OK Johnson Electric, Inc. v. HESS-MARTIN CORPORATION

464 P.2d 206, 204 Kan. 478, 1970 Kan. LEXIS 374
CourtSupreme Court of Kansas
DecidedJanuary 24, 1970
Docket45,516
StatusPublished
Cited by6 cases

This text of 464 P.2d 206 (OK Johnson Electric, Inc. v. HESS-MARTIN CORPORATION) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
OK Johnson Electric, Inc. v. HESS-MARTIN CORPORATION, 464 P.2d 206, 204 Kan. 478, 1970 Kan. LEXIS 374 (kan 1970).

Opinion

The opinion of the court was delivered by

O’Connor, J.:

This was an action instituted under the provisions of K. S. A. 60-1110 by O. K. Johnson Electric, Inc., a subcontractor, against Hess-Martin Corporation, Inc., the prime contractor, and its surety to recover for labor and materials furnished in the con *479 struction of the White Lakes Shopping Center in Topeka. White Lakes Development, Inc., the owner of the shopping center, was made a third party defendant, and as a result of an indemnifying agreement with Hess, assumed the defense of the case. From an adverse judgment in the district court, Johnson has appealed.

For clarity, the parties will be referred to in the opinion! as Johnson (appellant), Hess and White Lakes (appellees).

In the fall of 1963 Hess contracted with White Lakes to build the shopping center. On October 24, 1963, Johnson entered into a cost-plus contract with Hess for the installation of electrical systems in the new center.

The subcontract provided in part that Johnson was to be paid all of its “direct cost,” plus 17% of the “direct cost,” not to exceed $51,000. “Direct cost” was defined to include materials, labor and “payroll taxes and insurance, including workmen’s compensation insurance and union fringe benefits. (14% of labor).” The “total direct cost” was to be determined upon completion of the contract and was subject to the approval of Hess and the architect.

Under the contract Hess agreed to make periodic payments to Johnson on or before the tenth of each month for all work done in the preceding month. Each monthly payment was to include Johnson’s gross payroll for the month, as well as labor, fringe benefits, payroll taxes and insurance, in support of which Johnson agreed to submit notarized payroll reports. The monthly payment was also to include a portion of the fixed fee due Johnson, computed by allowing a factor of 17% of all direct cost for the preceding month. When a total of 80% of the fixed fee had been paid, no further payments thereon were to be made until the project was completed.

Other pertinent portions of the subcontract read:

“8. . . .
“C. . . .
“Upon receipt of written notice that the work is ready for final inspection and acceptance, the Architect shall promptly make an inspection, and when he finds the work acceptable under this Contract and the Contract fully performed he shall promptly issue a final certificate, over his own signature, stating that the work provided for in this Contract has been completed and is accepted by him under the terms and conditions thereof, and that the entire balance found to be due the [sub-] Contractor, and noted in said final certificate, is due and payable.
*480 “Before issuance of final certificate the. Sub-Contractor [Johnson] shall submit evidence satisfactory to the Architect that all payrolls, material bills, and other indebtedness connected with the work have been paid. “D. The Contractor [Hess] through his agreement with the owner agrees to pay all material invoices that have been approved by the Contractor and the architect as aforesaid and all applicable sales and use taxes. Said payments shall be made direct and the Sub-Contractor shall be furnished with a non-negotiable copy of each check covering such payments. The Sub-Contractor agrees that it will furnish all material invoices to the Contractor in ample time to take advantage of all cash discounts.
“9. The Sub-Contractor agrees to use the utmost diligence in buying material and shall use all leverage of his command to secure the lowest possible prices with good quality. Sub-Contractor agrees to furnish when requested by the Contractor, evidence that the prices paid for, or proposed to be paid for, materials purchased are the lowest reasonably to be expected compared to the current market prices for such materials.
“10. The Sub-Contractor agrees to supply all labor that shall be necessary from time to time to meet the Contractor’s work schedule, but that it will not use any labor in excess of the amount necessary to meet said schedule. The Sub-Contractor agrees to comply with any reasonable requests o.f the Contractor regarding the amount of labor used from time to time in the performance of this contract.” (Emphasis added.)

The work called for by the subcontract was performed by Johnson over a period of approximately one year. Upon completion of the job, including the corrections required by the architect to make the job satisfactory, Johnson was told by the architect a “certificate of acceptance” had been issued. Thereupon, Johnson submitted its final bill in the amount of $54,391.64.

Meanwhile, in January 1965, an audit was made by an accountant of all the billings for “direct cost” submitted by Johnson. The accountant determined that $13,696.23 of the billings constituted excess charges over Johnson s actual expenditures for payroll taxes, insurance, and union benefits. This came about because all of Johnson s billings had included a flat 14% for these items. No question had been raised on any of the billings previous to that time. After the audit Johnson, for the first time, realized that Hess and White Lakes were placing a different interpretation on the “14% of labor” clause in the contract. Finally, on March 30, 1965, Johnson was paid,.and accepted, the sum of $39,750 without prejudice to any of the parties concerning the balance of its claim in the amount of $14,641.64.

This lawsuit was filed August 20, 1965. Johnson’s claim was stated in two parts.

*481 The first was for interest on various payments under the contract which were made later than the tenth of the month. Judgment was entered in favor of Johnson in the amount of $2,664.41 for the interest item, and no appeal has been taken from that portion of the judgment.

Johnson also claimed the $14,641.64 balance alleged to be due under the contract. Against this the appellees, Hess and White Lakes, asserted two defenses. A partial defense was that the “14% of labor” clause in the contract was ambiguous, and that Johnson was entitled only to actual taxes, insurance, and union fringe benefits instead of an arbitrary 14% of labor, which he had already been paid—a difference of $13,696.23. As to this defense, the trial court found that the contract was not ambiguous and that its express terms were controlling, regardless of the actual amount expended for these items. Appellees have not appealed from this ruling, and it is no longer an issue in the case.

The second defense, and the one with which we are concerned in this appeal, was that Johnson’s “total direct cost” had not been approved by Hess or the architect, as required by the contract, and that such refusal was justified because Johnson had used labor in excess of that necessary in performing the job.

The case was tried to the court without a jury.

Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neighbors Construction Co. v. Woodland Park at Soldier Creek, LLC
284 P.3d 1057 (Court of Appeals of Kansas, 2012)
May v. Ralph L. Dickerson Const. Corp.
560 So. 2d 729 (Mississippi Supreme Court, 1990)
State Highway Commission v. Brasel & Sims Construction Co.
688 P.2d 871 (Wyoming Supreme Court, 1984)
Thomas v. Dudrey
494 P.2d 1039 (Supreme Court of Kansas, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
464 P.2d 206, 204 Kan. 478, 1970 Kan. LEXIS 374, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ok-johnson-electric-inc-v-hess-martin-corporation-kan-1970.