Interstate Contracting Corp. v. City of Dallas

407 F.3d 708, 2005 U.S. App. LEXIS 6981, 2005 WL 928593
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 22, 2005
Docket02-10138
StatusPublished
Cited by33 cases

This text of 407 F.3d 708 (Interstate Contracting Corp. v. City of Dallas) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interstate Contracting Corp. v. City of Dallas, 407 F.3d 708, 2005 U.S. App. LEXIS 6981, 2005 WL 928593 (5th Cir. 2005).

Opinion

DAVIS, District Judge:

In this breach of contract and breach of warranty case, the City of Dallas appeals a jury verdict awarding Interstate Contracting Corporation $3,046,964. Because the contract’s unambiguous language bars all of ICC’s claims, we reverse the trial court’s judgment and render judgment that Interstate Contracting Corporation take nothing.

BACKGROUND 2

On September 14, 1994, the City of Dallas, Texas (the “City”) and Interstate Contracting Corporation (“ICC”) entered into a fixed sum contract for levee construction around a City water treatment plant; the excavation of two areas to create storm water detention lakes; and some miscellaneous work including trash removal, surveying, and linear depth checking. ICC then entered into two written subcontracts with Mine Services, Inc. (“MSI”) for the levee construction and the excavation of the storm water detention lake.

To the extent it met specifications, the material excavated for the lakes was to be used as fill, material for the levees. In October 1994, MSI began work by mobilizing, surveying, and dewatering the Interi- or Borrow Lake (“IBL”), one of the “borrow” sites the City designated as a source of fill material. Shortly after work began, MSI discovered that the materials in the IBL were not suitable as fill for the levees, as MSI had expected.

Because the excavation did not yield sufficient quantities of suitable material, MSI manufactured fill material by mixing sand with the limited quantities of clay. This substantially decreased MSI’s productivity and increased its costs. The contract did not address manufacturing fill material. The parties discussed using fill from other sites, but MSI believed the contract did not designate those areas as borrow sites. Using those sources was also more expensive than the manufacturing process, and MSI persisted in manufacturing fill.

ICC informed the City of MSI’s increased work on March 1, 1995, but the *712 City indicated it would deny ICC’s claims. The City, through the claims process, also denied claims for increased costs regarding trash removal, linear depth checking, surveying, removing buried debris, and delay.

ICC filed this suit against the City on MSI’s behalf for breach of contract, quantum meruit, breach of implied warranty, and fraudulent inducement. 3 After an eleven day trial, the jury found that the City breached its contract with ICC by failing to pay ICC’s additional expenses relating to: (1) unanticipated subsoil conditions, (2) trash removal, (3) linear depth checking, (4) survey costs, and (5) delays caused by the City. The jury also found the City breached an implied warranty to provide accurate and suitable plans and specifications in light of subsoil conditions at the project site. In 2002, the City appealed this judgment, raising sixteen legal and evidentiary issues. Because there was no controlling Texas precedent, this court certified two questions to the Supreme Court of Texas regarding whether ICC could bring these claims on MSI’s behalf. 320 F.3d at 539. In 2004, the Supreme Court of Texas answered the certified questions by holding that a general contractor can bring claims on a subcontractor’s behalf and setting forth the requirements for doing so. 135 S.W.3d at 605. We issue this opinion resolving the remaining issues presented in this appeal.

STANDARD OF REVIEW

While we review the trial court’s conclusions of law de novo, we uphold a jury’s verdict unless it lacks a legally sufficient basis. Hiltgen v. Sumrall, 47 F.3d 695, 699-700 (5th Cir.1995); Watkins v. Petro-Search, Inc., 689 F.2d 537, 538 (5th Cir.1982). We review the evidence and all reasonable inferences in the light most favorable to the jury’s verdict. Id. at 700. Sitting as an Erie court, we rule on the issues as the Texas Supreme Court would rule. Hanson Prod. Co. v. Ams. Ins. Co., 108 F.3d 627, 629 (5th Cir.1997).

PRINCIPLES OF CONTRACT INTERPRETATION

We review the district court’s contract interpretation de novo. T.L. James & Co. v. Traylor Bros. Inc., 294 F.3d 743, 746 (5th Cir.2002) (citing Musser Davis Land Co. v. Union Pac. Res., 201 F.3d 561, 563 (5th Cir.2000)). Accordingly, we “review the record independently and under the same standard that guided the district court.” Id. (quoting Am. Totalisator Co. v. Fair Grounds Corp., 3 F.3d 810, 813 (5th Cir.1993)). Under Texas law, determining whether a contract is unambiguous and interpreting an unambiguous contract are questions of law. Leasehold Expense Recovery, Inc. v. Mothers Work, Inc., 331 F.3d 452, 456 (5th Cir.2003). The court’s primary concern is to enforce the parties’ intent as contractually expressed, and an unambiguous contract will be enforced as written. Id. If a question relating to a contract’s construction or ambiguity arises, the court examines the contract’s wording in context of the surrounding circumstances. Watkins, 689 F.2d at 538. If the contract is then susceptible to only one interpretation, it is unambiguous. Id. Determining the parties’ intent when expressed in an ambiguous contract is a question of fact. Id.

ICC’S STANDING TO BRING MSI’S CLAIMS

Although MSI and the City did not have privity of contract, ICC brought claims *713 against the City on MSI’s behalf. The City argues that privity of contract is an essential element to any contract-based action. ICC argues that the district court was correct in allowing ICC to present MSI’s claims on a pass-through basis. 4

Because there was no controlling precedent to determine whether a general contractor could bring pass-through claims against an owner on a subcontractor’s behalf, we certified the following questions to the Supreme Court of Texas:

(1) Does Texas law recognize pass-through claims, i.e., may a contractor assert a claim on behalf of its subcontractor against the owner when there is no privity of contract between the subcontractor and the owner?
If the first question is answered in the negative, then the remaining question need not be reached. However, if the first question is answered in the affirmative, the following question must be reached:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frew v. Young
Fifth Circuit, 2022
D2 Excavating, Incorporated v. Thompson Thrift Con
973 F.3d 430 (Fifth Circuit, 2020)
Ryder v. Shell Oil Co.
131 F. Supp. 3d 635 (S.D. Texas, 2015)
Carla Frew v. Thomas Suehs
780 F.3d 320 (Fifth Circuit, 2015)
In re Superior Tomato-Avocado, Ltd.
481 B.R. 866 (W.D. Texas, 2012)
State Farm Fire & Casualty Co. v. Matthew Lange, e
480 F. App'x 309 (Fifth Circuit, 2012)
City of San Antonio v. Valemas, Inc.
Court of Appeals of Texas, 2012

Cite This Page — Counsel Stack

Bluebook (online)
407 F.3d 708, 2005 U.S. App. LEXIS 6981, 2005 WL 928593, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interstate-contracting-corp-v-city-of-dallas-ca5-2005.