Loenco v. Londonderry

CourtDistrict Court, D. New Hampshire
DecidedSeptember 27, 1996
DocketCV-95-455-M
StatusPublished

This text of Loenco v. Londonderry (Loenco v. Londonderry) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Loenco v. Londonderry, (D.N.H. 1996).

Opinion

Loenco v . Londonderry CV-95-455-M 09/27/96 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Loenco, Inc., Plaintiff, v. Civil N o . 95-455-M Town of Londonderry, Board of Sewer Commissioners; Hoyle, Tanner & Associates, Inc.; and Pace Industries, Inc., Defendants.

O R D E R

This action arises from the construction of a wastewater

pumping station in Londonderry, New Hampshire. The contractor,

Loenco, Inc., seeks contract and tort damages from the Town of

Londonderry (the owner); Hoyle, Tanner, & Associates, Inc. (the

project engineers); and Pace Industries, Inc. (a subengineer and

equipment supplier). Pace Industries moves to dismiss

plaintiff's negligent breach of contract,1 third-party

beneficiary, and breach of contract claims. For the reasons

discussed below, Pace's motions to dismiss is granted in part and

denied in part.

1 Plaintiff concedes that New Hampshire does not recognize a cause of action for "negligent breach of contract" and has voluntarily withdrawn that claim. I. Background

In April 1992, the Town of Londonderry ("Londonderry")

launched plans to build a wastewater pumping station.

Londonderry hired Hoyle, Tanner & Associates, Inc. ("Hoyle"), an

engineering firm, to prepare plans and specifications for the construction of the pumping station. Hoyle in turn retained Pace

Industries, Inc. ("Pace") to draft specifications for the pumping

equipment. Specifically, Pace was to determine the size and

style of pump motors and related equipment required to properly

operate the pumping station.

On May 2 , 1993, Londonderry advertised for construction

bids. After studying the plans and specifications provided by

Hoyle to Londonderry, plaintiff submitted the successful bid, and

was awarded the contract to build the pumping station. The terms

of the contract required plaintiff to construct the pumping

station in accordance with the plans and specifications, and to

complete the project by August 1994. In a separate transaction,

plaintiff contracted with Pace to provide plaintiff with the pump

equipment necessary to complete the job.

Plaintiff began construction on August 9, 1993.

Construction went smoothly until late June 1994, when plaintiff

apparently discovered a problem with the specifications for the

2 pumping equipment. Delays ensued and the construction was not

completed by August 1994, the contract deadline. Claiming a

breach by plaintiff, Londonderry terminated the contract.

II. Standard of Review

A motion to dismiss under Fed. R. Civ. P. 12(b)(6) is one of

limited inquiry, focusing not on "whether a plaintiff will

ultimately prevail but whether the claimant is entitled to offer

evidence to support the claims." Scheuer v . Rhodes, 416 U.S.

232, 236 (1974). In considering a motion to dismiss, "the

material facts alleged in the complaint are to be construed in

the light most favorable to the plaintiff and taken as admitted,

with dismissal to be ordered only if the plaintiff is not

entitled to relief under any set of facts he could prove."

Chasan v . Village Dist. of Eastman, 572 F.Supp. 5 7 8 , 579 (D.N.H.

1983), aff'd without opinion, 745 F.2d 43 (1st Cir. 1984) (citations omitted). 2

2 Both plaintiff and Pace have attached documents to their memoranda. In all other respects, however, both parties have treated the pending motion as a motion to dismiss pursuant to Fed. R. Civ. P. 12(b)(6). The limited inquiry under Rule 12 ordinarily forbids any consideration of documents not attached to the complaint, or not expressly incorporated therein unless the proceeding is converted into one for summary judgment under Rule 5 6 . See Fed. R. Civ. P. 12(b)(6). The decision to convert the proceeding into one for summary judgment and to consider 3 III. Discussion A. Count IX Third-Party Beneficiary

Although plaintiff captions Count IX of its complaint,

"Third-Party Beneficiary," it appears that plaintiff is actually

attempting to plead two separate causes of action - a third-party beneficiary contract claim and a negligence claim. For the

purposes of this motion, the court will address each claim

separately.

1. Contract

First, plaintiff contends that as the builder of the pumping station, it was expected to rely on the plans and specifications prepared by Hoyle and Pace, and, as such, it was a third-party beneficiary of the Hoyle/Pace contract. Plaintiff argues that Pace breached that contract by providing defective specifications.

