Trikon Sunrise Associates, LLC v. Brice Building Co.

41 So. 3d 315, 2010 Fla. App. LEXIS 10342, 2010 WL 2882434
CourtDistrict Court of Appeal of Florida
DecidedJuly 14, 2010
Docket4D09-752
StatusPublished
Cited by5 cases

This text of 41 So. 3d 315 (Trikon Sunrise Associates, LLC v. Brice Building Co.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trikon Sunrise Associates, LLC v. Brice Building Co., 41 So. 3d 315, 2010 Fla. App. LEXIS 10342, 2010 WL 2882434 (Fla. Ct. App. 2010).

Opinion

COX, JACK S., Associate Judge.

Trikon Sunrise Associates, LLC, appeals an Order of Final Summary Judgment in favor of the defendant, Mark L. Saltz. We reverse.

FACTS

Mark Saltz, individually, was sued for professional malpractice for architectural services performed while working for the architectural firm of Saltz Michelson Architects, Inc. The firm was also named as a separate defendant.

The Complaint alleges that L.A. Fitness entered into a written contract with Saltz Michelson Architects, Inc., for professional services during the construction of a fitness center to be built by a general contractor, known as Brice, on property owned by Trikon that was leased to L.A. Fitness.

On July 14, 2004, the architectural firm entered into its consulting agreement with L.A. Fitness, the tenant. The consulting agreement provided that the firm employs fully-qualified professional architects, and was unambiguous in describing the services to be performed by the architectural corporation through its individual qualified professional architects. Brice, the contractor, was not a party to this agreement, nor was the owner of the property or Mark Saltz, though Saltz signed the contract on behalf of the firm.

Almost a year later, on May 20, 2005, the tenant, L.A. Fitness, and the general contractor, Brice, entered into an AIA Document A107-119 Form Contract. The owner of the property was not a party to the contract, neither was the architectural firm or Saltz. It is alleged that the contract specifically provided that the contractor would be solely responsible for and have control over the construction means, methods, techniques, sequences and procedures, and for safety precautions and programs in connection with the work on the project and that the architect would not be responsible for the contractor’s failure to perform in accordance with the contract documents.

The contractor commenced construction on the fitness center on October 24, 2005, utilizing “tilt” wall or “tilt up” construction panels. Hurricane Wilma struck Florida while the process of constructing the walls was incomplete. The walls had been temporarily braced, but collapsed nonetheless. *317 The collapse of the walls caused the project to be delayed.

The owner of the property, Trikon, filed suit against the general contractor, architect, and engineer. In the Complaint, both Saltz Michelson Architects, Inc., and Mark Saltz were sued in separate counts for professional malpractice, asserting that they should have known that the temporary bracing was inadequate for hurricane force winds and that they breached a duty of care for failing to verify the details of the erection of the concrete panels, including the temporary bracing. Further, it was alleged that they failed to initiate a review and approval process of the erection details, including the temporary bracing, before allowing fabrication and erection of the panels to proceed, and failed to determine prior to erection whether the temporary bracing was sufficient to withstand wind and/or other forces likely to occur prior to completion.

The architectural firm and Mark Saltz filed a joint Motion for Summary Judgment, arguing that the firm and Saltz “never had the duty alleged to have been breached, by contract or otherwise.” The motion also argued that negligence may consist of either doing something that a reasonably careful architect would not do under like circumstances or failing to do something that a reasonably careful architect would do under like circumstances and that no contracting party has any obligation greater than as promised in its contract, citing Lochrane Engineering, Inc. v. Willingham Realgrowth Investment Fund, Ltd., 552 So.2d 228 (Fla. 5th DCA 1989).

In their Motion for Summary Judgment, various portions of the owner’s Complaint were referenced; among those allegations were the following:

34.ARCHITECT agreed to provide its professional services with regard to design, planning and supervision of the construction of the FITNESS CENTER.
35. ARCHITECT knew or should have known that high winds and/or adverse weather conditions specifically associated with Hurricane Wilma would exist at the PROJECT on or about October 24, 2005.
36. ARCHITECT knew or should have known that the temporary bracing in place for the concrete panels was significantly inadequate for hurricane force winds.
37. ARCHITECT knew or should have known that if the concreted panels erected by BRICE collapsed then, thereafter, the resulting demolition and re-construction would significantly delay and impair TRIKON’s development activities.
38. ARCHITECT had a duty to exercise a degree of care and skill in the design, planning and supervision of the construction of the FITNESS CENTER as would be exercised by other reasonably skilled architects practicing in the South Florida area under the same or similar circumstances.
39. ARCHITECT breached its duty for reasons including but not limited to: (1) failing to exercise that degree of care and skill as would be exercised by other reasonably skilled architects practicing in the South Florida area under the same or similar circumstances; (2) failing to verify or ascertain that the details of the erection of the concrete panels, including the temporary bracing, were prepared and sealed by a registered engineer; (3) failing to initiate a review and approval process of erection details, including the temporary bracing, before allowing fabrication and erection of the concrete panels to proceed; and (4) failing to determine, prior to erection of the *318 concrete panels, whether the temporary bracing system which was utilized was sufficient to withstand or otherwise protect against wind and other forces that were likely to occur until connections to the permanent structural system were completed.

The trial court denied the architectural firm’s Motion for Summary Judgment, but granted Summary Judgment in favor of Saltz.

ANALYSIS

A professional duty may arise in favor of a third party as a result of a matter of law or as a result of a contract between parties, or by virtue of a gratuitous undertaking. In this case, the architectural corporation and the individual architect allegedly had duties imposed upon them and those allegations are supported by Florida Statute and also because of the contract scope of work.

Chapter 481, Florida Statutes (2005), “Architecture and Interior Design,” describes the services and responsibilities of an “Architect,” which specifically include services of “planning, providing preliminary study designs, drawings and specifications, job-site inspection, and administration of construction contracts.” § 481.203(6), Fla. Stat. (2005).

Chapter 471, Florida Statutes (2005), “Engineering,” describes the services of an “Engineer,” including the engineer’s responsibility for inspection of the construction and the services provided involved in safeguarding life, health, and property. § 471.005(7), Fla. Stat. (2005).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GRACE & NAEEM UDDIN, INC. v. SINGER ARCHITECTS, INC.
District Court of Appeal of Florida, 2019
School Board of Broward County v. Pierce Goodwin Alexander & Linville
137 So. 3d 1059 (District Court of Appeal of Florida, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
41 So. 3d 315, 2010 Fla. App. LEXIS 10342, 2010 WL 2882434, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trikon-sunrise-associates-llc-v-brice-building-co-fladistctapp-2010.