Southgate Community School District v. West Side Construction Co.

247 N.W.2d 884, 399 Mich. 72, 20 U.C.C. Rep. Serv. (West) 1202, 1976 Mich. LEXIS 207
Michigan Supreme Court·Decided December 27, 1976·No. 57484, (Calendar No. 3)·Published·Cited by 41 cases

Opinions

Fitzgerald, J.

This is a products liability action by which plaintiff, not in privity of contract with defendant manufacturer, seeks to recover on an implied-warranty theory the cost of maintenance, repair and ultimate replacement of an allegedly defective product. There was no personal injury involved, nor was there any damage claimed for injury to property other than deterioration of the product itself.1 The trial court granted defendant’s motion for accelerated judgment on the grounds that plaintiff’s action was time-barred by UCC § 2-[76]*76725.2 The Court of Appeals affirmed at 63 Mich App 634; 234 NW2d 738 (1975). The question on appeal is whether the correct statute of limitations was applied by the courts below.

I

On March 6, 1967, plaintiff-appellant Southgate Community School District entered into an agreement with West Side Construction Company, also a defendant herein, for the building of a new elementary school. Part of the agreement included the construction of concrete slab floors, upon which West Side was to supply and lay resilient tiles. West Side’s performance bond was executed by defendant Reliance Insurance Company as insurer.

The tiles selected by West Side were manufactured by defendant-appellee Kentile Floors, Inc. There was no direct relationship between South-gate and defendant Kentile. At some unidentified time, the tiles were purchased from Kentile by Advance Floor Coverings, Inc, from whom they were acquired by West Side or its subcontractor.

Based on plaintiffs requests for admissions, it appears that "West Side completed installation of the tiles on or about October 31, 1967”, and that "exudations between the tiles appeared first, and [77]*77certain of the tiles became loosened * * * within one week after West Side completed installation of the tiles”. It is further evident from plaintiffs requests for admissions that classroom number 9 of the school evidenced some tile adhesion failure on or before July 1, 1968. On January 20, 1969, plaintiffs architect wrote to West Side as follows:

"Please be advised that the resilient floor installation has continued to fail and it is now apparent that many areas of flooring will have to be replaced under the terms of the guarantee against defects in material or installation.
"It is becoming increasingly apparent that defective Kentile materials, mastic adhesive, or tile were incorporated in the work or improper methods or procedure were employed in the installation of the floor covering.
"You are hereby notified that, unless other causes for failure are established, beyond a reasonable doubt, the floor covering must be replaced under the terms of the guarantee against defective labor and material. This guarantee extends also to your sub-contractor, Davis Floor Company, and to the manufacturer of the material, Kentile.
"We will cooperate in any way to expedite correction of this problem and assist in determining the cause of failure and best method for correction.”

The letter, marked exhibit D, was attached to plaintiffs complaint which was filed September 14, 1973. The complaint alleged, inter alia, that the tiles were defective and sought recovery for increased maintenance costs at the school necessary to remove exudations as they appeared between the tiles in the amount of $25,000, and an additional $25,000 for tile replacement. The action was brought against West Side and its surety, Reliance, on the construction agreement, and against Ken-[78]*78tile for its products liability as manufacturer of the tiles.

Our inquiry herein concerns only the propriety of the accelerated judgment under GCR 1963, 116.1(5) (statute of limitations) entered by the trial court against plaintiff Southgate and in favor of defendant Kentile.

II

The manufacturer’s duty to the consumer with regard to products which it puts into the stream of commerce does not generally arise out of a contract for sale, and is therefore not limited by the UCC:

"While some of the concepts (e.g., implied warranty) developed by the courts in creating the consumer’s right of direct action against the manufacturer have been enacted into statute, the UCC draftsmen have acknowledged that the consumer’s remedy is not statutory, but essentially a judicial development which the courts should be free to develop further. The UCC did not create a new and separate consumer’s product liability claim against the manufacturer.”3

By its terms, UCC § 2-725 applies only to an "action for breach of any contract for sale”, and was not meant to apply to actions between consumers and manufacturers who were never in any commercial relationship or setting. For example, the parties to the contract may agree under UCC § 2-725(1) to reduce the limitations period to not less than one year, but such an agreement could not bind one not privy to the parties’ agreement and whose cause of action does not arise therefrom. Furthermore, under subsection 2, a cause of [79]*79action for breach generally accrues when tender of delivery is made. If applicable to the consumer’s products liability action against a remote manufacturer, the statute could run before all elements of plaintiffs claim were present.4 For these reasons, we hold that application by the lower courts of UCC § 2-725 to bar plaintiffs action was error.