Under New Hampshire law, a third-party beneficiary relationship exists i f : (1) the contract calls for performance

extrinsic materials rests with the court's discretion. Watterson v . Page, 987 F.2d 1 , 3-4 (1st Cir. 1993). The court elects to exclude matters outside the pleadings rather than provide the parties with an opportunity to present at this time all materials made pertinent to such motions by Fed. R. Civ. P. 5 6 , and declines to convert the motions to dismiss into motions for summary judgment.

4 by the promisor which will satisfy some obligation owed by the

promisee to the third party; or (2) the contract is so expressed

as to give the promisor reason to know that a benefit to a third

party is contemplated by the promisee as one of the motivating

causes of his making the contract. Tamposi Assoc., Inc. v . Star

Market Co., Inc., 119 N.H. 6 3 0 , 631 (1979). A plaintiff who

merely receives a pecuniary benefit from a contract is not a

third-party beneficiary, but an incidental beneficiary, with no

enforceable rights under the contract. Arlington Trust C o . v .

Estate of Wood, 123 N.H. 765, 768 (1983).

Plaintiff does not allege that the Hoyle/Pace contract

required some performance by Pace that would satisfy some

obligation owed by Hoyle to plaintiff. Rather, plaintiff argues

that its relationship to the Hoyle/Pace contract satisfies the

second, alternative test — that Hoyle and Pace contracted with

the specific intent of making plaintiff a third-party

beneficiary. The argument is not persuasive.

Although plaintiff could not construct the pumping station

without Pace's specifications, it is not evident that Hoyle and

Pace contracted with the intent of making plaintiff a third-party

beneficiary. Under its contract with Hoyle, Pace could complete

its promised performance (providing pump equipment specifications

5 to Hoyle) without conferring or intending to confer any benefit

on plaintiff. There is no clear language indicating that Hoyle

and Pace contemplated benefitting plaintiff, rather it is clear

that Hoyle contracted with Pace to enable Hoyle to perform under

its contract with Londonderry. Thus, any benefit that plaintiff

received from the Hoyle/Pace contract must be regarded as merely

incidental.

Moreover, plaintiff's argument that it relied upon the

specifications that resulted from the Hoyle/Pace contract and is

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Savings Bank v. Ward
100 U.S. 195 (Supreme Court, 1880)
Scheuer v. Rhodes
416 U.S. 232 (Supreme Court, 1974)
Valerie Watterson v. Eileen Page
987 F.2d 1 (First Circuit, 1993)
Berkel & Co. Contractors v. Providence Hosp.
454 So. 2d 496 (Supreme Court of Alabama, 1984)
Davidson & Jones, Inc. v. County of New Hanover
255 S.E.2d 580 (Court of Appeals of North Carolina, 1979)
Donnelly Const. Co. v. Oberg/Hunt/Gilleland
677 P.2d 1292 (Arizona Supreme Court, 1984)
Keene Lumber Co. v. Leventhal
165 F.2d 815 (First Circuit, 1948)
Thomson v. Espey Huston & Associates, Inc.
899 S.W.2d 415 (Court of Appeals of Texas, 1995)
Arlington Trust Co. v. Estate of Wood
465 A.2d 917 (Supreme Court of New Hampshire, 1983)
Gurtler, Hebert & Co. v. Weyland MacH. Shop, Inc.
405 So. 2d 660 (Louisiana Court of Appeal, 1981)
Carroll-Boone Water District v. M. & P. Equipment Co.
661 S.W.2d 345 (Supreme Court of Arkansas, 1983)
Normoyle-Berg & Associates, Inc. v. Village of Deer Creek
350 N.E.2d 559 (Appellate Court of Illinois, 1976)
Craig v. Everett M. Brooks Co.
222 N.E.2d 752 (Massachusetts Supreme Judicial Court, 1967)
R. C. Allen Business MacHines, Inc. v. Acres
281 A.2d 162 (Supreme Court of New Hampshire, 1971)
Guardian Construction Co. v. Tetra Tech Richardson, Inc.
583 A.2d 1378 (Superior Court of Delaware, 1990)
Conforti & Eisele, Inc. v. John C. Morris Assocs.
418 A.2d 1290 (New Jersey Superior Court App Division, 1980)
Owen v. Dodd
431 F. Supp. 1239 (N.D. Mississippi, 1977)
Forte Bros. v. National Amusements, Inc.
525 A.2d 1301 (Supreme Court of Rhode Island, 1987)
Rollins v. Rollins
440 A.2d 438 (Supreme Court of New Hampshire, 1982)
United States v. Rogers & Rogers
161 F. Supp. 132 (S.D. California, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
Loenco v. Londonderry, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loenco-v-londonderry-nhd-1996.