Spokane County v. Pacific Bridge Co.

213 P. 151, 106 Or. 550, 1923 Ore. LEXIS 36
CourtOregon Supreme Court
DecidedFebruary 27, 1923
StatusPublished
Cited by23 cases

This text of 213 P. 151 (Spokane County v. Pacific Bridge Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spokane County v. Pacific Bridge Co., 213 P. 151, 106 Or. 550, 1923 Ore. LEXIS 36 (Or. 1923).

Opinion

McCOURT, J.

The plaintiff, Spokane County, State of Washington, commenced this action against the Pacific Bridge Company, hereinafter referred to as “defendant,” and its surety, the United 'States Fidelity and Guaranty Company, to recover damages in the sum of $61,740, for alleged breaches of a construction contract, whereby defendant undertook and agreed to do all the work and furnish all the materials necessary to construct, improve and complete about thirteen and one-half miles of asphalt macadam pavement upon Permanent Highway No. 12, known as Palouse Permanent Highway, in Spokane County, [553]*553Washington, in accordance with, and as described in, the profiles, maps, plans and specifications made a part of the contract and governing the undertaking and improvement.

After the cause was at issue, a protracted trial was had to a jury, which resulted in a verdict in favor of plaintiff for the full amount prayed for in the complaint. A judgment was entered upon the verdict, but thereafter on motion of the defendants, the verdict and judgment were set aside by the trial court, and a new trial granted. Plaintiff appeals from the last-mentioned order.

Plaintiff insists that no error of law, prejudicial to the rights of the defendants, was committed by the court in the trial of the action, and inasmuch as there was in the record, substantial evidence to support the verdict, the action of the court in setting aside the verdict and judgment and granting a new trial constituted reversible error.

The authority of a trial court to set aside a verdict and judgment and grant a new trial is not restricted to the cases indicated in the foregoing statement of plaintiff’s contention, but extends to cases where, by reason of some misapplication of the principles of law, to which ho exception has been taken, or in consequence of some inadvertence to which attention has not been called, the court is satisfied that a party has not had his cause properly presented: Archambeau v. Edmunson, 87 Or. 476, 487 (171 Pac. 186); Cathcart v. Marshfield, 89 Or. 401 (174 Pac. 138); Duniway v. Hadley, 91 Or. 343, 346 (178 Pac. 942); State v. Evans, 98 Or. 214, 221 (192 Pac. 1062, 193 Pac. 927); Bottig v. Polsky, 101 Or. 530, 539 (201 Pac. 188).

The contract out of which this action arose was made and performed in the State of Washington. [554]*554The improvement was authorized by the statutes of the State of Washington, known as the Permanent Highway Law, which provides for the construction of permanent state highways: Yol. Ill, Eem. & Bal. Code, § 5879-1 et seq.; 1 Pierce’s Code, §§ 6157-6172.

The statutes mentioned constituted the County Commissioners of the several counties, agents of the state to contract directly and to oversee the work of constructing and improving permanent state highways within their respective counties, in accordance with plans and specifications approved by the State Highway Commissioner. Provision is made for the payment of such improvements from state funds, and the time and manner of payment is reserved to the state, and payment may be made only upon the certificate of the State Highway Commissioner to the State Auditor: Willapa Harbor Sand & Gravel Co. v. Pacific County, 103 Wash. 309 (174 Pac. 450); McClung v. King County, 119 Wash. 14, 204 Pac. 1064.

The contract was entered into on the fourteenth day of April, 1914. The defendant soon thereafter entered upon the performance of the contract, and on or before the twenty-first day of October, 1915, defendant claimed and represented that it had fully completed its contract; thereupon, in conformity with the contract and the Permanent Highway Law, the County Engineer and the State Highway Commissioner examined the improvement, and each certified that the same had been completed in accordance with the plans and specifications; the County Commissioners of plaintiff approved the final estimate and certificate of the County Engineer, and thereafter final payment was made upon the contract price.

Soon after completion, the surface of the road began to break, crumble and give away in a number of [555]*555places, and although plaintiff attempted to repair the road during the summer of 1916, the same continued to break, until in the spring of 1917 the pavement laid by defendant had very largely gone to pieces. Plaintiff then commenced an investigation of the condition of the pavement and the manner in which the same had been constructed, with the result that this action was commenced.

