GRACE & NAEEM UDDIN, INC. v. SINGER ARCHITECTS, INC.

CourtDistrict Court of Appeal of Florida
DecidedAugust 28, 2019
Docket18-2972
StatusPublished

This text of GRACE & NAEEM UDDIN, INC. v. SINGER ARCHITECTS, INC. (GRACE & NAEEM UDDIN, INC. v. SINGER ARCHITECTS, INC.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GRACE & NAEEM UDDIN, INC. v. SINGER ARCHITECTS, INC., (Fla. Ct. App. 2019).

Opinion

DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FOURTH DISTRICT

GRACE AND NAEEM UDDIN, INC., a Florida corporation, Appellant,

v.

SINGER ARCHITECTS, INC., BROWARD COUNTY, and ARCH INSURANCE COMPANY, Appellees.

No. 4D18-2972

[August 28, 2019]

Appeal from the Circuit Court for the Seventeenth Judicial Circuit, Broward County; John B. Bowman, Judge; L.T. Case No. 14-004946 (05) and 13-013834 CACE (02).

David R. Elder and Kerry H. Lewis of Elder & Lewis, P.A., Miami, for appellant.

Neil P. Robertson of Daniels Rodriguez Berkeley Daniels & Cruz, P.A., Coral Gables, for appellees.

MAY, J.

Whether a supervising architect owes a duty of care to a contractor hired by the county for an airport improvement project is the question asked in this appeal. The contractor argues the trial court erred in failing to apply Moyer 1 and granting final summary judgment for the architect. We agree and reverse.

The county entered into separate contracts with the architect and the contractor for the development of an improvement project at the Fort Lauderdale Airport. The county’s contract with the architect assigned the latter with consultant and administrative duties. The county’s contract with the contractor concerned the scope of work and the architect’s role as a consultant and administrator.

1 A.R. Moyer v. Graham, 285 So. 2d 397 (Fla. 1973). As the project neared completion, the county terminated its contract with the contractor. The contractor filed suit against the county and the architect claiming breach of contract and professional negligence, respectively. The trial court consolidated the actions for discovery and trial.

The architect moved for partial summary judgment, arguing it did not owe the contractor a duty of care and the contractor could not recover contract damages in tort. The trial court granted the architect’s motion, concluding the architect did not owe the contractor a duty of care in its role as the county’s consultant. From that partial summary judgment, the contractor now appeals.

• The Architect/County Contract

The contract between the architect and the county outlined the architect’s role as “CONSULTANT SERVICES FOR MISCELLANEOUS PROFESSIONAL ARCHITECT, ENGINEER, AND INTERIOR DESIGN SERVICES.” The contract designated the architect as a “Consultant.” Article 10.20 declared the parties’ intent not to “create any rights or obligations in any third person or entity under this agreement.”

Under Article 3, the “SCOPE OF SERVICES/TASKS/PHASES,” the architect was responsible for: (1) visiting the site and attending construction events and meetings regularly; (2) conducting joint observations of the work with the county; (3) informing the county of the progress and quality of the work; (4) managing administrative records outlined in the contract; (5) assisting the county in determining the amounts owed to the contractor; and (6) certifying the contractor’s evaluation for payment.

The architect was to:

(1) interpret and give recommendations on disputes arising between the county and contractor;

(2) recommend rejection of work not in conformity with the contract;

(3) review and act on the contractor’s “shop drawings, product data and samples”;

(4) coordinate with the county to review “Change Orders for Code Compliance”;

2 (5) conduct site observations, make recommendations, and assist the county in determining the project’s completion; and

(6) manage the finalization of the project by preparing a punch list of incomplete or work needing correction and confirm the contractor’s “successful demonstration” of the project.

The architect’s principal described his role as the county’s “eyes and ears” for the project. He subcontracted a consulting firm to help him “run the job” because he could not dedicate more than fifteen or twenty percent of his time on the project. The scope of the consulting firm’s work related to reviewing construction schedules and other administrative work.

