Nelson v. San Antonio Traction Company

175 S.W. 434, 107 Tex. 180, 1915 Tex. LEXIS 135
CourtTexas Supreme Court
DecidedApril 14, 1915
DocketNo. 2398.
StatusPublished
Cited by41 cases

This text of 175 S.W. 434 (Nelson v. San Antonio Traction Company) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nelson v. San Antonio Traction Company, 175 S.W. 434, 107 Tex. 180, 1915 Tex. LEXIS 135 (Tex. 1915).

Opinion

Mr. Chief Justice BBOWK

delivered the opinion of the court.

We find it somewhat difficult to make a proper statement of the facts upon which the decision of this case depends, but we believe that it can be’ better accomplished by making liberal extracts from the opinion of the Court of Civil Appeals, which we do as follows:

“This suit was brought "on May 22, 1905, by The Parker Washington Company against J. P. Kelson and others, to recover the price which Kelson had agreed to pay plaintiff as his subcontract for certain work done for the San Antonio Traction Company under Kelson’s contract with it, and to foreclose a mechanic’s lien upon the property of said Traction Company. Other defendants in this petition were the Kelson Paving Company and the San Antonio Traction Company and the TJvalde Asphalt Company.

“Kelson and the Kelson Paving Company filed a cross-action to recover against the Traction Company for what was due under Kelson’s contract with said company and to foreclose mechanic’s lien on the latter’s property.

“The Traction Company defended against said actions upon the ground that the work done by the Parker Washington Company was not in accordance with Kelson’s contract with it and claimed that it had . paid more for the work done than it was reasonably worth; and it also *185 on January 3, 1911, filed a cross-action against Nelson and the Nelson Paving Company for breach of his contract with it.

“The case was determined by the trial court in special findings of the jury, supplemented with finding by the trial judge.

“The case comes here narrowed down to issues of law which concern solely the Traction Company and Nelson. It is, therefore, unnecessary to state in this opinion more from the voluminous record than is necessary to elucidate those issues.

“Nelson, on January 3, 1901, entered into a contract with the San Antonio Traction Company to lay for it the certain asphalt pavements in controversy here, and to maintain and repair the same for a period of ten years. He assigned this contract to the Nelson Paving Company. On October 26,1901, he and the Nelson Paving Company, by subcontract, turned the work over to the Parker Washington Company, and the Parker Washington Company laid the pavement in controversy, completing the same December 20, 1901.

“The Traction Company had agreed to pay Nelson certain prices, partly as the work progressed and balance when the work was completed. The bulk of the price was paid during the progress of .the work, but when completed the Traction Company refused to make the final payment.

“Nelson and the Nelson Paving Company had agreed to pay the Parker Washington Company the price named in the contract and whenever Nelson received payments from the Traction Company they were turned over to Parker Washington Company; but when it came to the final payment he refused to pay the Parker Washington Company, claiming that the money was not due from him until he was paid by the Traction Company; and Nelson announced that he refused to be bound by his contract to maintain the pavement and claims that his contract with the Traction Company to do so was discharged or terminated by said company’s breach of its contract in refusing to make the final payment.

“The findings so far as material to this appeal were that the work 'when completed was in accordance with Nelson’s contract, hence no valid reason existed in fact for the Traction Company’s refusal to make the final payment when it was due. That Nelson was entitled to recover from it the sum of $18,516.52, this being the balance of the contract price, $11,819.51, with interest thereon to the date of the decree.

“There was also a finding that the San Antonio Traction Company was entitled to recover on its cross-action, against Nelson and the Nelson Paving Company, the sum of $15,714.40 and $3491.00 interest thereon to date of decree, making $19,205.60, for breach of Nelson’s contract to maintain.

“The above allowance to the Traction Company resulted in a judgment being rendered in favor of said company against Nelson and the Nelson Paving Company for the difference, $689.08.”

*186 The provision, of the contract on this subject reads as follows:

“The Contractor agrees to guarantee the pavement for a period of ten (10) years from the date of acceptance, which shall be when open to traffic, and during said period all defects in said pavement, upon notice from the ¡Railway Company or the City Engineer or City Council, shall be immediately repaired by the Contractor at his own cost and expense and free of cost to the Railway Company or to the City of San Antonio, said Contractor agreeing that before he shall receive any money on this contract he will furnish to the Railway Company a bond in the sum of seventeen thousand' dollars ($17,000) to be guaranteed by some surety company acceptable to the Railway Company, conditioned that said Contractor shall faithfulty maintain said pavements for said period of ten (10) years, and shall pay all costs of preparing the pavement to be constructed, hereunder during the said period of ten (10) years. The repairs shall be made at the time and in the manner and under the conditions specified in the contract of the City of San Antonio with the Parker-Washington Company.

