Gilbane Building Co. v. Nemours Foundation

606 F. Supp. 995, 1 Fed. R. Serv. 3d 475, 1985 U.S. Dist. LEXIS 21416
District Court, D. Delaware·Decided March 25, 1985·No. Civ. A. 83-58-WKS·Published·Cited by 9 cases

Opinion

OPINION

STAPLETON, Chief Judge:

Before me is one portion of a consolidated action arising out of the construction of an 830,000 square foot addition to the Alfred I. duPont Institute Children’s Hospital in Wilmington, Delaware (the “Project”). Contractual disputes and delays in completing the Project have spawned a complex and entangled thicket of litigation involving numerous parties and millions of dollars in claims. Since the factual background of the case has been set forth in some detail in prior opinions, see, e.g., Gilbane Building Co. v. Nemours Foundation, 568 F.Supp. 1085 (D.Del. 1983), repetition here is unnecessary. However, certain portions of this background must be highlighted in order to provide a factual backdrop for the discussion contained herein.

BACKGROUND

On April 5, 1983, Pierce Associates, Inc. (“Pierce”) and Dynalectric Company (“Dynalectric”) filed “sister” breach of contract actions against Gilbane Building Company (“Gilbane”). Gilbane had been retained by the Nemours Foundation (“Nemours”), the owner of the Project, to serve as the prime contractor during Phase 5B of the Project. Pierce and Dynalectric had both entered into subcontracts with Gilbane to perform portions of the work scheduled for completion during Phase 5B. It was the alleged breach of these contracts by Gilbane which provided the genesis for the suits by Pierce and Dynalectric.

In response to the initiation of these breach of contract actions, Gilbane filed counterclaims against Pierce and Dynalectric and third-party complaints against Nemours, Saxelbye, Powell, Roberts & Ponder, Inc. (“Saxelbye”), the architect for the Project, and Furlow Associates, Inc. (“Furlow”), the mechanical and building management systems engineer for the Project. Nemours then filed an answer and counterclaim against Gilbane in each of the cases and claims pursuant to Rule 14 of the Federal Rules of Civil Procedure against Pierce and Dynalectric. Subsequently, Nemours twice amended these claims against Pierce and Dynalectric.

*998 In April, 1984, both Pierce and Dynalectric answered Nemours’ claims and asserted virtually identical counterclaims against Nemours. Nemours moved to dismiss on the basis that neither Pierce nor Dynalectric had stated claims upon which relief could be granted and that Dynalectric had not stated a claim properly within the subject matter jurisdiction of the Court. On October 31, 1984, following the briefing of these motions, both Pierce and Dynalectric amended their counterclaims against Nemours, and on November 7, 1984, the Court heard oral argument, at which time, Nemours represented that its motions to dismiss applied to both the original counterclaims as well as the amended counterclaims. 1 Thereafter, the two cases were consolidated with three other actions similarly arising out of disputes concerning the Project.

DISCUSSION

A. Dynalectric’s Counterclaim Against Nemours — Subject Matter Jurisdiction

Nemours contends that Dynalectric’s counterclaim is not properly within the subject matter jurisdiction of the Court since Nemours and Dynalectric are both citizens of Florida and no federal question is presented by the counterclaim. 2 In short, Nemours argues that in order for a plaintiff to assert a claim against a third-party defendant, there must be an independent jurisdictional basis for such a claim, notwithstanding that such a claim may be in the nature of a counterclaim asserted in response to a claim made by the third-party defendant against the original plaintiff. In support of its position, Nemours relies principally on Owen Equipment & Erection Co. v. Kroger, 437 U.S. 365, 98 S.Ct. 2396, 57 L.Ed.2d 274 (1978).

In response, Dynalectric contends that where a third-party defendant has asserted a claim against the original plaintiff pursuant to Fed.R.Civ.P. 14, and, as a result, the original plaintiff has asserted what is essentially a compulsory counterclaim against the third-party defendant, Owen Equipment & Erection Co. v. Kroger, does not require an independent basis for jurisdiction since such a claim is properly within the ancillary jurisdiction of the Court.

While both parties have vigorously contested this issue, the Third Circuit Court of Appeals has recently held that “if ... a third-party defendant asserts claims under Rule 14(a) against [a] plaintiff, ancillary jurisdiction extends to support plaintiff’s ‘compulsory counterclaim’ under Fed.R. Civ.P. 13(a).” Finkle v. Gulf & Western Manufacturing Co., 744 F.2d 1015, 1018 (3d Cir.1984). 3 Since this decision is bind *999 ing precedent, the controlling issue therefore is whether Dynalectric’s claim against Nemours constitutes a “compulsory counterclaim”. 4

Rule 13(a) of the Federal Rules of Civil Procedure governs the assertion of compulsory counterclaims as follows:

A pleading shall state as a counterclaim any claim which at the time of serving the pleading the pleader has against any opposing party, if it arises out of the transaction or occurrence that is the subject matter of the opposing party's ■claim and does not require for its adjudication the presence of third parties of whom the court cannot acquire jurisdiction____

Fed.R.Civ.P. 13(a) (emphasis added).

Nemours does not contend that Dynalectric’s counterclaim requires the presence of third parties over whom this Court cannot acquire jurisdiction. Hence, the key question is whether Dynalectric’s counterclaim arises out of the same transaction or occurrence that formed the basis for Nemours’ claims against Dynalectric.

In Xerox Corp. v. SCM Corp., 576 F.2d 1057 (3d Cir.1978), the Third Circuit indicated that “the operative question in determining if a claim is a compulsory counterclaim is whether it bears a logical relationship to an opposing party’s claim.” Id. at 1059.

[A] counterclaim is logically related to the opposing party’s claim where separate trials on each of their respective claims would involve a substantial duplication of effort and time by the parties and the courts. Where multiple claims involve many of the same factual issues, or the same factual and legal issues, or where they are offshoots of the same

Free access — add to your briefcase to read the full text and ask questions with AI

Gilbane Building Co. v. Nemours Foundation, 606 F. Supp. 995, 1 Fed. R. Serv. 3d 475, 1985 U.S. Dist. LEXIS 21416 (D. Del. 1985).

606 F. Supp. 995 (Gilbane Building Co. v. Nemours Foundation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related