Harbor Mechanical, Inc. v. Arizona Electric Power Cooperative, Inc.

496 F. Supp. 681, 1980 U.S. Dist. LEXIS 9401
CourtDistrict Court, D. Arizona
DecidedAugust 15, 1980
DocketCIV 80-027, CIV 80-028-TUC-MAR
StatusPublished
Cited by7 cases

This text of 496 F. Supp. 681 (Harbor Mechanical, Inc. v. Arizona Electric Power Cooperative, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harbor Mechanical, Inc. v. Arizona Electric Power Cooperative, Inc., 496 F. Supp. 681, 1980 U.S. Dist. LEXIS 9401 (D. Ariz. 1980).

Opinion

MARY ANNE RICHEY, District Judge.

This case arises out of the construction of the Apache Electric Generating Station owned by defendant Arizona Electric Power Cooperative, Inc. (AEPCO). AEPCO hired defendant Burns and McDonnell (B&McD), an engineering firm, to prepare plans and specifications for construction of the plant and to supervise the various contractors at the construction site. Plaintiffs Harbor Mechanical (Harbor) and Schuchart Industrial Contractors (Schuchart) were hired by AEPCO to perform certain phases of the construction. Other phases of the construction were the responsibility of other prime contractors, not parties to this suit.

The construction of the power plant was plagued with delays and lack of coordination among the various prime contractors. As a result, Harbor and Schuchart allegedly incurred substantial additional costs and have brought. this action against the defendants to recover the amount of that loss. Each plaintiff filed a separate suit, but the defendants, the factual allegations, and legal claims are similar, with the exception that Harbor’s complaint contains a claim against B&McD for negligent misrepresentation which the Schuchart complaint omits. Both complaints contain a negligence count against M&McD, Count V.

B&McD has moved for dismissal of Count V from both complaints and for dismissal of the misrepresentation claim in Harbor’s complaint. The Court will treat this motion as one for summary judgment under Rule 12(b), Fed.R.Civ.P., the parties having submitted affidavits and other materials outside the pleadings. As counsel for both parties agreed at the hearing on this motion, under the Erie.doctrine the Court is bound to apply state law in this diversity action. See Klingebiel v. Lockheed Aircraft Corp., 494 F.2d 345, 346-47 (9th Cir. 1974).

I. The Negligence Claim

The gist of Count V of both complaints is that B&McD was negligent in its drafting of plans and specifications and was further negligent in supervision of the construction, with the result that plaintiffs suffered loss due to increased costs of construction. Plaintiffs further allege that this negligent supervision by B&McD breached a duty of due care owed to the prime contractors. Defendant argues that there existed no duty on its part to plaintiffs, since there was no contract between them, so that the only party who could recover for B&McD’s alleged negligence would be AEPCO. The issue, then, is whether Arizona recognizes a contractor’s cause of action for negligence against an architect/engineer in the absence of any contractual relationship.

In Arizona, as elsewhere, before a party can be held liable for negligence he must have owed a duty to the plaintiff, the breach of which results in injury. Berne v. Greyhound Parks of Arizona, Inc., 104 Ariz. 38, 448 P.2d 388, 389 (1968). For plaintiffs to recover from B&McD, they must demonstrate that B&McD owed them a duty to design the power plant and supervise its construction in a professionally competent manner. In their complaints and memoranda on this motion, plaintiffs contend that this duty arose from the contract between AEPCO and B&McD, the contract between AEPCO and the plaintiffs, and a B&McD procedures manual.

None of these documents expressly imposes duties upon B&McD toward the *683 plaintiffs. Plaintiffs contend, however, that the duties are implied in the grant of extensive powers and responsibilities from AEPCO to B&McD. With this background, the Court now turns to the scant Arizona law on the issue.

The first Arizona case to discuss the issue of engineer liability to third parties was Blecick v. School Dist. No. 18, 2 Ariz.App. 115, 406 P.2d 750 (1965), which involved a general contractor’s claim that an architect’s defective plans and negligent supervision resulted in the contractor incurring economic loss. The Arizona Court of Appeals squarely held that since there was no privity of contract between the architect and the contractor, the architect’s duties were owed solely to the school district and only the school district could recover for any negligence on the part of the architect. 406 P.2d at 755.

Plaintiffs attempt to distinguish Blecick as a case involving a contract dispute, whereas they characterize their claim against B&McD as sounding in negligence. This distinction is invalid, however, because plaintiffs’ Count V substantially premises the defendant's alleged duty to plaintiffs on the contract between B&McD and AEPCO. Blecick clearly holds that a contract between an architect and a property owner does not create duties owed to third party contractors. If Blecick remains good law, therefore, summary judgment must be granted to B&McD on the negligence count.

Plaintiffs attempt to avoid this conclusion by arguing that Blecick was “implicitly overruled” in Reber v. Chandler H.S. Dist. #202, 13 Ariz.App. 133, 474 P.2d 852 (1970). In Reber, a school district contracted with an architect to draw plans for a school building and to supervise the construction. Employees of the general contractor, injured due to an unsafe method of construction, sued the school district and the architect, the claim against the architect being based on “negligent supervision.” Instead of simply holding that the architect could not be sued by the employees of the general contractor due to lack of privity of contract, the Reber court stated that an architect might be liable to injured employees of the contractor in some cases. 474 P.2d at 854. The important aspect of Reber from Harbor and Schuchart’s point of view is that it contemplated imposing liability to parties other than the owner who engaged the architect. This result, plaintiffs argue, implicitly overrules Blecick. This Court does not agree.

Blecick held that a contractor who was not a party to the contract between an architect and the owner, or was not an intended beneficiary of that contract, could not hold the architect liable for negligence. 406 P.2d at 755. Reber is not inconsistent with that proposition. 1 Reber did not impose upon architects a general duty to third parties, based upon the architect’s supervision responsibilities. Instead, the court said that an architect may owe a duty to a third party, depending upon “whether or not the contract documents have created a duty.” 474 P.2d at 854 (emphasis added). In short, the court considered the intent of the parties, as reflected in the contract language, controlling on the scope of the architect’s duty to third parties.

This interpretation of Reber is supported by further language in the opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bacco Construction Co. v. American Colloid Co.
384 N.W.2d 427 (Michigan Court of Appeals, 1986)
Gilbane Building Co. v. Nemours Foundation
606 F. Supp. 995 (D. Delaware, 1985)
Donnelly Const. Co. v. Oberg/Hunt/Gilleland
677 P.2d 1298 (Court of Appeals of Arizona, 1983)
Donnelly Construction Co. v. Oberg/Hunt/Gilleland
677 P.2d 1298 (Court of Appeals of Arizona, 1983)
Arizona Feeds v. a & R ARGO, INC.
666 P.2d 520 (Court of Appeals of Arizona, 1983)
Bernard Johnson, Inc. v. Continental Constructors, Inc.
630 S.W.2d 365 (Court of Appeals of Texas, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
496 F. Supp. 681, 1980 U.S. Dist. LEXIS 9401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harbor-mechanical-inc-v-arizona-electric-power-cooperative-inc-azd-1980.