Oliver B. Cannon & Sons, Inc. v. Dorr-Oliver Inc.

312 A.2d 322, 1973 Del. Super. LEXIS 129
CourtSuperior Court of Delaware
DecidedSeptember 18, 1973
StatusPublished
Cited by135 cases

This text of 312 A.2d 322 (Oliver B. Cannon & Sons, Inc. v. Dorr-Oliver Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oliver B. Cannon & Sons, Inc. v. Dorr-Oliver Inc., 312 A.2d 322, 1973 Del. Super. LEXIS 129 (Del. Ct. App. 1973).

Opinion

OPINION AND ORDER ON PLAINTIFFS MOTION FOR SUMMARY JUDGMENT ON DEFENDANT BARCROFT’S COUNTERCLAIM: MOTION DENIED

QUILLEN, Chancellor: 1

In May of 1968, Barcroft Company (“Barcroft”) entered into an agreement with Dorr-Oliver Incorporated (“Dorr”), whereby Dorr was to design and construct a plant for the production of magnesium hydroxide paste on Barcroft’s site at Lewes, Delaware. Dorr subcontracted out a portion of this project (preparing and painting the interior linings of certain chemical process tanks) to Oliver B. Cannon & Sons, Inc. (“Cannon”), a paint contractor. Pursuant to a purchase order dat- 1 ed June 13, 1969, Cannon agreed to apply Glid-Flake paint linings to fourteen tanks at the Lewes plant. Glid-Flake is produced by third-party defendant SCM Corporation’s Glidden-Durkee Division.

In December 1969, Cannon finished painting the tanks. By late January 1970 the lining of one of the tanks (IS-103) began to show evidence of deterioration. And, by late May 1970 Barcroft was forced to close its plant because the linings of several tanks were coming off in large sheets and the tanks were rusting. The actual cause of this lining failure is a point of vigorous contention among the parties.

Upon requests from Barcroft and Dorr, Cannon performed repair work on all the tanks. Through Dorr, Barcroft paid Cannon $94,306.34 in connection with the repairs.

In January of 1971, Cannon filed suit against Dorr, as general contractor, demanding an additional payment of $113,914.23 for the relining of the chemical process tanks. Cannon also filed a claim for a mechanic’s lien in the same amount against Barcroft. 2

Alleging that Cannon failed to properly furnish paint linings for the tanks in question, Dorr counterclaimed against Cannon for $118,599.17. Barcroft also filed a counterclaim against Cannon which is the subject of this motion.

In Count I of its counterclaim, Barcroft seeks the return of the $94,306.34 paid Cannon in connection with the repair work. Barcroft alleges that Cannon was contractually obligated to repair, at its own expense, the defective paint linings. Bar-croft further claims that the $94,306.34 was only paid under protest through Dorr to Cannon as an inducement for Cannon to fulfill its contractual obligations.

In Count II of its counterclaim Barcroft charges that the Glid-Flake lining failure was the result of Cannon’s negligent workmanship. 3 As a result, Barcroft seeks *325 damages in the total amount of $420,856.36, consisting of (a) the $94,306.34 paid by Barcroft through Dorr to Cannon, and (b) $326,550.02 in profits which were lost to Barcroft during the period when the plant was shut down for repairs.

Denying that it was contractually obligated to correct the defective paint linings or that it was negligent, Cannon has moved for summary judgment on Bar-croft’s counterclaim under Civil Rule 56 of this Court. Cannon contends that there is no issue of material fact with respect to Barcroft’s counterclaim and that it is entitled to summary judgment as a matter of law. This is the decision on Cannon’s motion.

