City of Houston v. L. J. Fuller, Inc.

311 S.W.2d 285, 1958 Tex. App. LEXIS 1850
CourtCourt of Appeals of Texas
DecidedMarch 6, 1958
Docket13187
StatusPublished
Cited by22 cases

This text of 311 S.W.2d 285 (City of Houston v. L. J. Fuller, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Houston v. L. J. Fuller, Inc., 311 S.W.2d 285, 1958 Tex. App. LEXIS 1850 (Tex. Ct. App. 1958).

Opinion

BELL, Chief Justice.

This suit was brought by appellee to recover $7,431.40 allegedly the balance due under a contract it had performed for the appellant, which called for construction of a sanitary sewer line north of Liberty Road and south of Kashmere Gardens. On trial before the court without a jury, judgment was rendered for the amount for which suit was brought, plus $1,000 as attorney’s fees, attorney’s fees being allowed under Article 2226, Revised Civil Statutes, because suit was to recover for labor and material furnished.

On December 31, 1952, the contract was duly executed. Generally, it provides that appellee shall within 120 days construct the sewer line according to the plans and specifications which are made a part of the contract. The consideration stated was $67,-784. There is a general form of contract, which is printed, which was used by appellant. In this opinion where we use “general contract” we refer to such printed form as distinguished from the plans, specifications or special provisions, though the latter are by reference a part of the contract to be performed by appellee.

The general contract provided that appel-lee should furnish all tools, labor, material, machinery and appliances for the construction of the sanitary sewer in accordance with the plans, specifications and drawings of the Director of Public Works and Engineering and should construct such sewer in a good, sound and workmanlike manner. While the stated consideration in the general contract is $67,784, this amount represents the aggregate of the unit prices contained in the bid of appellee. Of course, the bid is expressly made a part of the contract. The general contract provides that when the work has been completed in accordance with the plans and specifications and has been accepted by the appellant, the appellant shall pay appellee “The unit prices set out in full in the contractor’s bid proposal.” At this point, it should be noticed that the bid sheets are composed of the following columns headed in the manner stated:

The bid sheets are those furnished by appellant and are mimeographed. The first three columns are filled in by the appellant so as to give the bidder the items on which he bids, the unit of measure and the approximate quantity. The last two columns are filled in on the typewriter and are the amounts bid by the appellee — first, his unit bid, and next, the total for each item. The contractor’s proposal signed by appellee states that appellee proposes to construct the sanitary sewer and appurtenances in *287 accordance with the enumerated plans and specifications “for the following unit prices.” The general contract in paragraph 4 provides as follows:

“The contractor has carefully examined the surface of the site and has made sufficient test holes to fully satisfy himself that such site is a correct and suitable one for this work and he assumes full responsibility therefor. The provisions of this contract shall control any inconsistent provisions contained in the specifications. All plans and specifications have been read and carefully considered by the Contractor, who understands the same and agrees to their sufficiency for the work to be done.”

Paragraph 8 of such contract is as follows :

“The plans, profiles and specifications approved by the City Council are a part of this contract. The following are in particular, whether or not the same be attached hereto, a part of this contract and every covenant and undertaking therein is as fully binding upon the parties hereto as if here set forth at length, to-wit: (a) The Notice to Bidders and the Contractor’s Bid Proposal, (b) Affidavit of non-interest on the Part of City Officials, Employees, etc.; (c) Specifications, ‘General Conditions,’ Form E-10, Revised June 1, 1948, and (d) All of those specifications and drawings which are referred to in the Contractor’s Bid Proposal. In case of conflict, any provision of the foregoing document shall prevail over any conflicting provision in any of the specifications, and any provision in a special item or specification pertaining particularly to the project herein referred to shall control over any inconsistent provision of the ‘General Conditions.’ ”

Paragraph 22 of the “Specifications— General Conditions” reads as follows:

“Local Conditions. — Bidders shall satisfy themselves as to local conditions affecting the work, and no information derived from maps, plans, specifications, profiles or drawings, or from the Engineer or his assistants, will relieve the Contractor from any work or from fulfilling all of the terms of his. contract. The accuracy of the interpretation of the facts disclosed by bor-ings or other preliminary investigations is not guaranteed. Each bidder or his representative should visit the site of the work and familiarize himself with local conditions; failure to do so when intelligent preparation of bids depends on a knowledge of local conditions may be considered sufficient cause for rejecting a proposal.”

