Gilbane Building Co. v. Nemours Foundation

666 F. Supp. 649, 1985 U.S. Dist. LEXIS 23122
CourtDistrict Court, D. Delaware
DecidedJanuary 25, 1985
DocketCiv. A. 83-58-WKS
StatusPublished
Cited by4 cases

This text of 666 F. Supp. 649 (Gilbane Building Co. v. Nemours Foundation) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gilbane Building Co. v. Nemours Foundation, 666 F. Supp. 649, 1985 U.S. Dist. LEXIS 23122 (D. Del. 1985).

Opinion

*651 OPINION

STAPLETON, Chief Judge:

DiSabatino & Sons, Inc. (“DiSabatino”), brought suit against The Nemours Foundation (“Nemours”) on February 2, 1983, seeking to recover damages allegedly incurred by DiSabatino as a result of Nem-ours’ alleged breaches of a construction contract (“the Contract”), and as a result of Nemours’ alleged failure to exercise reasonable care with respect to DiSabatino’s contract performance. (Civil Action No. 83-58). The dispute between these parties arises out of the performance by DiSabati-no of construction work for Nemours on the Alfred I. duPont Hospital construction project (“the Project”) in Wilmington, Delaware.

BACKGROUND

DiSabatino was one of several prime contractors involved in the construction of this sophisticated hospital project. Subsequent litigation developed between and among Nemours and another of the prime contractors on the Project, Gilbane Building Company (“Gilbane”), two of Gilbane’s subcontractors, Pierce Associates, Inc. (“Pierce”) and Dynalectric Company (“Dynalectric”), Nemours’ project architect, Saxelbye, Powell, Roberts & Ponder, Inc. (“the Architect”) and the Architect’s engineering firm, Furlow Associates (“the Engineer”). In addition, litigation recently was initiated by Honeywell, Inc. (“Honeywell”), also a subcontractor of Gilbane, against Gilbane and H.B. Frazer Company (“Frazer”), a subcontractor to Honeywell. These pending lawsuits have been consolidated for trial.

In response to DiSabatino’s claim, Nem-ours counterclaimed against DiSabatino for liquidated damages as provided for in the Contract in the event DiSabatino did not substantially complete its work by the contractually mandated completion date, as well as for indemnification against any actual losses which Nemours might incur as a result of claims made against it by the other contractors on the Project. It appears that the claims advanced against Nemours by Gilbane, Pierce, and Dynalec-tric are based on allegations that DiSabati-no actively interfered with the contemporaneous and follow-on activities of Gilbane, Pierce and Dynalectric on allegations that DiSabatino’s failure to meet its deadline increased the cost of those follow-on activities. Although DiSabatino and Nemours dispute the potential amount of the liquidated damages recoverable by Nemours, those liquidated damages are approximately $222,500. The claims made against Nemours by the other contractors on this project, and for which Nemours seeks indemnity from DiSabatino, are believed to exceed $15,000,000.

By this motion, DiSabatino seeks partial summary judgment limiting its liability, if any, to the liquidated damages provided for in the Contract. Nemours asks the Court to. declare that the Contract provided for the liquidation of some, but not all, of the damages flowing from DiSabatino’s alleged contract breaches and negligence pertaining to the Project.

THE CONTRACT

Nemours and DiSabatino entered into the Contract on May 14, 1979. It provided for the construction of Phase 5EXT of the Project. The hospital was being constructed in phases. Phase 5EXT was scheduled to follow Phases 1, 2, 3, 4 and 5A, and to precede the final phase, Phase 5B. Each phase was to be performed by a separate prime contractor. The principal work involved in Phase 5EXT was enclosing the building by erecting large blocks of limestone on the exterior of the structural steel framework and by installing windows and doors where appropriate around the structure. Under the terms of the Contract, DiSabatino was obligated to supply all the material needed to complete Phase 5EXT except the limestone. The limestone was to be supplied by Nemours.

Article 3 of the Contract required that DiSabatino substantially complete Phase 5EXT no later than December 20,1980, and provided for liquidated damages in the amount of $500 for each day’s delay in completing the work beyond that date. Article 3 of the Contract reads in full:

*652 The work to be performed under this Contract shall be commenced within ten (10) days and, subject to authorized adjustments, Substantial Completion shall be achieved not later than 20 December 1980. LIQUIDATED DAMAGES SHALL BE AS FOLLOWS: Five hundred dollars ($500) per consecutive calendar day for each day’s delay in completing the work under this contract, beyond 20 December 1980.

This liquidated damages agreement between DiSabatino and Nemours is also referred to in the Special Conditions of the Contract. Paragraph 1.25A of these Special Conditions, entitled “Liquidated Damages,” provides:

In case of failure on the part of the Contractor to complete the work within the time fixed in the contract or or (sic) any extensions thereof, the Contractor shall pay to the Owner, as fixed, agreed and liquidated damages, the sum of five hundred dollars ($500) for each calendar day of delay.

While there is disagreement between the parties as to the exact date of substantial completion, it is agreed that it was not achieved until more than a year after December 20, 1980.

DISCUSSION

Where damages are uncertain and the amount agreed upon is reasonable, the parties to a contract may agree to liquidated damages to be paid upon breach of the contract. See, e.g., Countywide Realty Corp. v. Albani, 420 A.2d 1181 (Del.1980); Lee Builders v. Wells, 34 Del.Ch. 307, 103 A.2d 918 (1954); In re Ross & Son, Inc., 10 Del.Ch. 434, 95 A. 311 (1915); In re Plywood Co. of Pennsylvania, 425 F.2d 151 (3d Cir.1970); Chapman Decorative Co. v. Security Mut. Life Ins. Co., 149 F. 189 (3d Cir.1906). It is common for construction contracts to contain liquidated damages provisions, similar to those at issue here, prescribing the damages for which the contractor will be liable if the construction work is not completed within the time provided in the contract. See generally 25 C.J.S. Damages § 106 (1966); 13 Am.Jur.2d Building and Construction Contracts § 86 (1964); Annot., 12 A.L.R.4th 891 (1982); Worthington Corp. v. Consolidated Aluminum Corp., 544 F.2d 227 (5th Cir.1976); Trans World Airlines v. Travelers Indemnity Co., 262 F.2d 321 (8th Cir.1959).

In actions for damages resulting from the failure to complete construction work in a timely fashion, “actual damages” and “liquidated damages” will not both be awarded. Where the parties have stipulated a figure as liquidated damages, that figure represents the outer limit of the injured party’s recovery. See Stone, Sand & Gravel Co. v. United States, 234 U.S. 270, 34 S.Ct. 865, 58 L.Ed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
666 F. Supp. 649, 1985 U.S. Dist. LEXIS 23122, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gilbane-building-co-v-nemours-foundation-ded-1985.