“Nothing is found in the contract which conditioned the above obligation upon compliance by the Traction Company with its obligations to make payments in accordance with the contract. The fact is that the contract price it was to pay for the work amounted to $93,554.30 and it had paid during the progress of the work all but $11,819.51.”

The application for writ of error is based upon the following two grounds:

¡First: That the Traction Company had, by refusing to pay the sum sued for, repudiated the contract between Nelson and the said Traction Company, and therefore could not make a defense under that contract.

Second: That the claim of the Traction Company was barred by • the statute of limitation of four years.

There was no abandonment of the contract by the Traction Company, as the evidence appears in the record, but its demand was simply an enforcement of the terms of the contract by which it was entitled to a credit upon a balance due to the Nelson Company for the cost that it had been put to in maintaining the pavement. In the terms of the contract itself the cost of the work of maintaining it was included in the sum agreed to be paid by the Traction Company.

The claim set up by the Traction Company for a reduction of the demand made by the Nelson Company for the construction of the pavement was based upon the refusal of Nelson to perform his part of the contract for the construction and upkeep of the pavement itself. When the Nelson Company refused to make the necessary repairs upon the pavement in accordance with their contract they were guilty of a breach of that contract, and the Traction Company, being bound to the city to perform that work, had the right to perform it in accordance with its eontráct. and the measure of its recompense would be the cost to it of performing the work which Nelson had contracted to do, but had failed to perform. In order to determine the question of limitation upon this

Free access — add to your briefcase to read the full text and ask questions with AI

Related

IO I SYSTEMS, INC. v. City of Cleveland, Tex.
615 S.W.2d 786 (Court of Appeals of Texas, 1980)
Hobbs Trailers v. JT Arnett Grain Co., Inc.
560 S.W.2d 85 (Texas Supreme Court, 1977)
Christian v. First National Bank of Weatherford
531 S.W.2d 832 (Court of Appeals of Texas, 1975)
Troy v. Mutual Life Insurance Co. of New York
514 S.W.2d 822 (Court of Appeals of Texas, 1974)
Swaim v. INTERNATIONAL HARVESTER COMPANY
505 S.W.2d 634 (Court of Appeals of Texas, 1974)
Finger v. Morris
468 S.W.2d 572 (Court of Appeals of Texas, 1971)
Southern Pacific Company v. Porter
331 S.W.2d 42 (Texas Supreme Court, 1960)
Clanton v. Community Finance & Thrift Corp.
262 S.W.2d 252 (Court of Appeals of Texas, 1953)
Hayward v. City of Corpus Christi
195 S.W.2d 995 (Court of Appeals of Texas, 1946)
Murphy v. Boyt
180 S.W.2d 199 (Court of Appeals of Texas, 1944)
Waterbury Tool Co. v. Commissioner
2 T.C. 904 (U.S. Tax Court, 1943)
Pennsylvania R. Co. v. Miller
124 F.2d 160 (Fifth Circuit, 1941)
Tenison v. Wilson
151 S.W.2d 327 (Court of Appeals of Texas, 1941)
De Witt v. Kent County
148 S.W.2d 213 (Court of Appeals of Texas, 1940)
Tyrrell Combest Realty Co. v. Ellis
127 S.W.2d 598 (Court of Appeals of Texas, 1939)
Causeway Investment Co. v. Nass
111 S.W.2d 703 (Texas Supreme Court, 1938)
Joiner v. City of Terrell
103 S.W.2d 1055 (Court of Appeals of Texas, 1937)
Morris-Buick Co. v. Davis
91 S.W.2d 313 (Texas Supreme Court, 1936)
Morriss-Buick Co. v. Davis
59 S.W.2d 937 (Court of Appeals of Texas, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
175 S.W. 434, 107 Tex. 180, 1915 Tex. LEXIS 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nelson-v-san-antonio-traction-company-tex-1915.