Coryell v. Dubois Borough

75 A. 25, 226 Pa. 103, 1909 Pa. LEXIS 883
CourtSupreme Court of Pennsylvania
DecidedOctober 11, 1909
DocketAppeal, No. 266
StatusPublished
Cited by10 cases

This text of 75 A. 25 (Coryell v. Dubois Borough) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coryell v. Dubois Borough, 75 A. 25, 226 Pa. 103, 1909 Pa. LEXIS 883 (Pa. 1909).

Opinion

Opinion by

Mr. Justice Stewart,

The plaintiff company engaged by written contract to construct for the borough of Dubois, as part of a projected municipal water supply system, a section of the work designated in the plan as Anderson Creek dam or reservoir, in accordance with certain specifications, for the sum of $24,482.30. This price was based on estimates furnished by the borough as to the probable amount of work and material that would be required. Had there been no departure from the original plans and specifications, these estimates would have proved sufficiently accurate, and no controversy would have arisen. It rarely happens, however, that constructive work of this character is completed in exact accordance with the original specifications, for the reason that actual conditions below surface can only be known as the work is proceeded with, and disappointment with respect to these necessarily involves change in some degree. This contract contemplated such contingency, and, as we shall see, provided against it, both with respect to the rights of the borough, and the compensation to be paid the contractor. In the specifications furnished prospective bidders the work was classified according to the kind and character, as, for instance, grubbing, excavating, masonry, puddling, etc, each being made a distinct item, and with each item was given the approximate amount required under the estimates. The plaintiffs' bid specified in detail the rate price at which it would furnish the labor and mate[105]*105rial for each separate item. The sum total, based on the approximate quantities of each, was $24,482.30, and this was expressed in the contract as the price the borough was to pay for the completed section. The contract provided that the water committee, representing the borough, should have the right to make any alterations in extent, dimensions, form or plan of the work either before or after the commencement of construction, and further, that for any increase in quantity of work or material that should result from any such change the plaintiff company should be paid at contract rate for work or material of its class. The first disappointment in estimates came in connection with the excavation for the dam. It was expected that rock bottom would be reached at a depth of seven feet below the spillway at the breast, and at twenty-seven feet below the extreme top at the other part of the dam, and the amount of excavating that would be required was estimated at 7,000 cubic yards. These depths were reached without discovering rock bottom, and the water committee required the plaintiffs to continue excavating. The work was proceeded with until the amount excavated more than doubled the original estimate. As a result, the amount and extent of masonry required for the breast of the dam was correspondingly increased, that is to say, from 1,200 cubic yards to 2,944; and instead of a surface of ten acres a clearing of nearly forty-four acres was required. If this additional work in kind and character fell within the classifications defined in the specifications, then, barring a certain disputed item of credit to be considered later, the plaintiff company has been paid in full. Its contention, 'however, is that it was extra work for which no price was fixed in the contract, and in the present action it seeks to recover as on a quantum valebat for work and labor done in this regard. The case was tried without a jury, and resulted in a judgment for the plaintiffs in the snm of $32,135.91. The appeal challenges both the facts as found by the learned trial judge and his conclusions of law as well. However lacking in support some of the findings of fact may be, these are not only of questionable relevancy, but, with a single exception to be referred to later on, they are in [106]*106themselves unimportant; for after all the case turns upon the construction of the contract between the parties. The admitted facts are quite sufficient to disclose the relation of- the parties to each other and to the subject-matter, while the contract itself is neither obscure nor ambiguous. What the parties contracted for was a completed dam or reservoir. This involved more or less uncertainty as to the amount and extent of work required, and against this provision was made — additional work over and above the estimate was to be paid for at contract rate for work of its class. It involved as well a possibility that conditions unforeseen would require a kind and character of work unlike that required to complete the work according to the original plans. Against this also was provision made — such work is designated in the contract as “extra,” and is there thus defined: “It is understood that extra work, as considered in the contract or specifications, is work that the contractor is required to perform and for which no price is fixed in the contract, specifications or proposal, and which is not covered by the contract sum or the specifications.” The question then resolves itself into this, Was this work for which plaintiffs claim additional, or was. it extra? The amount of work claimed in excess of the original estimate is not in dispute; nor is it denied that the plaintiffs were required by the borough to do this work. Manifestly it is not covered by the contract sum of $24,482.30. All that remains, therefore, to inquire is, Was it work for which a rate was fixed in the contract; in other words, did the work fall within the classification? It is not attempted to differentiate it in any way from that classified in connection with the original estimates except in the matter of cost. The masonry was the same in kind and character; so too the excavation, and so too the clearing; the difference was in the facility in doing these several kinds of work. As the depth was increased, more labor was required to accomplish the same results, and other instrumentalities had to be employed and other conveniences provided. A necessary result of increased depth would be increase of cost. The learned trial judge held this circumstance — increase of cost to the contractor — conclusive in favor of plaintiffs’ con[107]*107tention that the work was not embraced within the classification, but was extra within the meaning of that term as used in the contract. We quote his ruling: “The true test of classification must be the cost of doing the work, and any change of the conditions which would materially increase the cost must necessarily change the classification. The evidence clearly shows that the increased depth greatly increased the cost of doing the work requiring different and more expensive equipment. This applies also to the excess masonry. Not only was the expense of placing the masonry in position increased greatly, but the large amount of the increase, from 1,200 yards to 2,944 yards, must be considered in determining whether the same conditions existed. The cost of the masonry was largely controlled by the convenience of obtaining the stone. The evidence shows that there was sufficient in the vicinity to have supplied the amount named in the specifications. The increase of 1,744 yards changed the conditions which existed when the contract was made. The plaintiff was required to go to a great distance and to a very large expense to procure the extra amount of stone, and it would be unreasonable to require him under such changed conditions to be bound to supply the same at the price named.” To this we cannot give our assent. It would determine the question in controversy not by the terms of the contract, but by a supposed rule of construction which is supported by no citation of authority, and which bears marks of too recent invention.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Electri-Tech, Inc. v. Radnor Twp.
Commonwealth Court of Pennsylvania, 2025
City of Houston v. L. J. Fuller, Inc.
311 S.W.2d 285 (Court of Appeals of Texas, 1958)
Bradshaw v. Wolfe City
3 S.W.2d 527 (Court of Appeals of Texas, 1927)
Carroll Electric Co. v. Irwin & Leighton
80 Pa. Super. 438 (Superior Court of Pennsylvania, 1923)
Texter v. Wachs
73 Pa. Super. 19 (Superior Court of Pennsylvania, 1919)
Ahrens v. Reading
104 A. 511 (Supreme Court of Pennsylvania, 1918)
Ferro-Concrete Co. v. Northampton County
91 A. 506 (Supreme Court of Pennsylvania, 1914)
Ritchie v. City of Topeka
138 P. 618 (Supreme Court of Kansas, 1914)
Pressy v. McCornack
84 A. 427 (Supreme Court of Pennsylvania, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
75 A. 25, 226 Pa. 103, 1909 Pa. LEXIS 883, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coryell-v-dubois-borough-pa-1909.