Bautech USA, Inc. v. Resolve Equipment, Inc.

CourtDistrict Court, S.D. Florida
DecidedJune 26, 2023
Docket0:23-cv-60703
StatusUnknown

This text of Bautech USA, Inc. v. Resolve Equipment, Inc. (Bautech USA, Inc. v. Resolve Equipment, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bautech USA, Inc. v. Resolve Equipment, Inc., (S.D. Fla. 2023).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA

CASE NO. 23-60703-CIV-ALTONAGA/Strauss

BAUTECH USA, INC.,

Plaintiff, v.

RESOLVE EQUIPMENT, INC.; et al.,

Defendants. ___________________________________/

ORDER

THIS CAUSE came before the Court on Defendants, Resolve Equipment, Inc. (“Resolve Equipment”); Resolve Marine Group, Inc. (“Resolve Marine”); Olsen Associates, Inc. (“Olsen”); Skyrise Engineering & Testing, LLC (“Skyrise”); and the Federal Insurance Company’s (“FIC[’s]”) Joint Motion to Dismiss [ECF No. 19], filed on May 12, 2023. Plaintiff filed a Response [ECF No. 42], to which Defendants filed a Reply [ECF No. 43]. The Court has carefully considered the Amended Complaint [ECF No. 5], the parties’ written submissions, and applicable law. For the following reasons, the Motion is granted in part. I. BACKGROUND This case arises from a contract dispute concerning the fabrication of offshore reef mitigation units. (See generally Am. Compl.). In December 2019, Defendant Resolve Equipment — whose parent company is Resolve Marine — entered into a contract with Broward County for installation of offshore reef mitigation units. (See id. ¶¶ 11, 123). Plaintiff, a concrete fabricator, responded to Resolve Equipment’s bid solicitation for fabrication of the units, and Plaintiff and Resolve Equipment entered into a Subcontract on October 23, 2020. (See id. ¶¶ 10, 14; see generally id., Ex. 1, Subcontract [ECF No. 5-1]). After significant investments in preparation for the work, Plaintiff began fabricating units under the Subcontract in January 2021. (See Am. Compl. ¶¶ 18–19). Resolve Equipment and Resolve Marine hired Defendants Olsen and Skyrise to consult on the project and inspect Plaintiff’s finished units. (See id. ¶ 20).1 According to Plaintiff, Olsen and Skyrise “lacked the

knowledge and experience to detail the characteristic of the [u]nits” and were unfamiliar with the “standards and requirements” of the Subcontract. (Id. ¶ 21 (alteration added)). Consequently, “the County Consultants (and later, Resolve) unfairly and in bad faith rejected completed Units that conformed entirely to the Subcontract requirements, often for noncontractual and non-material issues.” (Id. ¶ 22). Plaintiff implemented design revisions in response to the inspections and sought a change order to reflect additional costs, which Olsen, Resolve Equipment, and Resolve Marine “wrongfully denied[.]” (Id. ¶ 29 (alteration added)). Nonetheless, Plaintiff continued production, and Olsen, Resolve Equipment, and Resolve Marine accepted and installed 1,327 units. (See id. ¶ 30). As production progressed, however, Olsen, Skyrise, Resolve Equipment, and Resolve Marine

proceeded to “wrongfully reject all [u]nits and withhold payments [Plaintiff] had rightfully and contractually earned.” (Id. ¶ 37 (alterations added)). Plaintiff sought to remedy the supposed deficiencies in various ways, including by proposing an enhanced quality control plan, but the four Defendants continued to reject Plaintiff’s units and remediation efforts. (See id. ¶ 49). Eventually, on March 22, 2022, Resolve Equipment sent Plaintiff a Notice of Termination and called on Plaintiff’s surety to perform. (See id. ¶ 60).

1 Plaintiff refers to Olsen and Skyrise collectively as the “County Consultants” or the “County Inspectors,” despite alleging these Defendants were hired by Resolve Equipment and Resolve Marine (which Plaintiff collectively refers to as “Resolve”) rather than Broward County. (See Am. Compl. ¶¶ 3, 7, 20). Months later, “Olsen accepted 274 previously rejected units that had been neither repaired nor modified.” (Id. ¶ 61 (alteration added)). Additionally, because Defendants “determined that no other contractor offered the terms [Plaintiff] offered under the Subcontract[,]” Plaintiff was invited back to the project. (Id. ¶¶ 62–63 (alterations added)). Olsen, Skyrise, Resolve Equipment,

and Resolve Marine “stated their commitment that the terms of the Subcontract would govern [Plaintiff’s] contractual requirements until [Plaintiff] completed its scope of work[;]” on that promise, Plaintiff entered into a Completion Agreement with its performance surety, Penn National Insurance Company. (Id. ¶¶ 63–64 (alterations added)). Despite the parties’ new beginning, the problems persisted. Plaintiff alleges the four Defendants “resumed their pattern of hostility, harassment, and over-inspection of [Plaintiff’s] manufacturing processes and completed [u]nits[,]” “doctoring reports[,]” rejecting more units, and instructing Plaintiff to “cease all further delivery.” (Id. ¶¶ 65–73 (alterations added)). Finally, on March 6, 2023, “Resolve issued its second Notice of Termination and Cure” to Plaintiff, followed by a deductive change order. (Id. ¶¶ 79, 84). As a result of Defendants’ conduct, Plaintiff suffered

