Halvorson v. Blue Mt. Prune Growers Co-Op.

217 P.2d 254, 188 Or. 661
CourtOregon Supreme Court
DecidedNovember 1, 1949
StatusPublished
Cited by5 cases

This text of 217 P.2d 254 (Halvorson v. Blue Mt. Prune Growers Co-Op.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Halvorson v. Blue Mt. Prune Growers Co-Op., 217 P.2d 254, 188 Or. 661 (Or. 1949).

Opinions

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 663 Action by E. Halvorson and others, doing business as the Halvorson Construction Company, against the Blue Mountain Prune Growers Cooperative, on an account stated for balance allegedly due under a building contract.

From a judgment of the Circuit Court, Umatilla County, R.J. Green, J., in favor of plaintiffs, the defendant appealed.

The Supreme Court, Hay, J., held that under the contract the procurement of an architect's certificate by the contractors was a condition precedent to recovery of balance due, and that, in absence of allegation or proof that certificate had been procured or that requirement had been waived, the contractors could not recover on an account stated.

JUDGMENT REVERSED. The plaintiffs are building contractors. On April 2, 1945, they entered into a contract in writing with defendant to construct an addition to defendant's fruit-packing and storage plant at Milton-Freewater, Oregon. We shall refer to plaintiffs as "the contractors" and to defendant as "the owner".

The contract provided that the contractors should furnish all materials for the construction of the building, and perform all the work of construction, in accordance with certain drawings, specifications, and documents *Page 665 prepared by the architect. The work was to be completed on or before June 1, 1945, under penalty of $100 as liquidated damages for each calendar day's delay in completion beyond that date.

The contract price was $47,403, payable by monthly installments on or about the 10th day of each month, each such installment to cover 85 per cent of the work completed during the previous month. The amount of each payment was to be determined by the architect, and payment thereof authorized by his certificate.

The work was not finished within the time limited by the contract, but the contractors claim that it was completed on or before July 12, 1945. On that date, they submitted to the architect a "final estimate", whereby, having, as they said, completed the building, they claimed to be entitled to receive a balance of $33,934.02, computed as follows:

"Contract for construction of addition to warehouse 47,403.00 Plus additional work 1,531.02 ___________ 48,934.02 Less previous payment 15,000.00 ___________ Balance due $33,934.02"

A statement of the details of the claimed additional work was appended.

On July 18, 1945, the architect certified to the owner that a payment of $25,292.55 was due the contractors "under terms of the contract", as follows:

85% of Contract ($47,403.00) $40,292.55 Less payment of $15,000.00 5/18/45 15,000.00 ___________ Due $25,292.55

*Page 666

The amount of the above-mentioned certificate was paid by the owner to the contractors, $20,000 on July 19, 1945, and $5,292.55 on August 14, 1945. This left, according to the contractors' figures, an unpaid balance of $8,641.47 upon the contract price and amount claimed for additional work.

On August 10, 1945, the contractors wrote the architect stating that they would appreciate his "issuing the final voucher for the job at Milton", so that they might obtain final payment without further delay. On October 30, 1945, the contractors sent the owner a letter as follows:

"We have sent invoices to you two or three times, and also to Mr. Morgan [the architect] and I called Mr. Morgan several times the latest was last Wednesday, and he said that he would take the matter up and make out a statement for us the next day. However, we have not heard from him and hope that you will take care of this for us as soon as possible as we would like to have the job closed out."

On November 16, 1945, the contractors wrote the architect as follows:

"Please advise us when we will receive our final payment from the Blue Mountain Prune Growers Cooperation as you have promised us several times that you would make up our final certificates."

The evidence shows that Mr. E. Halvorson, one of the plaintiffs, in the intervals between correspondence, talked by telephone with Mr. Morgan, the architect, two or three times, and with Mr. C.C. Yates, manager for the owner, several times. His talks with Mr. Morgan were for the purpose of urging him to issue the final certificate. Mr. Halvorson testified, in part: "When I called Mr. Yates, he told me he was waiting *Page 667 for Mr. Morgan to give him the certificate." Mr. Yates testified, in part: "In each case Mr. Halvorson called and asked when we would get the final certificate from the architect, Mr. Morgan, and when he could get his money. In each case I reminded him I couldn't issue a check only on the basis of the architect's certificate; that I was in touch with Mr. Morgan regarding the certificate and while I couldn't say when Mr. Morgan would get the certificate out, I would give him all the help in my power to get it out."

On November 24, 1945, the contractors wrote the owner as follows:

"We are somewhat surprised to find that we do not receive any replies to our letters and telephone calls in regard to receiving final payment on the building we built for you. Even though you look to Mr. Morgan for a certificate we had a contract with you and therefore we believe you should at least answer our letters and advise us when we may receive payment. We did our utmost in getting the job done for you and we did not anticipate that final payment would be dragged out as long as this and can see no reason for it.

"We trust we will receive our check without any further delay."

Under date of November 30, 1945, the architect issued to the owner his final certificate. The certificate is based upon the contract price plus the amount claimed by the contractors for additional labor and materials, but against this the architect made certain surcharges, leaving a net balance of $4,873.79 owing to the contractors by the owner. The principal item so surcharged was a $3,000 penalty, "per contract", for thirty days' delay in completion of the building. Other items were: For omitting "sacking", $500; for *Page 668 "tack nailing" certain floors, instead of nailing tight, $140; for tools belonging to owner and taken away by contractors, $95; for work performed after contractors left the job, $132.79.

On November 30, 1945, the owner mailed to the contractors its check in the sum of $4,873.79, as and for payment of the balance due under the architect's final certificate, which check the contractors refused to accept.

Thereafter, the contractors instituted this action. The cause of action, as set forth in the amended complaint, is account stated in the sum of $8,641.47. It is based upon the contractors' "final estimate" of July 12, 1945, as an account rendered, which is alleged to have become an account stated by having been held by the owner without objection until December 6, 1945. The owner answered the amended complaint by general denial. For affirmative defense, it pleaded the contract between the parties, and particularly that part thereof which provided that payments were to be made to the contractors in amounts as determined by the architect and authorized by certificate from him. It recited the issuance of the architect's final certificate, the tender to the contractors of the amount thereof, and their refusal of such tender.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Big Sky Livestock, Inc. v. Herzog
558 P.2d 1107 (Montana Supreme Court, 1976)
OK Johnson Electric, Inc. v. HESS-MARTIN CORPORATION
464 P.2d 206 (Supreme Court of Kansas, 1970)
State v. Jackson
365 P.2d 294 (Oregon Supreme Court, 1961)
Creith Lumber, Inc. v. Cummins
163 Ohio St. (N.S.) 264 (Ohio Supreme Court, 1955)
Shepard & Morse Lumber Co. v. Collins
256 P.2d 500 (Oregon Supreme Court, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
217 P.2d 254, 188 Or. 661, Counsel Stack Legal Research, https://law.counselstack.com/opinion/halvorson-v-blue-mt-prune-growers-co-op-or-1949.