There is a mimeographed sheet entitled' “Special Provisions” and this special provision reads as follows:

“Special Item: ‘Sand Stabilized Shell in Trench Bottom’ — Where the earth in the trench bottom does not, in the opinion of the engineer, provide a suitable foundation for the sewer, the contractor shall, where ordered by the engineer, place sand stabilized shell in the trench bottom, under, around and over the sewer. Where this work is ordered, the contractor will be provided with a special plan or other instruction showing the depth of this material to be placed below the grade of the sewer and the height of material above the grade of the sewer.”

In the Specifications, Item 3:14, that especially apply to sewer construction is this-provision:

“Special plans for construction of sewers in unstable soil will be provided as found necessary during the progress of the work. The contractor will be paid for such work at the unit prices bid for items involved, as concrete,, timber, or any other items upon which unit prices have been secured andi deemed advisable to use.”

*288 These are the parts of the contract which we deem controlling in the disposition of this appeal.

The appellee in his petition alleges that he examined the construction site and drilled numerous test holes to a point 1 foot below grade depth and this investigation revealed a suitable site for this construction work. It further alleges that as provided in said contract, as work progressed, the City Engineer directed that between stations six plus 30 on Salina Street and IS plus 11 on Bigelow Street appellee place sand stabilized shell in the trench bottom. The contract did not state how much shell was to be placed in the trench bottom, but left this to be determined as work progressed. Between these stations, when this area was reached, the City Engineer directed that 4 to 6 inches of shell be placed. This was done. Before all of the work was completed, it was discovered that there were five breaks in the line between the stations mentioned.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D2 Excavating, Incorporated v. Thompson Thrift Con
973 F.3d 430 (Fifth Circuit, 2020)
Interstate Contracting Corp. v. City of Dallas
407 F.3d 708 (Fifth Circuit, 2005)
IT Corp. v. Motco Site Trust Fund
903 F. Supp. 1106 (S.D. Texas, 1994)
Lake LBJ Municipal Utility District v. Coulson
839 S.W.2d 880 (Court of Appeals of Texas, 1992)
City of Austin v. North Austin State Bank
631 S.W.2d 564 (Court of Appeals of Texas, 1982)
Turner, Collie & Braden, Inc. v. Brookhollow, Inc.
624 S.W.2d 203 (Court of Appeals of Texas, 1981)
Potler v. MCP Facilities Corp.
471 F. Supp. 1344 (E.D. New York, 1979)
Scott v. Abilene Independent School District
438 F. Supp. 594 (N.D. Texas, 1977)
Brown-McKee, Inc. v. Western Beef, Inc.
538 S.W.2d 840 (Court of Appeals of Texas, 1976)
Southwestern Bell Telephone Co. v. Chrisman Construction Co.
529 S.W.2d 586 (Court of Appeals of Texas, 1975)
Board of Regents of the University of Texas v. S & G Construction Co.
529 S.W.2d 90 (Court of Appeals of Texas, 1975)
City of San Marcos v. Lower Colorado River Authority
508 S.W.2d 403 (Court of Appeals of Texas, 1974)
Cole v. City of Houston
442 S.W.2d 445 (Court of Appeals of Texas, 1969)
State v. F & C ENGINEERING COMPANY
438 S.W.2d 647 (Court of Appeals of Texas, 1969)
Renault, Inc. v. City of Houston
415 S.W.2d 948 (Court of Appeals of Texas, 1967)
Willis v. City of Lubbock
385 S.W.2d 617 (Court of Appeals of Texas, 1964)
Housing Authority of City of Dallas v. Hubbell
325 S.W.2d 880 (Court of Appeals of Texas, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
311 S.W.2d 285, 1958 Tex. App. LEXIS 1850, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-houston-v-l-j-fuller-inc-texapp-1958.