Ritchie v. City of Topeka

138 P. 618, 91 Kan. 615, 1914 Kan. LEXIS 89
Supreme Court of Kansas·Decided February 7, 1914·No. 18,759·Published·Cited by 17 cases

Opinion

The opinion of the court was delivered by

Johnston, C. J.:

The controversy in this action grew out of two contracts between the parties, one fox* the paving of streets and alleys, and an earlier one for the construction of a sewer. John Ritchie, the appellant, brought the action to recover $12,-343.75 for the paving of streets and alleys in the city of Topeka under a contract with the city made in April, 1909, in which it was stipulated that the work was to be completed on or before January 1, 1910, and that for every day that the work remained uncompleted after that time Ritchie should forfeit $10 per day. The contract was not fully executed until October 27, 1910, and at that time the city engineer estimated that there was due *617 Ritchie the sum sued for. The city answered, setting-up a counterclaim of $3000 as liquidated damages, the: amount alleged to have been forfeited by Ritchie by-delaying the completion of the paving for three hundred days after the stipulated time. The city also-pleaded a set-off of $23,665.50 arising from alleged overpayments on a sewer contract entered into by Ritchie and his partner, Hanley, with the city on March 20, 1905. As to the set-off, it was alleged that Ritchie- and his partner received payment for certain sewers, not constructed, and that the city engineer, without the consent or knowledge of the city, included in his estimate such overcharges to the amount of about $5740.50. It was further alleged that the city engineer raised grades and changed the size of sewers, thus relievingRitchie of the excavation of about 13,000 cubic yards, provided for in the contract, and gave estimates of the work as if it had been fully performed in accordance-with the requirements of the contract, and that in this, way Ritchie was overpaid the sum of about $7800. It. was further alleged that there was an overcharge in. the rock excavations to the extent of $10,125, and that-the city engineer included this overcharge in his estimates and thereby enabled Ritchie to obtain payment, for work which was not done. In his reply Ritchie alleged that the delay in completing the paving contract was caused by the city, and further, that if the city-had any right to claim a forfeiture for failure to complete the contract within the specified time it had been waived. As to the set-off claimed under the sewer contract Ritchie replied that the work was done in accordance with the directions of the city engineer, who was acting for the city, and that no changes in the work-done or material furnished were made except such as were ordered by the city engineer with the knowledge-of the city. He also averred that work not included in-the contract was done under the direction and approval of the city engineer in place of work contracted for- *618 but not performed, and that this substitution was made with the knowledge of the city, and that all the money paid to him under the sewer contract had been fully earned and was justly due. .

The pleadings disclosed that a trial of the case involved an examination of a long and intricate account between the parties, which included many items and was too complicated to be tried by a jury, and the court rightly determined it was a referable one and on its •own motion referred the case to Robert Stone, Esquire, with power to try the issues and report his findings of fact and conclusions of law to the court within a fixed time. Upon a trial by the referee he found that Ritchie had furnished material and done work under the paving contract for which he was entitled to $10,941.38, but that because of his delay in completing the contract ihe city was entitled, to a deduction of $2000, which left a balance due Ritchie under that contract of $8941.33. He also found that Ritchie was indebted to the city for payments made to him on overcharges under the sewer contract in the sum of $20,173.46 with interest thereon from December 18, 1907, at six per cent per annum, and that the city was entitled to a judgment against Ritchie in the sum of $16,035.48. Ritchie moved the •court for judgment on the findings of fact made by the referee, contending that the conclusions of law were not justified by the facts found. This motion was •overruled, as was one made by him to set aside the report of the referee. Pinal judgment was then rendered by the court upon the conclusions of the referee in favor of the city for $16,035.48 with interest thereon at the rate of six per cent per annum from October 23, 1912.

It is contended on this appeal that the forfeiture of $2000 for delay in finishing the paving and the deduction of that sum from the amount due Ritchie for the paving done by him is error. This contention is based on two grounds, one that the city in fact caused the *619 delay by its own wrong and neglect, and the other that it had effectually waived performance of the contract within the stipulated time. The finding of fact relating to the responsibility of the city for the delay of Ritchie is:

“John Ritchie was delayed one hundred days in the performance and completion of such work by reason of the failure of the said City of Topeka to move certain poles, water and gas pipes, and to lower certain water and gas pipes in said streets and alleys, and to designate the kind of catch basins to be used in certain localities.”

Free access — add to your briefcase to read the full text and ask questions with AI

Ritchie v. City of Topeka, 138 P. 618, 91 Kan. 615, 1914 Kan. LEXIS 89 (kan 1914).

138 P. 618 (Ritchie v. City of Topeka) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hutton Contracting Co. v. City of Coffeyville
487 F.3d 772 (Tenth Circuit, 2007)
Thompson v. L. J. Voldahl, Inc.
188 N.W.2d 377 (Supreme Court of Iowa, 1971)
Neale Construction Co. v. Topeka Township Sewage District No. 1
285 P.2d 1086 (Supreme Court of Kansas, 1955)
Erwin v. Leonard
203 P.2d 207 (Supreme Court of Kansas, 1949)
Grady v. City of Livingston
141 P.2d 346 (Montana Supreme Court, 1943)
Sioux Falls Taxpayers Ass'n v. City of Sioux Falls
7 N.W.2d 136 (South Dakota Supreme Court, 1942)
Bartron v. Codington County
2 N.W.2d 337 (South Dakota Supreme Court, 1942)
J. D. Adams Co. v. Dor Township
113 P.2d 138 (Supreme Court of Kansas, 1941)
City of Frankfort v. Warders
240 P. 589 (Supreme Court of Kansas, 1925)
Seaside, City of v. Randles
180 P. 319 (Oregon Supreme Court, 1919)
Irelan v. Portland
179 P. 286 (Oregon Supreme Court, 1919)
Dolman v. Kaw Construction Co.
176 P. 145 (Supreme Court of Kansas, 1918)
City of Topeka v. Ritchie
170 P. 1003 (Supreme Court of Kansas, 1918)
Humphrey v. Flaherty
158 P. 1112 (Supreme Court of Kansas, 1916)
City of Topeka v. Federal Union Surety Co.
213 F. 958 (Eighth Circuit, 1914)