The improvement which defendant undertook to construct included: (1) An asphaltic macadam pavement, full six inches in thickness and sixteen feet in width, laid upon the roadway in a trench of the full width of the finished pavement, and of the depth below the established and constructed grade equal to the thickness of the finished pavement, and (2) A drainage ditch on each side of the road, the edge of the bank of which should be eighteen feet distant from the center of the road. To afford drainage for the sub-base upon which the pavement was to be laid, the specifications required that the bottom of the ditch should be two feet wide and two feet below the grade of the crown of the road, and to provide surface drainage for the highway, the specifications required that an earth shoulder, having the same slope as the pavement, should be extended from the pavement on each side for a distance of four feet, and thence with a sharper slope to the bank of the drainage ditch.

The contract contained the following paragraphs:

Paragraph HI: “It is understood and agreed by and between the parties hereto that the work included in this contract is to be done under the direction and supervision of the County Engineer and hereinafter called the Engineer, and his decision as to the true construction and meaning of the profiles, maps, plans and specifications and estimates shall be final.”
[556]*556Paragraph YU: “Partial payments upon this contract, not to exceed eighty (80) per cent of the work done, shall be made at the request of the Contractor, once each month, said payments to be made upon the estimates of the Engineer in charge. * * Final payment for said work shall be made within thirty (30) days after the entire work has been completed and accepted and certificate has been made by the Engineer and the State Highway Commissioner that such work has been fully completed in accordance with the contract and profiles, maps, plans and specifications * * .”
Paragraph X: “The Contractor shall provide sufficient safe and proper facilities at all times for the inspection of the work by the Board or its authorized representatives. * * All materials and methods shall be subject to the approval of the Engineer.
“Defective work or material may be condemned by the Engineer at any time before the final acceptance of the work. Notice of condemnation shall be given in writing by the Engineer, and such condemned work shall be immediately taken down or changed. Defective material shall be immediately removed or disposed of .to the satisfaction of the Engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strandholm v. General Construction Co.
382 P.2d 843 (Oregon Supreme Court, 1963)
City of Granville v. Kovash, Incorporated
118 N.W.2d 354 (North Dakota Supreme Court, 1962)
McQuagge v. United States
197 F. Supp. 460 (W.D. Louisiana, 1961)
Boyer v. Dawson
337 P.2d 785 (Oregon Supreme Court, 1959)
Culver v. RENDAHL ET UX
318 P.2d 275 (Oregon Supreme Court, 1957)
Fischer v. Howard
271 P.2d 1059 (Oregon Supreme Court, 1954)
Halvorson v. Blue Mountain Prune Growers Cooperative
217 P.2d 254 (Oregon Supreme Court, 1950)
Halvorson v. Blue Mt. Prune Growers Co-Op.
217 P.2d 254 (Oregon Supreme Court, 1949)
Neal v. Haight
206 P.2d 1197 (Oregon Supreme Court, 1949)
Bean v. Hostettler
188 P.2d 636 (Oregon Supreme Court, 1948)
Karberg v. Leahy
26 P.2d 56 (Oregon Supreme Court, 1933)
Cicrich v. State Industrial Accident Commission
23 P.2d 534 (Oregon Supreme Court, 1933)
Shain v. Meier & Frank Co.
13 P.2d 360 (Oregon Supreme Court, 1932)
Odrlin v. Dugan
1 P.2d 599 (Oregon Supreme Court, 1931)
Weinstein v. Wheeler
296 P. 1079 (Oregon Supreme Court, 1930)
Timmins v. Hale
256 P. 770 (Oregon Supreme Court, 1927)
Southern Oregon Co. v. Kight
228 P. 132 (Oregon Supreme Court, 1924)
Lovell v. Potts
207 P. 1006 (Oregon Supreme Court, 1924)
Hughes v. Holman
223 P. 730 (Oregon Supreme Court, 1924)
American National Bank v. Kerley
220 P. 116 (Oregon Supreme Court, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
213 P. 151, 106 Or. 550, 1923 Ore. LEXIS 36, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spokane-county-v-pacific-bridge-co-or-1923.