has committed fraud in making this

decision. The Owner’s Representative made a final decision as to

the amount and quantity of excavated rock for which Barnard was

to be paid when it determined under the contract that it need not

pay for rock excavated outside of Line A1.

IV

Barnard’s second argument also fails. First, it argues that

the contract is unambiguous thereby requiring payment for rock

excavated outside of Line A1. Alternatively, Barnard argues the

contract is ambiguous and therefore creates a genuine issue of

material fact, requiring reversal and remand. Whether a contract

is ambiguous is a question of law for the court to decide. Coker

v. Coker, 650 S.W.2d 391, 394 (Tex. 1983). If the written

contract is worded such that it can be given a certain or

definite legal meaning or interpretation, then it is not

ambiguous and the court will construe the contract as a matter of

law. J.M. Davidson, Inc. v. Webster, 128 S.W.3d 223, 229 (Tex.

2003); Coker, 650 S.W.2d at 393. The court must give meaning to

each of its provisions, in light of the circumstances surrounding

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Universal C. I. T. Credit Corp. v. Daniel
243 S.W.2d 154 (Texas Supreme Court, 1951)
City of San Antonio v. Heath & Stich, Inc.
567 S.W.2d 56 (Court of Appeals of Texas, 1978)
IO I SYSTEMS, INC. v. City of Cleveland, Tex.
615 S.W.2d 786 (Court of Appeals of Texas, 1980)
Degan v. Ford Motor Co.
869 F.2d 889 (Fifth Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Barnard Const Co Inc v. City of Lubbock, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barnard-const-co-inc-v-city-of-lubbock-ca5-2006.