In weighing a motion for summary judgment under Rule 56, the Court must examine the present record, including pleadings, depositions, admissions, affidavits, and answers to interrogatories. Continental Cas. Co. v. Ocean Acc. & Guarantee Corp., 8 Storey 338, 209 A.2d 743 (Super.Ct.1965). The facts must be viewed in a light favorable to the non-moving party (Barcroft), although uncontroverted evidence offered in support of the motion must be accepted as true. The moving party must show that, on unquestioned facts, he is entitled to a judgment as a matter of law. Matas v. Green, 3 Storey 473, 475, 171 A.2d 916, 918 (Super.Ct.1961); 6 Moore’s Federal Practice, § 56.-15(3); Superior Court Rules, Civil R. 56(c). Wilson v. Tweed, 8 Storey 391, 209 A.2d 899 (Sup.Ct.1965). The Court’s function is not to weigh evidence or to accept that which appears to have greater weight. Continental Oil Co. v. Pauley Petroleum, Del.Sup., 251 A.2d 824 (1969).

An examination of the record indicates that one factual question is clearly in issue. The parties are unable to agree as to the cause of the Glid-Flake paint lining fail-' ure. Barcroft and Dorr offer testimony tending to prove that the failure was due to negligent workmanship by Cannon. On the other hand, Cannon blames the lining failure on chemical attack allegedly occurring when Barcroft (without forewarning Cannon of its intentions) used the tanks to store chemicals of a higher toxicity than Glid-Flake was intended to withstand. At this stage, the Court must take the version most favorable to Barcroft and assume that Cannon was negligent. And, Bar-croft’s payment for the repair work cannot be called voluntary as a matter of law under any reasonable view of the case.

Assuming its negligence, Cannon argues that, as a matter of law, it is still entitled to summary judgment on Barcroft’s counterclaim. Cannon denies that its performance under the purchase order contract with Dorr created any legal duty or obligation to Barcroft. Therefore, Cannon contends, Barcroft’s counterclaim cannot stand either in contract or in tort. Accordingly, to decide the issue, the Court must determine whether Barcroft’s relation to Cannon is such that the law entitles Barcroft to seek compensation, in contract or in tort, for Cannon’s assumed negligence.

Before examining Barcroft’s contract claim, the preliminary question of what law to apply must be disposed of. The rule in Delaware is that the courts look to the law of the place of contracting to determine the validity and construction of a contract. Wilmington Trust Company v. Pennsylvania Company, 40 Del.Ch. 1, 172 A.2d 63 (Sup.Ct.1961). It is unclear whether the Cannon-Dorr purchase order contract was executed in Pennsylvania or Connecticut. However, since Connecticut conflict of laws rules would apply Delaware law, and both Delaware and Pennsylvania apply general contract principles to the questions at issue, it is only necessary for the Court to apply general contract principles in reaching its decision. Jenkins v. Indemnity Ins. Co. of North America, 152 Conn. 249, 205 A.2d 780 (1964); Royal Indemnity Co. v. Alexander Industries, Inc., 8 Storey 548, 211 A.2d 919 (Sup.Ct.1965); Sears, Roebuck and Co. v. Jardel Co., 421 F.2d 1048 (3 Cir. 1970).

*326 Turning now to Barcroft’s contract claim, Barcroft concedes that it had no direct contractual relationship with Cannon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MidFirst Bank v. Mullane
Superior Court of Delaware, 2023
Genworth Financial v. AIG Specialty Insurance
Superior Court of Delaware, 2023
Hopkins v. Owens
Superior Court of Delaware, 2023
Dominica v. The Greenery at Rodney Square, Inc.
Superior Court of Delaware, 2020
Hrycak v. Public Storage, Inc.
Superior Court of Delaware, 2019
Arch Insurance Company v. Murdock
Superior Court of Delaware, 2019
Winshall v. Viacom International, Inc.
Superior Court of Delaware, 2019
Elsey-Jones v. Gullion
Superior Court of Delaware, 2018
Negron v. Geico Secure Insurance Company
Superior Court of Delaware, 2018

Cite This Page — Counsel Stack

Bluebook (online)
312 A.2d 322, 1973 Del. Super. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oliver-b-cannon-sons-inc-v-dorr-oliver-inc-delsuperct-1973.