Bacco Construction Co. v. American Colloid Co.

384 N.W.2d 427, 148 Mich. App. 397
Michigan Court of Appeals·Decided January 21, 1986·No. Docket 82943·Published·Cited by 24 cases

Opinion

Shepherd, J.

Plaintiff, Bacco Construction Company, commenced this action against defendants on September 20, 1982, seeking to recover the costs it incurred in repairing a waste water treatment lagoon system it had constructed for Houghton County. Plaintiff appeals as of right from a January 15, 1985, order granting accelerated judgment in favor of defendants American Colloid Company, D. J. Moriva Company, Inc., and Don Moriva, and granting both accelerated and summary judgment in favor of defendant McNamee, Porter & Seeley (MPS). We reverse the trial *402 court’s order granting accelerated judgment and summary judgment in favor of defendants, except as to that part of the order regarding plaintiffs implied warranty claim against Colloid and Moriva Company which is barred by a statute of limitations.

Plaintiffs complaint provides the following description of the events leading to this lawsuit. Plaintiff was the general contractor on a project to construct a waste water lagoon and irrigation system in Houghton County. MPS was employed by the county as the project engineer. Plaintiff, as the low bidder on the project, entered into a contract with the County of Houghton. The contract provided various specifications for the project including that the lagoons were to be constructed with a seal using either clay, powdered bentonite, or a combination of clay and bentonite.

Prior to the letting of the project on December 14, 1977, Colloid indicated an interest in supplying bentonite materials for use in providing the seal for the lagoons. Following discussions among the various parties, on August 8, 1978, MPS issued a contract change order which provided that the seal on the lagoons would be changed from specifications known as GS 50 to SG 40. SG 40 is a Volclay bentonite product manufactured by Colloid.

Plaintiff alleged that it applied the material in the lagoons in accordance with provisions of the contract, and in the presence or under the observation of representatives of MPS, Colloid and Moriva Company. (Although Moriva Company’s relationship to the project is not entirely clear, it appears that it acted with Colloid in selling the bentonite product.) After the installation of the material, tests were performed to determine the exfiltration rates of the lagoons, and, thereafter, it appeared that the lagoons failed to meet the standards *403 contained in the specifications. The county, with the approval and at the direction of its engineers, MPS, suspended and withheld payments to plaintiff for work done on the project. The county notified plaintiff of an "extensive leak” in a letter dated July 17, 1979. On October 15, 1979, the county, through MPS, formally rejected the work done by plaintiff for not meeting contract specifications.

Discussions were then held among the county, plaintiff and the defendants to determine responsibility for the leakage of the lagoons and the most appropriate method for correcting the problem. Since all parties denied liability, plaintiff and all defendants determined that it would be in their best interests to correct the leakage problem, thereby eliminating the county from the controversy, but without admitting responsibility among themselves. Accordingly, in an agreement dated September 30, 1981, plaintiff, MPS and Colloid agreed to perform corrective work on the lagoons. Although MPS and Colloid shared in bearing the costs of the corrective work, plaintiff expended most of the funds. In paragraph 4 of the agreement, the parties, though agreeing to participate in the corrective work, stated that none of them admitted liability for the lagoon problem and that the corrective work would be accomplished with the parties reserving the right to later litigate or arbitrate the matter, including the questions of how the responsibility and costs for the repair of the lagoons would ultimately be divided.

Plaintiff commenced this action on September 20, 1982, after the corrective work had been completed and the parties became unable to agree on responsibility for the lagoon leakage. The complaint contains eleven counts: Count I — based on the repair agreement itself and against all of the *404 defendants; Count II — breach of express and implied warranty claim against Colloid and Moriva Company; Count III — negligence claim against Colloid; Count IV — negligence claim against Moriva Company; Count V — negligence claim against MPS; Count VI — negligence claim against Don Moriva; Count VII — common law indemnity claim against all defendants; Count VIII — implied contract of indemnity claim against all defendants; Count IX — restitution and unjust enrichment claim against all defendants; Count X — negligent misrepresentation claim against Colloid, MPS and Moriva Company; Count XI — contribution claim against all defendants.