Ill

The question becomes whether plaintiff seeks "to recover damages for injuries to * * * property”5 or whether its suit fits within the catch-all statute governing "[all] other personal actions.”6

Plaintiff argues that the three-year injury-to-property statute does not apply because no damage occurred to property other than the product itself. Plaintiff further argues that the word "injuries” is used in the statute to describe a physical event:

"Thus, to fall within the statute, the damages sought must be attributable to 'injury’, in some physical sense, to specific property. The phrase 'injuries to property’ implies that the 'property’, prior to and but for the consequence of some cause external to itself, attributable to the defendant, was, and would have remained, in an unaltered state; that some cause external to the 'property’ itself has caused a physical change in the 'property’.”7

Plaintiffs complaint, however, alleges the follow[80]*80ing: that water-soluble chemicals contained in the tiles "caused the degradation of the mastic adhering the tiles to the slabs, destruction of the adhesion bond and contraction of the tiles”; further, that these chemicals caused the "formation of exudations along the joints between the tiles, contraction of the tiles, and raising and destruction of the tiles”.

Metaphysics aside, no one entering the Howard D. Allen Elementary School, upon physically confronting such a loose, cracked and oozing floor and being informed of the alleged cause, could seriously question that plaintiffs had been injured in its property. Although the tiles and the mastic were the manufacturer’s product, they nevertheless had become plaintiff’s property.

Plaintiff argues that this case is controlled by

Free access — add to your briefcase to read the full text and ask questions with AI

Southgate Community School District v. West Side Construction Co., 247 N.W.2d 884, 399 Mich. 72, 20 U.C.C. Rep. Serv. (West) 1202, 1976 Mich. LEXIS 207 (Mich. 1976).

247 N.W.2d 884 (Southgate Community School District v. West Side Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Patricia Wendel v. Ford Motor Company
Michigan Court of Appeals, 2024
Simonet v. SmithKline Beecham Corp.
506 F. Supp. 2d 77 (D. Puerto Rico, 2007)
Trentadue v. Buckler Automatic Lawn Sprinkler Company
479 Mich. 378 (Michigan Supreme Court, 2007)
Pack v. Damon Corp
Sixth Circuit, 2006
Frankenmuth Mutual Insurance v. Ace Hardware Corp.
899 F. Supp. 348 (W.D. Michigan, 1995)
Garden City Osteopathic Hospital v. Hbe Corporation
55 F.3d 1126 (Sixth Circuit, 1995)
Garden City Osteopathic Hospital v. HBE Corp.
55 F.3d 1126 (Sixth Circuit, 1995)
Michigan Mutual Insurance v. Osram Sylvania, Inc.
897 F. Supp. 992 (W.D. Michigan, 1995)
Chase v. Sabin
516 N.W.2d 60 (Michigan Supreme Court, 1994)
Neibarger v. Universal Coopertives, Inc.
486 N.W.2d 612 (Michigan Supreme Court, 1992)
Rust-Pruf Corp. v. Ford Motor Co.
431 N.W.2d 245 (Michigan Court of Appeals, 1988)
Larson v. Johns-Manville Sales Corp.
399 N.W.2d 1 (Michigan Supreme Court, 1986)
Bacco Construction Co. v. American Colloid Co.
384 N.W.2d 427 (Michigan Court of Appeals, 1986)
Heller v. U. S. Suzuki Motor Corp.
477 N.E.2d 434 (New York Court of Appeals, 1985)
Sylla v. Massey-Ferguson, Inc.
660 F. Supp. 1044 (E.D. Michigan, 1984)
Filcek v. Utica Building Co.
345 N.W.2d 707 (Michigan Court of Appeals, 1984)