Auburn Hills Tax Increment Finance Auth v. Haussman Construction

CourtMichigan Court of Appeals
DecidedJanuary 11, 2018
Docket333972
StatusUnpublished

This text of Auburn Hills Tax Increment Finance Auth v. Haussman Construction (Auburn Hills Tax Increment Finance Auth v. Haussman Construction) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Auburn Hills Tax Increment Finance Auth v. Haussman Construction, (Mich. Ct. App. 2018).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

AUBURN HILLS TAX INCREMENT FINANCE UNPUBLISHED AUTHORITY, January 11, 2018

Plaintiff-Appellant,

v No. 333972 Oakland Circuit Court HAUSSMAN CONSTRUCTION COMPANY and LC No. 2015-149357-CB DENNIS BURT,

Defendants, and

MAYOTTE GROUP, INC.,

Defendant-Appellee.

Before: CAMERON, P.J., and SERVITTO and GLEICHER, JJ.

PER CURIAM.

Plaintiff, the Auburn Hills Tax Increment Finance Authority, appeals as of right the trial court’s order granting summary disposition under MCR 2.116(C)(10) and dismissing plaintiff’s claims of professional negligence and negligent misrepresentation against defendant, Mayotte Group, Inc. (Mayotte).1 We affirm.

I. BACKGROUND

On August 8, 2011, general contractor, Haussman Construction Company (Haussman), and the architecture firm, Mayotte, entered into a Builder-Architect Agreement with Mayotte agreeing to provide architectural services for the construction of a four-story concrete parking structure (the Project) to be built in Auburn Hills, Michigan. The owner of the Project was listed

1 As discussed below, plaintiff’s claims against defendants, Haussman Construction Company and Dennis Burt, were not the subject of the trial court’s order, as those claims were subject to an automatic stay because Burt filed for bankruptcy.

-1- as the City of Auburn Hills. The Builder-Architect Agreement indicated that the date of the contract between Haussman and the “Owner” was “TBD.”

Thereafter, plaintiff, as the owner, and Haussman entered into an Owner-Builder Agreement with Haussman agreeing to serve as general contractor for the design and construction of the Project. The “owner” was listed as the Auburn Hills Tax Increment Finance Authority. Mayotte, which was not a party to that contract, was listed as the architect for the Project. Attached to the Owner-Builder Agreement was an addendum that included a liquidated damages provision in the event that the construction was not completed on time. Haussman agreed to pay $1,000 a day for each day “that expired after the contractually specified time for completion until the Project was substantially completed.” A date for the completion of the Project, however, was not included in the provision.

According to plaintiff’s former executive director, Thomas Tanghe, Haussman was required under the Owner-Builder Agreement to select and retain an architect because plaintiff wanted the architect “to be working directly for [Haussman] and not for us.” For that reason, the provision in the Owner-Builder Agreement that required plaintiff to retain an architect was crossed out and initialed “CM,” which stood for “construction manager.” Tanghe acknowledged that there was never an agreement between plaintiff and Mayotte. After completing the Project allegedly behind schedule, defendant Dennis Burt, as the “principal, majority shareholder, and President,” dissolved Haussman and left Michigan without paying Haussman’s subcontractors.

In its complaint, plaintiff raised two claims against Mayotte: professional negligence and negligent misrepresentation. 2 Plaintiff alleged that Mayotte was responsible for “issuing a final Certificate for Payment” and reporting any “known deviations from the construction schedule” to plaintiff pursuant to the Builder-Architect Agreement. According to plaintiff, the Builder- Architect Agreement incorporated the “General Conditions” of plaintiff and Haussman’s Owner- Builder Agreement. Plaintiff also claimed that “the Project was only substantially completed several months after the contractually specified time for completion.” Plaintiff alleged that Mayotte certified the last payment to Haussman “for the full amount of the [Owner-Builder Agreement] contract sum, less $13,408.93 as retainage, without any allowance for the liquidated damages specified in the [Owner-Builder Agreement].” Further, plaintiff alleged that Haussman was “paid the full amount of the [Owner-Builder Agreement] contract sum,” but that Haussman “failed to pay its subcontractors on the Project, which then made claims on these funds against [plaintiff].” Therefore, plaintiff alleged that it paid “two times for some of the same work” because it was forced to pay Haussman’s subcontractors.

On December 3, 2015, the trial court entered an order staying the case due to Burt’s bankruptcy filing in a Florida federal court. However, the trial court eventually lifted the stay with regard to plaintiff’s claims against Mayotte. Subsequently, Mayotte filed a motion for summary disposition under MCR 2.116(C)(10). Ultimately, the trial court granted Mayotte’s motion for summary disposition because plaintiff had failed to identify any provision of the

2 Plaintiff also raised five claims against Haussman and Burt: (1) breach of contract, (2) unjust enrichment, (3) liquidated damages, (4) fraud, and (5) common law and statutory conversion.

