Neale Construction Co. v. Topeka Township Sewage District No. 1

285 P.2d 1086, 178 Kan. 359, 1955 Kan. LEXIS 283
CourtSupreme Court of Kansas
DecidedJuly 6, 1955
Docket39,817
StatusPublished
Cited by3 cases

This text of 285 P.2d 1086 (Neale Construction Co. v. Topeka Township Sewage District No. 1) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neale Construction Co. v. Topeka Township Sewage District No. 1, 285 P.2d 1086, 178 Kan. 359, 1955 Kan. LEXIS 283 (kan 1955).

Opinion

The opinion of the court was delivered by

Parker, J.:

This action, to recover an unpaid balance alleged to *360 be due and payable under its terms, is founded on a unit price contract entered into between the plaintiff and the defendant Sewage District for the construction of a sewer line. With issues joined on all questions relating to liability of the parties, under pleadings consisting of the plaintiff’s petition, the defendant’s answer and the plaintiff’s reply, all as finally amended, the cause came on for trial by the district court where defendant’s motion for judgment on plaintiff’s opening statement was ultimately sustained. Thereafter a judgment was rendered against plaintiff on such opening statement. However, because defendant had theretofore confessed judgment in its answer for the sum of $2,861.55 the trial court gave plaintiff judgment for that amount. The appeal is from the order sustaining the motion for judgment on the opening statement, the judgment as rendered, and from an order overruling a motion for a new trial.

The opinion in this case will be simplified at the outset by reference to certain matters having to do with the disposition of the cause, about which the record discloses there is implied if not express agreement between the parties. Those having that status will now be mentioned and can be stated thus:

1. Notwithstanding the scope of the notice of appeal the fundamental and all decisive issue involved is whether the trial court erred in holding as a matter of law that appellee was entitled to judgment on the appellant’s opening statement.

2. In reaching the decision just mentioned the trial court’s decision was founded on the premise no issues of fact were presented for determination by the opening statement, and other facts included therein by reference, because valid provisions of the contract, which were conditions precedent to appellant’s recovery, were not followed.

3. If the decision sustaining the motion for judgment on the opening statement is warranted by the record the judgment of $2,861.55 is proper by reason of the allegations of the appellee’s answer confessing judgment for that amount.

4. Since appellant’s opening statement specifically adopted and included by reference the allegations of its petition and all exhibits attached thereto, including the formal contract entered into between the parties, the facts alleged in the petition and such exhibits are to be regarded as a part of the opening statement and *361 all matters and things therein set forth must be considered together and liberally construed in determining its sufficiency.

5. Under its decisions (See West’s Kansas Digest, Trial, § 109, and Hatcher’s Kansas Digest [Rev. Ed.], Trial, § 69K) this court is committed to the rules (a) that no judgment can be rendered on an opening statement unless in the making of such statement it appears the party making it has admitted facts which necessarily and absolutely preclude his recovery and (b) that where in making such a statement a plaintiff admits or states facts having the force and effect just mentioned the court may close the case at once and give judgment against him.

The nature of the decisive issue on which this lawsuit depends is such that even if limits of time and space permitted it would not be necessary to detail the contents of appellant’s opening statement proper or the petition and exhibits incorporated therein by reference. Instead, for informative and other purposes essential to appellate review, it will suffice to quote a factual statement appearing in appellant’s own brief on which it relies to sustain its position the opening statement was sufficient to withstand the attack made against it by the motion for judgment; quote portions of the contract relied on by appellee as sustaining its position; and then direct attention to matters to which no reference whatsoever is made in the opening statement or in the petition.

The factual statement just mentioned, which we pause to note is based on averments to be found in both the opening statement and the petition, reads:

“On September 17, 1951, Hie plaintiff appellant Neale Construction Company entered into a written contract with the defendant appellee Topeka Township Sewage District No. 1 to construct a sewer. This sewer was to be built in an area to the southeast and southwest of the intersection of 29th Street and U. S. 75, near the south edge of Topeka, Kansas. The contract provided for varying prices according to Hie depth of the sewer and according to the type of soil or rock through which constructed, as well as for the number of manholes and their depths.
“The contract was based on a set of specifications and plans furnished by the appellee Sewage District to the appellant contractor. The estimated cost of construction made by the contractor appellant based on the sewer line as shown by the original plans was $19,196.33.
“The appellant contractor alleges that after the appellant’s bid had been accepted and sewer construction about 33-%% completed on November 9, 1951, when the appellees, acting through its agent, the engineer, changed the location of the sewer line. Appellant alleges that it was ordered by defendant to *362 construct the line as changed on the east leg of the sewer to run about 132 feet to the west of the location shown by the plans furnished by appellee and bid on by contractor.
“The appellant alleges this first change moved the line from a straight line through dirt to a southwest angle through a rock filled creek bed. Appellant alleges that said change resulted in an entirely different and more expensive digging classification and resulted in the contractor having to work in water and mud and having to pump water.
“Appellant further alleges that the change was made after 140 feet of 8 inch pipe had been Iayed along the bid on the route and that it would have been more expensive to reclaim than to leave said pipe in the ground.
“Appellant then alleges that on or about January 5, 1952, the defendants, through their engineer, K. E. Rector, directed the plaintiff to alter the location of the west leg of the sewer from that bid on by the contractor. The contractor appellant alleges that that resulted in the line being approximately 12 feet to the east and in a drainage ditch, whereas the line was to have been entirely in dirt. Appellant alleges that this second change resulted in requiring use of more expensive digging equipment and working in and having to pump water.
“Appellant also alleges that it had to rework Manhole No. 8 and that the defendant Sewer District allowed another sewer district to dump water into the line prior to defendant’s accepting the sewer.
“The appellant contractor sets up in its petition three important exhibits of this matter in an attempt to simplify a somewhat complicated matter. The Exhibit sets up the contract including proposals, etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

OK Johnson Electric, Inc. v. HESS-MARTIN CORPORATION
464 P.2d 206 (Supreme Court of Kansas, 1970)
Joplin Cement Co. v. White-Layton Mechanical Contractors, Inc.
356 P.2d 820 (Supreme Court of Kansas, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
285 P.2d 1086, 178 Kan. 359, 1955 Kan. LEXIS 283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neale-construction-co-v-topeka-township-sewage-district-no-1-kan-1955.