“millions of dollars in damages[.]” (Id. ¶ 88 (alteration added)). Plaintiff brings ten claims against various configurations of Defendants for: breach of contract, Prompt Pay Act penalties, breach of payment bond, negligent design, negligent inspection, defamation, interference with contract, misrepresentation, and promissory estoppel. (See generally id.). Defendants move to dismiss the Amended Complaint under Federal Rule of Civil Procedure 12(b)(6), asserting it is a shotgun pleading and on the basis of specific arguments regarding nine of Plaintiff’s ten claims for relief. (See generally Mot.; Reply). II. LEGAL STANDARD “To survive a motion to dismiss [under Rule 12(b)(6)], a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (alteration added; quoting Bell Atl. Corp. v. Twombly, 550 U.S.

544, 570 (2007)). Although this pleading standard “does not require ‘detailed factual allegations,’ . . . it demands more than an unadorned, the-defendant-unlawfully-harmed-me accusation.” Id. (alteration added; quoting Twombly, 550 U.S. at 555). Pleadings must contain “more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do[.]” Twombly, 550 U.S. at 555 (alteration added; citation omitted). “[O]nly a complaint that states a plausible claim for relief survives a motion to dismiss.” Iqbal, 556 U.S. at 679 (alteration added; citing Twombly, 550 U.S. at 556). To meet this “plausibility standard,” a plaintiff must “plead[] factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Id. at 678 (alteration added; citing Twombly, 550 U.S. at 556). “The mere possibility the defendant

acted unlawfully is insufficient to survive a motion to dismiss.” Sinaltrainal v. Coca-Cola Co., 578 F.3d 1252, 1261 (11th Cir. 2009) (citation omitted), abrogated on other grounds by Mohamad v. Palestinian Auth., 566 U.S. 449 (2012). When considering a motion to dismiss, a court must construe the complaint in the light most favorable to the plaintiff and take its factual allegations as true. See Brooks v. Blue Cross & Blue Shield of Fla., Inc., 116 F.3d 1364, 1369 (11th Cir. 1997) (citing SEC v. ESM Grp., Inc., 835 F.2d 270, 272 (11th Cir. 1988)). III. DISCUSSION Defendants assert the Amended Complaint is a shotgun pleading. (See Mot. 4).2 Defendants also argue Plaintiff fails to state claims for relief as to nine of the ten claims. (See generally id.). Plaintiff concedes Defendants’ arguments as to Counts Two, Three, and Six and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert Garfield v. NDCHealth Corporation
466 F.3d 1255 (Eleventh Circuit, 2006)
Vega v. T-MOBILE USA, INC.
564 F.3d 1256 (Eleventh Circuit, 2009)
Sinaltrainal v. Coca-Cola Company
578 F.3d 1252 (Eleventh Circuit, 2009)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
General Aviation, Inc. v. The Cessna Aircraft Co.
915 F.2d 1038 (Sixth Circuit, 1990)
Mohamad v. Palestinian Authority
132 S. Ct. 1702 (Supreme Court, 2012)
ADVANCED MARKET. SYS. CORP. v. ZK Yacht Sales
830 So. 2d 924 (District Court of Appeal of Florida, 2002)
Spancrete v. Ronald E. Frazier & Assoc.
630 So. 2d 1197 (District Court of Appeal of Florida, 1994)
McCurdy v. Collis
508 So. 2d 380 (District Court of Appeal of Florida, 1987)
Palm Beach County Health Care District v. Professional Medical Education, Inc.
13 So. 3d 1090 (District Court of Appeal of Florida, 2009)
Townsend Contracting v. JENSEN CIV. CONST.
728 So. 2d 297 (District Court of Appeal of Florida, 1999)
Yoder v. Shell Oil Co.
405 So. 2d 743 (District Court of Appeal of Florida, 1981)
Making Ends Meet, Inc. v. Cusick
719 So. 2d 926 (District Court of Appeal of Florida, 1998)
Salit v. Ruden, McClosky, Smith, Schuster
742 So. 2d 381 (District Court of Appeal of Florida, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Bautech USA, Inc. v. Resolve Equipment, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bautech-usa-inc-v-resolve-equipment-inc-flsd-2023.