National Sand, Inc v. Nagel Construction, Inc

451 N.W.2d 618, 182 Mich. App. 327
CourtMichigan Court of Appeals
DecidedFebruary 20, 1990
DocketDocket 106970
StatusPublished
Cited by41 cases

This text of 451 N.W.2d 618 (National Sand, Inc v. Nagel Construction, Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Sand, Inc v. Nagel Construction, Inc, 451 N.W.2d 618, 182 Mich. App. 327 (Mich. Ct. App. 1990).

Opinion

Sawyer, J.

Plaintiff National Sand, Inc., appeals from an order granting partial summary disposition pursuant to MCR 2.116(C)(7) and (8), dismissing defendants Progressive Engineering, Inc., and Missaukee Sanitary Drain Commission from the suit. The order was certified as a final order under MCR 2.604(A). We affirm in part and remand.

Defendant drain commission contracted with defendant Nagel Construction, Inc., to construct a sewage treatment facility. Nagel subcontracted with National Sand to excavate the sewage pits and to line the pits with clay. Progressive Engineering prepared the plans and specifications for the project.

*330 In October, 1984, National Sand began excavating the sewage pits at the site of the sewage treatment facility. During excavation, National Sand discovered that there was insufficient clay on the site for lining the sewage pits. 1 Thereafter, an alternate site was sought which contained sufficient clay. A site was located in 1985 and the contracts were modified to provide compensation for the additional expenditures of money and labor required as a result of the insufficient clay deposits.

However, on September 16, 1985, it was again discovered that there were insufficient clay deposits in the areas set forth in Progressive Engineering’s plans. The contracts were again modified to provide compensation for the additional costs.

Ultimately, National Sand completed its services under the original subcontract and Nagel Construction paid National Sand the amount due under the original subcontract, but refused to pay an additional $258,000 which National Sand claimed was incurred as a result of the insufficient clay deposits.

The instant action was filed on October 1, 1987. Count i of the complaint alleges breach of contract. Count ii alleges negligence by Progressive Engineering in preparing the construction plans and in failing to use proper procedures in locating the clay deposits.

First, we briefly consider Progressive Engineering’s argument that the jurisdiction of this Court has not been properly invoked because the order appealed from was not properly entered. However, this issue was considered by this Court on Progressive Engineering’s motion to dismiss, which denied *331 the motion by an order entered July 25, 1988. We see no need to revisit the issue.

Next, we briefly consider plaintiff’s arguments that Progressive Engineering and the drain commission are proper parties to the suit despite the lack of privity of contract. Contrary to plaintiff’s arguments, on the basis of the Supreme Court’s decision in Williams v Polgar, 391 Mich 6; 215 NW2d 149 (1974), Michigan has not "categorically eliminated” the requirement of privity of contract. Rather, Williams concluded that privity is no longer a requirement for liability by a title abstracter. Id. at 15-18. That is, a third party injured by the negligence of the abstracter may maintain an action in tort, specifically, negligent misrepresentation. Id. at 20. Similarly, this Court has allowed a contractor to maintain an action in tort (specifically, negligence) against a project engineer despite the lack of privity of contract. Bacco Construction Co v American Colloid Co, 148 Mich App 397, 413-416; 384 NW2d 427 (1986).

Thus, what can be concluded is not, as plaintiff suggests, that a breach of contract claim can be maintained regardless of privity; rather, it is that a plaintiff may maintain an action in tort where he is injured by the defendant’s negligent performance of contract even where there is no privity between the parties. Thus, in the case at bar, the trial court properly dismissed plaintiff’s breach of contract claims against Progressive Engineering and the drain commission since there was no contractual relationship between plaintiff and those two defendants. However, that does not preclude plaintiff from maintaining its tort claim against Progressive Engineering. 2

This then brings us to the issue whether the *332 period of limitations has run on plaintiffs tort claim against Progressive Engineering. The trial court concluded that the two-year malpractice limitation period of MCL 600.5805(4); MSA 27A.5805(4) was applicable and barred plaintiffs claim. Plaintiff argues that the six-year limitation period for "other personal actions” contained in MCL 600.5813; MSA 27A.5813 should apply, relying on Bacco, supra. For the reasons to be discussed below, we believe that §5805 controls the instant case.

MCL 600.5805; MSA 27A.5805, often referred to as the "negligence” statute of limitations, provides in pertinent part as follows:

(1) A person shall not bring or maintain an action to recover damages for injuries to persons or property unless, after the claim first accrued to the plaintiff or to someone through whom the plaintiff claims, the action is commenced within the periods of time prescribed by this section.
(4) Except as otherwise provided in this chapter, the period of limitations is 2 years for an action charging malpractice.
(8) The period of limitations is 3 years after the time of the death or injury for all other actions to recover damages for the death of a person, or for injury to a person or property. [Emphasis added.]

Plaintiff, relying on Bacco, supra, argues that, since its injury is financial rather than a physical injury to "persons or property,” the provisions of § 5813, relating to "other personal actions,” apply. While Bacco does support plaintiffs position, we believe Bacco was incorrectly decided.

The effect of the "injuries to persons or property” language in § 5805 has been the source of a *333 great deal of confusion in the case law. In Bacco, the plaintiff was a contractor engaged to construct a waste-water lagoon. Leaks developed in the lagoon and the work was rejected. By agreement of the parties, the plaintiff made the necessary repairs with none of the parties admitting liability for the problem. The plaintiff sought to recover damages for its additional expenses. Its complaint alleged, inter alia, negligence by the materials supplier and its sales agent as well as by the project engineer. The Bacco Court concluded that § 5813 applied since there was no physical harm to persons or property. In reaching its decision, the Court relied on Coats v Uhlmann, 87 Mich App 385; 274 NW2d 792 (1978), Borman’s, Inc v Lake State Development Co, 60 Mich App 175; 230 NW2d 363 (1975), and Tel-Twelve Shopping Center v Sterling Garrett Construction Co, 34 Mich App 434; 191 NW2d 484 (1971).

Bacco’s reliance on Coats, supra, is misplaced. First, Coats

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Russett v. NTVB Media Inc.
E.D. Michigan, 2023
Sun Yu v. Frank Migliazzo
Michigan Court of Appeals, 2018
Raymond J Carey v. Foley & Lardner LLP
Michigan Court of Appeals, 2016
Alfieri v. Bertorelli
813 N.W.2d 772 (Michigan Court of Appeals, 2012)
In Re Nm Holdings Company, LLC
405 B.R. 830 (E.D. Michigan, 2008)
Estes v. Idea Engineering & Fabricating, Inc
649 N.W.2d 84 (Michigan Court of Appeals, 2002)
DiPonio Construction Co. v. Rosati Masonry Co.
631 N.W.2d 59 (Michigan Court of Appeals, 2001)
Eastern Steel Constructors, Inc. v. City of Salem
549 S.E.2d 266 (West Virginia Supreme Court, 2001)
Aikens v. Debow
541 S.E.2d 576 (West Virginia Supreme Court, 2001)
Baks v. Moroun
576 N.W.2d 413 (Michigan Court of Appeals, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
451 N.W.2d 618, 182 Mich. App. 327, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-sand-inc-v-nagel-construction-inc-michctapp-1990.