The trial court, in an opinion dated August 8, 1984, held with respect to Colloid, Moriva Company and Don Moriva that plaintiffs negligence claims accrued on July 12, 1979, and were barred by the expiration of the three-year period of limitation. The court further ruled that the warranty count had expired on August 14, 1982, four years after the bentonite product was delivered to plaintiff. On this basis and without specifically ruling on the effect of the statute of limitations on Counts I, VII, VIII, IX and XI, the court granted accelerated judgment in favor of these defendants on plaintiffs entire complaint. In a subsequent opinion dated December 11, 1984, the court held with respect to defendant MPS that expiration of the two-year period of limitation for professional malpractice barred plaintiffs claims and that, in addition, plaintiffs negligence claim was barred by summary judgment for the reason that MPS owed no duty to plaintiff. This opinion too neglects to mention Counts I, VII, VIII, IX, and XI of plaintiff’s complaint.

*405 I

Count I

In Count I of its complaint, plaintiff sought recovery under the September, 1981, agreement among the parties to repair the lagoons. Plaintiff alleged that the parties agreed to determine who was responsible for the project’s failure and to reimburse costs accordingly. Similarly plaintiff argues on appeal that the parties "intended to be bound to determine, at some date after the lagoon repairs had been completed, by process of arbitration, litigation or otherwise, the merits of their dispute, i.e., who caused the failure of the lagoons and, based on that, by whom and in what proportion the costs should ultimately be borne”. (Emphasis in original.)

Paragraph 4 of the agreement provides:

"4. Reservation of Rights.

Free access — add to your briefcase to read the full text and ask questions with AI

Bacco Construction Co. v. American Colloid Co., 384 N.W.2d 427, 148 Mich. App. 397 (Mich. Ct. App. 1986).

384 N.W.2d 427 (Bacco Construction Co. v. American Colloid Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Eastern Steel Constructors, Inc. v. City of Salem
549 S.E.2d 266 (West Virginia Supreme Court, 2001)
Tommy L. Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc.
463 S.E.2d 85 (Supreme Court of South Carolina, 1995)
Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc.
463 S.E.2d 85 (Supreme Court of South Carolina, 1995)
National Steel Erection, Inc. v. J.A. Jones Construction Co.
899 F. Supp. 268 (N.D. West Virginia, 1995)
Enzymes of America, Inc v. Deloitte, Haskins & Sells
523 N.W.2d 810 (Michigan Court of Appeals, 1994)
Jim's Excavating Service, Inc. v. HKM Associates
878 P.2d 248 (Montana Supreme Court, 1994)
LOCAL 1064, RWDSU AFL-CIO v. Ernst & Young
516 N.W.2d 492 (Michigan Court of Appeals, 1994)
Mid-Western Electric, Inc. v. DeWild Grant Reckert & Associates Co.
500 N.W.2d 250 (South Dakota Supreme Court, 1993)
John Martin Co. v. Morse/Diesel, Inc.
819 S.W.2d 428 (Tennessee Supreme Court, 1991)
Atlantis Group, Inc. v. Rospatch Corp.
760 F. Supp. 1239 (W.D. Michigan, 1991)
In Re Rospatch Securities Litigation
760 F. Supp. 1239 (W.D. Michigan, 1991)
National Sand, Inc v. Nagel Construction, Inc
451 N.W.2d 618 (Michigan Court of Appeals, 1990)
Law Offices of Lawrence J Stockler, PC v. Rose
436 N.W.2d 70 (Michigan Court of Appeals, 1989)
BLUE CROSS AND SHIELD OF MICH. v. Folkema
436 N.W.2d 670 (Michigan Court of Appeals, 1988)