-2- Builder-Architect Agreement that required Mayotte to “assess [p]laintiff’s right to liquidated damages or to approve payment claims.” Therefore, the trial court ruled that plaintiff had “failed to present any evidence establish[ing] that it was Mayotte’s duty to administer the construction or approve payments to Haussman.”

On appeal, plaintiff claims that the trial court erred when it granted Mayotte’s motion for summary disposition. At the outset, we note that plaintiff does not raise any contentions directly related to the trial court’s grant of summary disposition concerning its negligent misrepresentation claim against Mayotte. “An appellant may not merely announce his position and leave it to this Court to discover and rationalize the basis for his claims, nor may he give issues cursory treatment with little or no citation of supporting authority.” Houghton ex rel Johnson v Keller, 256 Mich App 336, 339; 662 NW2d 854 (2003) (citations omitted). Therefore, plaintiff has abandoned any contentions relating to its claim of negligent misrepresentation.

Plaintiff, however, claims that the trial court erred when it granted Mayotte’s motion for summary disposition on the professional negligence claim because Mayotte owed plaintiff a legal duty “to properly and accurately certify” Haussman’s “pay applications” for work completed on the Project pursuant to Mayotte’s contract with Haussman.3 Plaintiff also claims, in a footnote in its brief on appeal, that Mayotte’s legal duty arises from the “General Conditions” that were part of plaintiff’s Owner-Builder Agreement with Haussman. Plaintiff asserts that it is entitled to foreseeable economic damages as a result of the breach of Mayotte’s duties, which includes (1) damages for causing plaintiff to pay Haussman and the subcontractors for the same work, and (2) damages for failing to “conduct inspections to determine the date or dates of Substantial Completion and the date of Final Completion . . . and to issue a final Certificate of Payment.”4 Finally, plaintiff claims that the trial court granted summary disposition prematurely because the window for discovery had not closed. We conclude that the trial court did not err in granting summary disposition.

II. NEGLIGENCE

Plaintiff first claims that Mayotte breached its professional duty of care as the architect of the Project. We disagree.

3 According to Tanghe, processing pay applications entailed the following: “[Plaintiff] will send [Haussman] a pay application.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loweke v. Ann Arbor Ceiling & Partition Co, LLC
809 N.W.2d 553 (Michigan Supreme Court, 2011)
Fultz v. Union-Commerce Associates
683 N.W.2d 587 (Michigan Supreme Court, 2004)
Valcaniant v. Detroit Edison Co.
679 N.W.2d 689 (Michigan Supreme Court, 2004)
Dyer v. Trachtman
679 N.W.2d 311 (Michigan Supreme Court, 2004)
Townsend v. Chase Manhattan Mortgage Corp.
657 N.W.2d 741 (Michigan Court of Appeals, 2003)
Spiek v. Department of Transportation
572 N.W.2d 201 (Michigan Supreme Court, 1998)
Francisco v. Manson, Jackson & Kane, Inc
377 N.W.2d 313 (Michigan Court of Appeals, 1985)
Davis v. Venture One Construction, Inc.
568 F.3d 570 (Sixth Circuit, 2009)
Roulo v. Automobile Club of Mich.
192 N.W.2d 237 (Michigan Supreme Court, 1971)
Bacco Construction Co. v. American Colloid Co.
384 N.W.2d 427 (Michigan Court of Appeals, 1986)
Riddle v. McLouth Steel Products Corp.
485 N.W.2d 676 (Michigan Supreme Court, 1992)
Houghton v. Keller
662 N.W.2d 854 (Michigan Court of Appeals, 2003)
Maiden v. Rozwood
597 N.W.2d 817 (Michigan Supreme Court, 1999)
Beaty v. Hertzberg & Golden, Pc
571 N.W.2d 716 (Michigan Supreme Court, 1997)
Smith v. Allendale Mutual Insurance
303 N.W.2d 702 (Michigan Supreme Court, 1981)
Smith v. City of Detroit Swarthout
202 N.W.2d 300 (Michigan Supreme Court, 1972)
Hart v. Ludwig
79 N.W.2d 895 (Michigan Supreme Court, 1956)
Village of Dimondale v. Grable
618 N.W.2d 23 (Michigan Court of Appeals, 2000)
Liparoto Construction, Inc v. General Shale Brick, Inc
772 N.W.2d 801 (Michigan Court of Appeals, 2009)
Marilyn Froling Revocable Living Trust v. Bloomfield Hills Country Club
769 N.W.2d 234 (Michigan Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Auburn Hills Tax Increment Finance Auth v. Haussman Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/auburn-hills-tax-increment-finance-auth-v-haussman-construction-michctapp-2018.