Rapp v. Mountain States Telephone & Telegraph Co.

606 P.2d 1189, 1980 Utah LEXIS 855
CourtUtah Supreme Court
DecidedFebruary 1, 1980
Docket16248
StatusPublished
Cited by16 cases

This text of 606 P.2d 1189 (Rapp v. Mountain States Telephone & Telegraph Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rapp v. Mountain States Telephone & Telegraph Co., 606 P.2d 1189, 1980 Utah LEXIS 855 (Utah 1980).

Opinion

HALL, Justice:

This appeal comes from the dismissal of an action by John M. Rapp, doing business as Rapp Construction Co. (hereafter plaintiff) against Mountain States Telephone and Telegraph Co. (hereafter defendant) for damages due to breach of a construction agreement, and is accompanied by a cross-appeal of the dismissal of defendant’s counterclaim alleging breach of contract by plaintiff.

Defendant, a Colorado corporation functioning as a public utility in numerous western states, made public announcement on March 2, 1974, that it was soliciting bids on a construction contract for the erection of a telephone building in Green River, Wyoming. Plaintiff, a duly licensed Utah contractor, requested and received the plans and related contract documents from defendant.

The provisions of these documents, where relevant here, called upon prospective bidders to examine the plans carefully, familiarize themselves with the requirements and circumstances thereof, base any bid submitted upon strict adherence to the terms and specifications set forth in the contract documents. Furthermore, bidders were to request any clarification or substitution in the plans or terms of the agreement prior to making a bid, and recognize that a bid submission constituted an acceptance of the specifications given as sufficient to allow the bidder to satisfactorily complete the project in conformity therewith. The general conditions of the contract also stated that any information prepared for the defendant by independent sources, and included in the specifications, was not warranted by the defendant, and that bidders relied thereon at their own risk. The terms of the offered contract set the deadline for completion at October 1, 1974, time being of the essence due to the anticipated delivery and installation of sensitive telephone equipment.

Plaintiff solicited numerous bids from subcontractors in the preparation of his own bid on the project, among them a bid from Star Plumbing and Heating Company of Salt Lake City for air circulation equipment and duct work. Plaintiff then submitted his bid to defendant, and on March 29, 1974, received word that he was low bidder. A formal contract was agreed upon shortly thereafter.

The plans submitted to plaintiff, consisting both of architectural drawings and mechanical drawings, called for the installation of a Carrier air handling unit. C & H Sheet Metal, supplier of Star Plumbing and Heating’s air handling equipment, made inquiry into the availability of such a unit, and learned that delivery to the construction site would take 25 weeks, making it impossible for plaintiff to meet the October 1 deadline specified in the construction agreement. 1 Plaintiff contacted defendant’s architect, Gerald Deines and Associates, and informed them of the problem. Upon consultation with defendant’s mechanical engineer, the architect approved a suggested substitute, a McQuay model 164 air handling unit. The change, together with an alteration in the contract price to reflect the more expensive unit, was embodied in a written change order, submitted by plaintiff and signed by both parties.

Early in August, plaintiff inquired of defendant’s mechanical engineer regarding the proper size for a hole which would have to be left in the wall of the room designed to house the air handling system, in order to *1191 install the unit. Upon rechecking the mechanical drawings which he had prepared (and upon which plaintiff had been relying), the engineer discovered that he had omitted certain ceiling beams, which extended 21½ inches down into the room in question. The parties reached the conclusion that, in light of this neglected space limitation, the 164 unit formerly agreed upon would be too large, and a further substitution, of a unit having less expansive dimensions, would have to be made. 2 Plaintiff, by letter, authorized defendant to negotiate directly with C & H Sheet Metal regarding the selection of a substitute. Defendant, however, made no such contact, but unilaterally selected the McQuay model 150 air handling unit, and pursued arrangements for its delivery. McQuay, which had committed to a delivery date of September 13, 1974, for the 164 unit stated that it would try to honor that commitment with the substitute 150 unit, but expressly refused to guarantee delivery on time. Nonetheless, defendant issued, and plaintiff signed, a change order reflecting the switch to the 150 unit, together with price alterations in the contract agreement.

Delivery of the air handling unit to the job site was drastically delayed, coming on November 29,1974. Although plaintiff had experienced, during the summer, some difficulty in keeping up with the projected schedule for the job, the delay in delivery of the unit ground the operation to a standstill for over two months, costing both parties substantial amounts by way of various delay expenses, and preventing ultimate completion of the building until May 1, 1975. During the delay, defendant ordered plaintiff to erect a temporary partition in the uncompleted building to protect the telephone equipment which had been installed.

Plaintiff brought suit to recover expenses occasioned by the delay in delivery of the air handling unit, together with the cost of the partition installed at defendant’s direction. Defendant counterclaimed for its own expenses resulting from the delay. Following a trial to the court sitting without a jury, both claims for recovery due to delay were dismissed, but defendant was ordered to reimburse plaintiff for the cost of the partition.

Plaintiff seeks recovery of losses due to the delay, on the theory that the defendant breached an implied warranty by issuing bids on a contract, the particulars of which were impossible to complete within the specified time; defendant denies the existence of such a warranty, asks that the ruling dealing with the partition be reversed, and that plaintiff recompense defendant for its own losses due to the belated delivery. In support of their respective theories of recovery, both parties cite acts and omissions dating all the way back to March 2, 1974. Curiously, neither party, pursuant to this appeal, addressed itself to the impact upon their claims of the two change orders signed by the parties during the course of their dealings.

It is well-settled law that the parties to a contract may, by mutual consent, alter all or any portion of that contract by agreeing upon a modification thereof. 3 Where such a modification is agreed upon, the terms thereof govern the rights and obligations of the parties under the contract, and any pre-modification contractual rights which conflict with the terms of the contract as modified must be deemed waived or excused. 4 Where a party’s expectations under a contract are frustrated, he may seek *1192 recovery from the other party only if his injury is the direct result of a breach of the contract as modified. 5

Article 13 of the “general conditions” section of the contract here under consideration sets forth the specific means whereby changes in the contractual agreement should come about.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hanks v. Anderson
D. Utah, 2024
Arlington Management v. Urology Clinic
2021 UT App 72 (Court of Appeals of Utah, 2021)
Errato v. American Express Co.
D. Connecticut, 2019
Glenn v. Reese
2009 UT 80 (Utah Supreme Court, 2009)
Low v. City of Monticello
2002 UT 90 (Utah Supreme Court, 2002)
Fisher v. Fisher
907 P.2d 1172 (Court of Appeals of Utah, 1995)
Western Surety Co. v. Murphy
754 P.2d 1237 (Court of Appeals of Utah, 1988)
Ted R. Brown & Associates, Inc. v. Carnes Corp.
753 P.2d 964 (Court of Appeals of Utah, 1988)
J & M Construction, Inc. v. Southam
722 P.2d 779 (Utah Supreme Court, 1986)
Shintech Inc. v. Group Constructors, Inc.
688 S.W.2d 144 (Court of Appeals of Texas, 1985)
Bradshaw v. Burningham
671 P.2d 196 (Utah Supreme Court, 1983)
General Leasing Co. v. Manivest Corp.
667 P.2d 596 (Utah Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
606 P.2d 1189, 1980 Utah LEXIS 855, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rapp-v-mountain-states-telephone-telegraph-co-utah-1980.