National Steel Erection, Inc. v. J.A. Jones Construction Co.

899 F. Supp. 268, 1995 U.S. Dist. LEXIS 18851, 1995 WL 561806
CourtDistrict Court, N.D. West Virginia
DecidedSeptember 20, 1995
Docket2:94-cv-00225
StatusPublished
Cited by5 cases

This text of 899 F. Supp. 268 (National Steel Erection, Inc. v. J.A. Jones Construction Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Steel Erection, Inc. v. J.A. Jones Construction Co., 899 F. Supp. 268, 1995 U.S. Dist. LEXIS 18851, 1995 WL 561806 (N.D.W. Va. 1995).

Opinion

ORDER

KEELEY, District Judge.

I.

This dispute, arising from a construction project at Virginia Electric and Power Company’s (“VEPCO”) Mt. Storm plant, requires this Court to decide whether a subcontractor may sue another contractor for economic damages where there is no privity of contract between the parties. The plaintiff, subcontractor National Steel Erection (“NSE”), incurred significant economic loss due to cost overruns and delays allegedly due to the negligent design and project administration of defendant General Electric Environmental Services, Inc. (“GEESI”). In this action, NSE seeks to recover from GEESI and also from defendant J.A. Jones Construction Co. (“Jones”), the construction manager with whom NSE had contracted to perform certain work at the Mt. Storm plant. The parties do not dispute the relevant facts giving rise to this suit.

*270 On May 15, 1991, defendant GEESI and Jones entered into a blanket consortium agreement (“GEESI/Jones Contract”) for the purpose of jointly securing the Mt. Storm construction contract. GEESI agreed to serve as the overall project supervisor, with Jones managing the details of the construction work. See GEESI/Jones Contract Part 7.3.3. Pursuant to the GEESI/Jones contract, GEESI would contract with VEPCO and Jones would subcontract with third parties. 1

GEESI and Jones recognized the unique nature of their relationship and, in an effort to minimize the possibility of internal disputes concerning potential liability to third parties, inserted the following indemnification provisions into the GEESI/Jones contract:

9.1LIABILITY AND INDEMNIFICATION WITH RESPECT TO CLAIMS OF THE CUSTOMER AND THIRD PARTIES
9.1.1 It is the express intention of this AGREEMENT that each PARTY’S responsibility and liability be limited to its respective SCOPE OF WORK for each PROJECT. Therefore, except as expressly provided otherwise herein, the PARTIES agree to indemnify one another as follows: Each PARTY (Indemnifying PARTY) agrees to indemnify and hold the other PARTY (Indemnified PARTY) harmless from any claim made against the Indemnified PARTY by ... other THIRD PARTIES to the degree that such claim arises in connection with said Indemnifying PARTY’S SCOPE OF WORK, for any breach or default of this AGREEMENT or each CONTRACT or is due to the Indemnifying PARTY’S fault or negligence.

Part 9.1.2 further states:

9.1.2 Except as provided otherwise herein, in the event that claims are made by ... THIRD PARTIES and the PARTIES fail to agree as to which PARTY is responsible for such fault or negligence on a PROJECT, liability will be provisionally borne by the PARTY designated by the LEADER pending resolution pursuant to the provisions of Part 10.

Subsequent to the execution of the GEE-SI/Jones contract, VEPCO awarded GEESI the Mt. Storm contract. Thereafter, Jones entered into three subcontracts with NSE: (1) one for the fabrication and erection of carbon steel tanks (“tank contract”); (2) one for the installation of high nickel alloy liners (“lining contract”); and (3) one for the subas-sembly and erection of necessary duct work (“duct contract”). 2 Each of these documents explicitly recognized the managerial structure created in the GEESI/Jones contract. 3 Furthermore, NSE agreed to perform its work in accordance with the general provisions and drawings provided by “the architect, engineer, or other comparable person designated as [VEPCO’s] representative” and also promised to accept reasonable design modifications of existing specifications, provided Jones compensated it for these changes. (See Articles 8 and 10 as amended by Schedule E.)

NSE contends that, after the execution of these subcontracts, Jones enlarged its scope of work, altered the time of completion and “otherwise interfered with, disrupted and hindered NSE’s performance of its contracts, thereby increasing the cost and expense to NSE.” NSE also alleges that Jones failed to provide adequate plans and specifications, failed to adjust the contract price to reflect design modifications and failed to timely deliver necessary materials. NSE contends that, as a result of the foregoing actions, Jones breached the express and implied terms of the subcontracts.

*271 In addition to its claim for breach of contract against Jones, NSE claims, in Counts II, III, and V of the complaint, that certain plans and specifications prepared by GEESI negligently misrepresented the work to be performed by NSE. NSE further claims in Count VI that GEESI fraudulently induced NSE to enter into the lining contract. GEESI contests the validity of NSE’s claims and argues that NSE cannot recover economic damages in negligence and, further, has failed to state a claim for fraud. 4 The matter is now before the Court on GEESI’s motion for summary judgment. 5

II.

Summary judgment is appropriate “if there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). When a moving party supports its motion under Rule 56 with affidavits and other appropriate materials pursuant to the rule, the opposing party “may not rest upon the mere allegations or denials of the adverse party’s pleadings, but ... the response ... by affidavits or as otherwise provided in this rule, must set forth specific facts showing that there is a genuine issue for trial.” Fed.R.Civ.P. 56(e). Summary judgment is proper “[wjhere the record taken as a whole could not lead a rational trier of fact to find for the non-moving party, there [being] no genuine issue for trial.” Matsushita Electric Industrial Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 1356, 89 L.Ed.2d 538 (1986) (quotation omitted).

III.

Counts II, III and V of NSE’s complaint allege that GEESI is liable for its negligent performance as the “project designer who produced the [c]ontract plans and specifications” for the Mt. Storm site. 6 NSE contends that GEESI had a duty to provide it with correct information and, having assumed this duty, should have known that NSE would rely on its representations; therefore, pursuant to Section 552 of the Restatement Seoond of ToRts (Section 552), 7 GEESI is responsible for its economic damages. In its motion to dismiss, GEESI argues that NSE cannot recover economic losses from a party with whom it had no contractual relationship.

Both NSE and GEESI agree that the West Virginia Supreme Court of Appeals has not specifically addressed the question of whether Section 552 would apply to disputes in the construction industry.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alejandre v. Bull
153 P.3d 864 (Washington Supreme Court, 2007)
Eastern Steel Constructors, Inc. v. City of Salem
549 S.E.2d 266 (West Virginia Supreme Court, 2001)
Sebago, Inc. v. Beazer East, Inc.
18 F. Supp. 2d 70 (D. Massachusetts, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
899 F. Supp. 268, 1995 U.S. Dist. LEXIS 18851, 1995 WL 561806, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-steel-erection-inc-v-ja-jones-construction-co-wvnd-1995.