Ritchie v. City of Topeka

138 P. 618, 91 Kan. 615, 1914 Kan. LEXIS 89
CourtSupreme Court of Kansas
DecidedFebruary 7, 1914
Docket18,759
StatusPublished
Cited by17 cases

This text of 138 P. 618 (Ritchie v. City of Topeka) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ritchie v. City of Topeka, 138 P. 618, 91 Kan. 615, 1914 Kan. LEXIS 89 (kan 1914).

Opinion

The opinion of the court was delivered by

Johnston, C. J.:

The controversy in this action grew out of two contracts between the parties, one fox* the paving of streets and alleys, and an earlier one for the construction of a sewer. John Ritchie, the appellant, brought the action to recover $12,-343.75 for the paving of streets and alleys in the city of Topeka under a contract with the city made in April, 1909, in which it was stipulated that the work was to be completed on or before January 1, 1910, and that for every day that the work remained uncompleted after that time Ritchie should forfeit $10 per day. The contract was not fully executed until October 27, 1910, and at that time the city engineer estimated that there was due *617 Ritchie the sum sued for. The city answered, setting-up a counterclaim of $3000 as liquidated damages, the: amount alleged to have been forfeited by Ritchie by-delaying the completion of the paving for three hundred days after the stipulated time. The city also-pleaded a set-off of $23,665.50 arising from alleged overpayments on a sewer contract entered into by Ritchie and his partner, Hanley, with the city on March 20, 1905. As to the set-off, it was alleged that Ritchie- and his partner received payment for certain sewers, not constructed, and that the city engineer, without the consent or knowledge of the city, included in his estimate such overcharges to the amount of about $5740.50. It was further alleged that the city engineer raised grades and changed the size of sewers, thus relievingRitchie of the excavation of about 13,000 cubic yards, provided for in the contract, and gave estimates of the work as if it had been fully performed in accordance-with the requirements of the contract, and that in this, way Ritchie was overpaid the sum of about $7800. It. was further alleged that there was an overcharge in. the rock excavations to the extent of $10,125, and that-the city engineer included this overcharge in his estimates and thereby enabled Ritchie to obtain payment, for work which was not done. In his reply Ritchie alleged that the delay in completing the paving contract was caused by the city, and further, that if the city-had any right to claim a forfeiture for failure to complete the contract within the specified time it had been waived. As to the set-off claimed under the sewer contract Ritchie replied that the work was done in accordance with the directions of the city engineer, who was acting for the city, and that no changes in the work-done or material furnished were made except such as were ordered by the city engineer with the knowledge-of the city. He also averred that work not included in-the contract was done under the direction and approval of the city engineer in place of work contracted for- *618 but not performed, and that this substitution was made with the knowledge of the city, and that all the money paid to him under the sewer contract had been fully earned and was justly due. .

The pleadings disclosed that a trial of the case involved an examination of a long and intricate account between the parties, which included many items and was too complicated to be tried by a jury, and the court rightly determined it was a referable one and on its •own motion referred the case to Robert Stone, Esquire, with power to try the issues and report his findings of fact and conclusions of law to the court within a fixed time. Upon a trial by the referee he found that Ritchie had furnished material and done work under the paving contract for which he was entitled to $10,941.38, but that because of his delay in completing the contract ihe city was entitled, to a deduction of $2000, which left a balance due Ritchie under that contract of $8941.33. He also found that Ritchie was indebted to the city for payments made to him on overcharges under the sewer contract in the sum of $20,173.46 with interest thereon from December 18, 1907, at six per cent per annum, and that the city was entitled to a judgment against Ritchie in the sum of $16,035.48. Ritchie moved the •court for judgment on the findings of fact made by the referee, contending that the conclusions of law were not justified by the facts found. This motion was •overruled, as was one made by him to set aside the report of the referee. Pinal judgment was then rendered by the court upon the conclusions of the referee in favor of the city for $16,035.48 with interest thereon at the rate of six per cent per annum from October 23, 1912.