The principal admitted he recommended the contractor’s termination to the county and knew termination could happen upon his recommendation. Conversely, the county’s project manager testified that although the county and architect had discussions regarding the contractor’s termination, the architect never expressly recommended termination. The county’s director of capital improvement and projects and contract administrator for the project described the architect as the “architect on the job,” and relied on the principal’s input in reviewing pay applications, change orders, time extensions, and inspection of the punch list. He added that the county paid the contractor based on the principal’s recommendation.

• The Appeal

The contractor argues that Moyer recognized a professional negligence claim against an architect, who supervises a project resulting in economic damages to the contractor. Therefore, the contractor argues the trial court erred in granting partial summary judgment. The architect responds that the trial court correctly found the architect hired by the county owed no duty of care to the contractor because Florida case law does not extend the architect’s duty of care to the contractor. The architect also argues the contractor cannot recover contract damages against the architect because those damages would be duplicative.

We review summary judgments de novo. Chirillo v. Granicz, 199 So. 3d 246, 249 (Fla. 2016). “The duty of care in a negligence action is a question of law . . . .” Cheeks v. Dorsey, 846 So. 2d 1169, 1171 (Fla. 2003).

“Under Florida’s common law a person who is injured by another’s

3 negligence may maintain an action against the other person based on that other person’s violation of a duty of due care to the injured person.” Moransais v. Heathman, 744 So. 2d 973, 975 (Fla. 1999). “A professional duty may arise in favor of a third party as a result of a matter of law . . . .” Trikon Sunrise Assocs. v. Brice Bldg. Co., 41 So. 3d 315, 318 (Fla. 4th DCA 2010).

“[A] third party general contractor, who may foreseeably be injured or sustained an economic loss proximately caused by the negligent performance of a contractual duty of an architect, has a cause of action against the alleged negligent architect, notwithstanding absence of privity.” Moyer, 285 So. 2d at 402. Moyer relied upon California case law that recognized the professional liability of a supervising architect to a third-party contractor.

Altogether too much control over the contractor necessarily rests in the hands of the supervising architect for him not to be placed under a duty imposed by law to perform without negligence his functions as they affect the contractor. The power of the architect to stop the work alone is tantamount to a power of economic life or death over the contractor.

Id. at 401 (quoting United States v. Rogers & Rogers, 161 F. Supp. 132, 136 (S.D. Cal. 1958)).

Florida courts have required the existence of “supervisory duties” or responsibilities and a “close nexus” between the architect and contractor for Moyer to apply. McElvy, Jennewein, Stefany, Howard, Inc. v. Arlington Elec., Inc., 582 So. 2d 47, 49-50 (Fla. 2d DCA 1991); E.C. Goldman, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dic Commercial Const. v. Broward Co.
668 So. 2d 697 (District Court of Appeal of Florida, 1996)
Cheeks v. Dorsey
846 So. 2d 1169 (District Court of Appeal of Florida, 2003)
McElvy, Jennewein, Stefany, Howard, Inc. v. Arlington Elec., Inc.
582 So. 2d 47 (District Court of Appeal of Florida, 1991)
Moransais v. Heathman
744 So. 2d 973 (Supreme Court of Florida, 1999)
EC Goldman, Inc. v. A/R/C ASSOC., INC.
543 So. 2d 1268 (District Court of Appeal of Florida, 1989)
AR Moyer, Inc. v. Graham
285 So. 2d 397 (Supreme Court of Florida, 1973)
United States v. Rogers & Rogers
161 F. Supp. 132 (S.D. California, 1958)
Trikon Sunrise Associates, LLC v. Brice Building Co.
41 So. 3d 315 (District Court of Appeal of Florida, 2010)
Joseph S. Chirillo, Jr., M.D. v. Robert Granicz, etc.
199 So. 3d 246 (Supreme Court of Florida, 2016)
Tiara Condominium Ass'n v. Marsh & McLennan Companies
110 So. 3d 399 (Supreme Court of Florida, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
GRACE & NAEEM UDDIN, INC. v. SINGER ARCHITECTS, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/grace-naeem-uddin-inc-v-singer-architects-inc-fladistctapp-2019.