Ric-Man Construction Inc v. Neyer Tiseo & Hindo Ltd

CourtMichigan Court of Appeals
DecidedJanuary 17, 2017
Docket329159
StatusUnpublished

This text of Ric-Man Construction Inc v. Neyer Tiseo & Hindo Ltd (Ric-Man Construction Inc v. Neyer Tiseo & Hindo Ltd) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ric-Man Construction Inc v. Neyer Tiseo & Hindo Ltd, (Mich. Ct. App. 2017).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

RIC-MAN CONSTRUCTION, INC., UNPUBLISHED January 17, 2017 Plaintiff/Counter-Defendant- Appellee,

v No. 329159 Wayne Circuit Court NEYER, TISEO & HINDO LTD. d/b/a NTH LC No. 11-011315-CZ CONSULTANTS, LTD.,

Defendant/Counter-Plaintiff- Appellant.

Before: TALBOT, C.J., and JANSEN and HOEKSTRA, JJ.

PER CURIAM.

In this dispute between a contractor and project engineer, defendant/counter-plaintiff Neyer, Tiseo & Hindo LTD., d/b/a NTH Consultants, LTD. (NTH), appeals by leave granted1 the trial court’s August 14, 2015 opinion and order granting in part and denying in part its motion for summary disposition. Plaintiff/counter-defendant Ric-Man Construction, Inc. cross-appeals a portion of the same opinion and order. We affirm in part, reverse in part, and remand for further proceedings.

I. FACTS

The instant dispute revolves around the rehabilitation of the Oakland-Macomb Interceptor (the OMI). As background:

The OMI is an intercounty drain formerly owned by Detroit. In 2009, the [Oakland-Macomb Interceptor Drain Drainage District (OMIDDD)] was formed and purchased the OMI. . . . At the time the OMIDDD acquired the OMI, the system was in a serious state of disrepair. The OMIDDD was tasked with rehabilitating the system. An expensive, multi-year rehabilitation project was

1 Ric-Man Construction, Inc v Neyer, Tiseo & Hindo LTD, unpublished order of the Court of Appeals, entered February 17, 2016 (Docket No. 329159).

-1- approved, and is just now nearing completion. The project was funded largely by apportionments paid by 23 communities that connected to the OMI and used it to deliver wastewater to the Detroit Water and Sewerage Department (DWSD).[2]

The dispute in this matter revolves around one portion of the rehabilitation project. Specifically, at issue is the construction of Control Structure 6 (CS-6). Generally speaking, construction of this structure required excavating 75 feet deep underground to install a gate that could be used to facilitate repairs to the sewer system in the future. The project was designed by NTH. NTH’s plans were made available to contractors, who bid on the project. Ric-Man won the bid, and entered into an agreement that included the construction of CS-6. This contract, which actually consists of several documents, is referred to as the Prime Contract. The Prime Contract designated NTH as the OMIDDD’s representative during the construction phase. NTH would oversee the project, ensuring that Ric-Man’s work conformed to NTH’s design. NTH was also given responsibility to make determinations regarding problems or disputes that might arise during construction.

During construction, Ric-Man encountered two primary issues. First, Ric-Man, on advice of a supplier and several consultants, believed the upper temporary earth retention system (TERS) designed by NTH was defective. The TERS is a safety system, made of steel, that is designed to keep earth from collapsing as workers excavate deeper into the ground. Ric-Man believed that the system as designed by NTH was not sufficient to prevent a collapse. Ric-Man brought its concerns to NTH, but NTH maintained that the system it designed was sufficient. Eventually, Ric-Man constructed the TERS as it believed was necessary to protect its workers.

The second issue involves the soil conditions encountered at the work site. Based on geotechnical reports prepared by NTH, Ric-Man expected to encounter “stiff silty clay and medium compact to very compact silty sands and silts . . . .” However, as it excavated, Ric-Man found that the soil was materially different. As a result, Ric-Man had to begin an emergency grouting program, incurring additional expenses. Ric-Man sought a time extension related to this issue, but the request was denied.

In 2011, Ric-Man and the OMIDDD agreed to arbitrate their disputes. Shortly thereafter, Ric-Man filed the instant suit against NTH. The complaint raised five counts: professional negligence, intentional misrepresentation, tortious interference with contract, negligent misrepresentation, and defamation. On NTH’s motion, the trial court granted summary disposition on all claims in NTH’s favor, concluding that these claims should be submitted to arbitration along with Ric-Man’s claims against the OMIDDD. However, on appeal, this Court reversed, holding that NTH could not compel arbitration between itself and Ric-Man.3

2 Marrocco v OMIDDD, unpublished opinion per curiam of the Court of Appeals, issued June 16, 2016 (Docket No. 326575), unpub op at 2. 3 Ric-Man Const, Inc v Neyer, Tiseo & Hindo Ltd, unpublished opinion per curiam of the Court of Appeals, issued March 26, 2013 (Docket No. 309217).