It is contended on this appeal that the forfeiture of $2000 for delay in finishing the paving and the deduction of that sum from the amount due Ritchie for the paving done by him is error. This contention is based on two grounds, one that the city in fact caused the *619 delay by its own wrong and neglect, and the other that it had effectually waived performance of the contract within the stipulated time. The finding of fact relating to the responsibility of the city for the delay of Ritchie is:

“John Ritchie was delayed one hundred days in the performance and completion of such work by reason of the failure of the said City of Topeka to move certain poles, water and gas pipes, and to lower certain water and gas pipes in said streets and alleys, and to designate the kind of catch basins to be used in certain localities.”

In December, 1909, Ritchie asked the city for an extension of time in which to finish the paving, stating that circumstances over which he had no control would prevent him from completing the work within the stipulated time. The request, which was in writing, was received by the mayor and commissioners, and while they did not take any formal action on the request they did permit him to go on with the work and did continue to approve and pay his estimates as the work progressed the same as if the time of completion had not been limited. Until June 3, 1910, no objection was made by the city, but at that time a resolution was passed declaring that the city would claim damages at the rate of $10 per day for failure of Ritchie to complete the contract in accordance with its terms. On July 7, 1910, Ritchie presented to the city an application for an extension of time to complete the contract, alleging that there had been a distinct understanding between the parties that by reason of certain obstacles which he had met and the delays occasioned by the changes of grade made by the city engineer it was impossible to finish the paving at an earlier time. The mayor and commissioners did not formally grant the application, but after hearing it at a regular session attended by Ritchie, where all of the commissioners were present, it was definitely agreed that Ritchie might *620 go on and complete the contract, not at any specified time but as soon as it could reasonably be done. These facts are sufficient to show a waiver of the forfeiture clause of the contract and of the stipulated damages to be paid in case of delay in completing the work. The mere fact that the city allowed Ritchie to continue the work did not, of itself, operate as a waiver of the right to insist on a forfeiture, as the terms of the contract itself contemplated that work might possibly be done after the stipulated time, but the conduct of the city fairly indicated an acquiescence in the delay and a waiver of any right that it had to stipulated damages because of delay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hutton Contracting Co. v. City of Coffeyville
487 F.3d 772 (Tenth Circuit, 2007)
Thompson v. L. J. Voldahl, Inc.
188 N.W.2d 377 (Supreme Court of Iowa, 1971)
Neale Construction Co. v. Topeka Township Sewage District No. 1
285 P.2d 1086 (Supreme Court of Kansas, 1955)
Erwin v. Leonard
203 P.2d 207 (Supreme Court of Kansas, 1949)
Grady v. City of Livingston
141 P.2d 346 (Montana Supreme Court, 1943)
Sioux Falls Taxpayers Ass'n v. City of Sioux Falls
7 N.W.2d 136 (South Dakota Supreme Court, 1942)
Bartron v. Codington County
2 N.W.2d 337 (South Dakota Supreme Court, 1942)
J. D. Adams Co. v. Dor Township
113 P.2d 138 (Supreme Court of Kansas, 1941)
City of Frankfort v. Warders
240 P. 589 (Supreme Court of Kansas, 1925)
Seaside, City of v. Randles
180 P. 319 (Oregon Supreme Court, 1919)
Irelan v. Portland
179 P. 286 (Oregon Supreme Court, 1919)
Dolman v. Kaw Construction Co.
176 P. 145 (Supreme Court of Kansas, 1918)
City of Topeka v. Ritchie
170 P. 1003 (Supreme Court of Kansas, 1918)
Humphrey v. Flaherty
158 P. 1112 (Supreme Court of Kansas, 1916)
City of Topeka v. Federal Union Surety Co.
213 F. 958 (Eighth Circuit, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
138 P. 618, 91 Kan. 615, 1914 Kan. LEXIS 89, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ritchie-v-city-of-topeka-kan-1914.