United States v. Rogers & Rogers

161 F. Supp. 132, 1958 U.S. Dist. LEXIS 2335
CourtDistrict Court, S.D. California
DecidedApril 22, 1958
DocketCiv. 19487, 19769
StatusPublished
Cited by66 cases

This text of 161 F. Supp. 132 (United States v. Rogers & Rogers) is published on Counsel Stack Legal Research, covering District Court, S.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Rogers & Rogers, 161 F. Supp. 132, 1958 U.S. Dist. LEXIS 2335 (S.D. Cal. 1958).

Opinion

MATHES, District Judge.

These actions were brought in the name of the United States, pursuant to § 2 of the Miller Act [49 Stat. 794 (1935), 40 U.S.C.A. § 270b], by the Los Angeles Testing Laboratory and D. L. Holliday, suppliers of labor and materials for a Government school-construction project, against the partnership of Rogers and Rogers, prime contractor for the project, and its surety [see Miller Act § 1, 49 Stat. 793 (1935), 40 U.S.C.A. § 270a].

In each action the defendant prime contractor has answered and asserted a counterclaim against the plaintiff mate-rialmen and the Government’s architect for the project, the latter being brought in as an additional party counterdefend-ant pursuant to Rule 13(h) [Fed.R.Civ.P. 13(h), 28 U.S.C.].

Briefly put, the factual background is this. Holliday supplied transit-mix concrete for the project, and is suing for the balance due on the purchase price. The Los Angeles Testing Laboratory was designated by the Government architect and retained by the prime contractor to test and inspect the concrete, and is suing for the balance of its fee.

The prime contractor alleges in the counterclaim that certain concrete furnished by Holliday was not up to specifications ; that this was not brought to the prime contractor’s attention until, after *134 the concrete had been incorporated into the building; that the furnishing and incorporation into the building of this sub-standard concrete was due to negligence on the part of one or more or all the counterdefendants; that as a result of the concrete’s failure to meet specifications the architect ordered the work stopped; that in order to secure approval of the work and have the stop-work order withdrawn, corrective measures were required which, together with the consequent delay, caused substantial expense for which the prime contractor seeks judgment against the counterde-fendants.

The counterdefendant architect now moves in the alternative for judgment on the pleadings or for summary judgment on the counterclaim. Inasmuch as various affidavits and other matters of record outside the pleadings have been presented to and considered by the court, the motion must be treated as one solely for summary judgment. Fed.R. Civ.P. 12(c).

Although not raised by any of the parties, there is confronted at the outset the question, as yet undecided in this Circuit, whether this court has jurisdiction of the prime contractor’s counterclaim as against the brought-in counterdefendant architect. That claim, not being one for labor or material furnished in the performance of a contract with respect to which a payment bond is required by § 1 of the Miller Act [40 U.S.C.A. § 270a], does not arise under that Act; nor does diversity of citizenship exist between the counterclaimant contractor and the coun-terdefendant architect [28 U.S.C. § 1332],

As to the plaintiff material-men, the counterclaim is clearly a compulsory one [Fed.R.Civ.P. 13(a)] over which this Court has jurisdiction ancillary to original jurisdiction under the Miller' Act, so no independent jurisdictional ground is essential to support the counterclaim as against the materialmen. Moore v. New York Cotton Exchange, 1926, 270 U.S. 593, 46 S.Ct. 367, 70 L.Ed. 750. And the better reasoned cases hold that ancillary jurisdiction which will support a compulsory counterclaim against one or more counterdefendants also extends to additional parties counterde-fendant brought in under Rule 13(h), so no independent or separate ground of federal jurisdiction is necessary as to such additional parties. United Artists Corp. v. Masterpiece Productions, Inc., 2 Cir., 1955, 221 F.2d 213; United States for Use and Benefit of Jones Contracting Co. v. Skilken, D.C.N.D.Ohio 1943, 53 F.Supp. 14; see Ciechanowicz v. Bowery Savings Bank, D.C.S.D.N.Y.1956, 19 F.R.D. 367. Contra, McNaughton v. New York Central R. Co., 7 Cir., 1955, 220 F.2d 835, 840.