-2- After the matter returned to the trial court, NTH moved for summary disposition on all counts. Ric-Man agreed that its intentional misrepresentation claim failed as a matter of law, but contested the motion with regard to the remaining counts. After receiving a multitude of briefs from the parties and hearing their arguments, the trial court issued its opinion. For the most part, the trial court denied NTH’s motion. The trial court did hold that Ric-Man could not recover the lost profits of a separate company, Mancini Enterprises, LLC, owned by the same three brothers that own Ric-Man. NTH filed the instant application for leave to appeal, which this Court granted. Ric-Man then filed a cross-appeal, challenging the trial court’s decision that it could not pursue a claim of lost profits on behalf of Mancini Enterprises.

The issues raised on appeal generally fit into two categories: those challenging the merits of the various counts of the complaint, and those addressing what damages Ric-Man may recover. We begin with the arguments addressing the viability of the individual counts.

II. DUTY OF CARE – PROFESSIONAL NEGLIGENCE AND NEGLIGENT MISREPRESENTATION

The first issue concerns Ric-Man’s professional negligence and negligent misrepresentation counts. These counts allege that NTH negligently designed the TERS and was negligent in reporting the soil conditions at the work site. NTH contends that both claims must fail because neither alleges the existence of a duty of care separate and distinct from its agreement with the OMIDDD to design the project. We agree that the professional negligence count is barred for this reason. However, we find that the negligent misrepresentation count may proceed.

Whether a plaintiff owes a defendant a duty of care is a question of law, reviewed de novo.4 This Court also “reviews the grant or denial of summary disposition de novo to determine if the moving party is entitled to judgment as a matter of law.”5 NTH brought its motion pursuant to MCR 2.116(C)(8) and (C)(10). As our Supreme Court has explained:

A motion under MCR 2.116(C)(8) tests the legal sufficiency of the complaint. All well-pleaded factual allegations are accepted as true and construed in a light most favorable to the nonmovant. A motion under MCR 2.116(C)(8) may be granted only where the claims alleged are “so clearly unenforceable as a matter of law that no factual development could possibly justify recovery.” When deciding a motion brought under this section, a court considers only the pleadings.

* * *

A motion under MCR 2.116(C)(10) tests the factual sufficiency of the complaint. In evaluating a motion for summary disposition brought under this subsection, a trial court considers affidavits, pleadings, depositions, admissions,

4 Fultz v Union-Commerce Assoc, 470 Mich 460, 463; 683 NW2d 587 (2004). 5 Maiden v Rozwood, 461 Mich 109, 118; 597 NW2d 817 (1999) (citations omitted).

-3- and other evidence submitted by the parties . . . in the light most favorable to the party opposing the motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mars, Inc. v. Coin Acceptors, Inc.
527 F.3d 1359 (Federal Circuit, 2008)
Poly-America, L.P. v. Gse Lining Technology, Inc.
383 F.3d 1303 (Federal Circuit, 2004)
Loweke v. Ann Arbor Ceiling & Partition Co, LLC
809 N.W.2d 553 (Michigan Supreme Court, 2011)
Smith v. Anonymous Joint Enterprise
487 Mich. 102 (Michigan Supreme Court, 2010)
Roberts v. Saffell
766 N.W.2d 288 (Michigan Supreme Court, 2009)
Fultz v. Union-Commerce Associates
683 N.W.2d 587 (Michigan Supreme Court, 2004)
Monat v. State Farm Insurance
677 N.W.2d 843 (Michigan Supreme Court, 2004)
Wilkie v. Auto-Owners Insurance
664 N.W.2d 776 (Michigan Supreme Court, 2003)
Klapp v. United Insurance Group Agency, Inc
663 N.W.2d 447 (Michigan Supreme Court, 2003)
Keywell & Rosenfeld v. Bithell
657 N.W.2d 759 (Michigan Court of Appeals, 2003)
Lawsuit Financial, LLC v. Curry
683 N.W.2d 233 (Michigan Court of Appeals, 2004)
Porter v. City of Royal Oak
542 N.W.2d 905 (Michigan Court of Appeals, 1995)
Ditmore v. Michalik
625 N.W.2d 462 (Michigan Court of Appeals, 2001)
Hines v. Volkswagen of America, Inc
695 N.W.2d 84 (Michigan Court of Appeals, 2005)
Seasword v. Hilti, Inc.
537 N.W.2d 221 (Michigan Supreme Court, 1995)
Bacco Construction Co. v. American Colloid Co.
384 N.W.2d 427 (Michigan Court of Appeals, 1986)
Riddle v. McLouth Steel Products Corp.
485 N.W.2d 676 (Michigan Supreme Court, 1992)
Helmus v. Department of Transportation
604 N.W.2d 793 (Michigan Court of Appeals, 2000)
Roberts v. Saffell
760 N.W.2d 715 (Michigan Court of Appeals, 2008)
Williams v. Polgar
214 N.W.2d 149 (Michigan Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
Ric-Man Construction Inc v. Neyer Tiseo & Hindo Ltd, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ric-man-construction-inc-v-neyer-tiseo-hindo-ltd-michctapp-2017.