The apparent holding to the contrary in Reynolds v. Maples, 5 Cir., 1954, 214 F.2d 395, 399, has been distinguished on the ground that there the court might have thought the counterclaim was not compulsory. United Artists Corp. v. Masterpiece Productions, Inc., supra, 221 F.2d at page 217, note 4. In any event, doubt is cast upon the authority of the jurisdictional holding in Reynolds v. Maples by the recent ruling of the Fifth Circuit that a cross claim’ under Rule 13 (g) is to be considered ancillary to the main action and so maintainable without any independent ground of federal jurisdiction. Childress v. Cook, 5 Cir., 1957, 245 F.2d 798, 802-805.

Accordingly I hold that this Court has jurisdiction over the counterclaim asserted against the architect, and now proceed to consider on the merits his motion for summary judgment.

The record before the Court on the pending motion establishes without contradiction that the architect was contractually obligated to the United States to prepare plans and specifications for and supervise the construction of the school building involved. This record further shows beyond dispute that under the prime contractor’s agreement with the Government the architect had not only the general supervision and direction of the work, but also the authority to stop the work whenever that might be *135 necessary to insure specified performance.

The gravamen of the prime contractor’s counterclaim as against the architect is negligent supervision: that the architect negligently construed and interpreted reports of tests on the concrete in question; that he then negligently approved bents (pre-formed structures which when hoisted into place form the skeleton of the building) made of that concrete, when in fact, as he should have known, the concrete failed to meet specifications; that he then negligently authorized or ordered incorporation of the . bents into the building; that because the concrete failed to meet specifications the State agency with ultimate power of approval refused to pass the bents; that the architect then stopped the work, and the prime contractor suffered damage by reason of the cost of compensating for the defective bents and the consequent delay in completion of the contract.

The architect has joined a genuine issue of fact by denying that he was negligent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GRACE & NAEEM UDDIN, INC. v. SINGER ARCHITECTS, INC.
District Court of Appeal of Florida, 2019
Lathan Co. v. State
237 So. 3d 1 (Louisiana Court of Appeal, 2017)
Aliant Bank v. Four Star Invs., Inc.
244 So. 3d 896 (Supreme Court of Alabama, 2017)
Harris Builders, L.L.C. v. URS Corp.
861 F. Supp. 2d 746 (E.D. Louisiana, 2012)
Robertson Stephens, Inc. v. Chubb Corp.
473 F. Supp. 2d 265 (D. Rhode Island, 2007)
Cincinnati Ins. Cos. v. BARBER INSULATION
946 So. 2d 441 (Supreme Court of Alabama, 2006)
Ellis-Don Construction, Inc. v. HKS, Inc.
353 F. Supp. 2d 603 (M.D. North Carolina, 2004)
Insurance Co. of North America v. Town of Manchester
17 F. Supp. 2d 81 (D. Connecticut, 1998)
Loenco v. Londonderry
D. New Hampshire, 1996
Dic Commercial Const. v. Broward Co.
668 So. 2d 697 (District Court of Appeal of Florida, 1996)
RPR & ASSOCIATES v. O'Brien/Atkins Associates
921 F. Supp. 1457 (M.D. North Carolina, 1995)
Tommy L. Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc.
463 S.E.2d 85 (Supreme Court of South Carolina, 1995)
Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc.
463 S.E.2d 85 (Supreme Court of South Carolina, 1995)
National Steel Erection, Inc. v. J.A. Jones Construction Co.
899 F. Supp. 268 (N.D. West Virginia, 1995)
Boston Investment Property 1 State v. E.W. Burman, Inc.
658 A.2d 515 (Supreme Court of Rhode Island, 1995)
PALAU INTERN. TRADERS v. Narcam Aircraft, Inc.
653 So. 2d 412 (District Court of Appeal of Florida, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
161 F. Supp. 132, 1958 U.S. Dist. LEXIS 2335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-rogers-rogers-casd-1958.