Bavaria Investment Co. v. Washington Brick, Lime & Sewer Pipe Co.

144 P. 68, 82 Wash. 187, 1914 Wash. LEXIS 1517
CourtWashington Supreme Court
DecidedNovember 10, 1914
DocketNo. 11593
StatusPublished
Cited by10 cases

This text of 144 P. 68 (Bavaria Investment Co. v. Washington Brick, Lime & Sewer Pipe Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bavaria Investment Co. v. Washington Brick, Lime & Sewer Pipe Co., 144 P. 68, 82 Wash. 187, 1914 Wash. LEXIS 1517 (Wash. 1914).

Opinion

Ellis, J.

This action was brought to recover damages certified by the architects of an apartment building erected by the plaintiff in the city of Spokane, and for the cancellation of a claim of lien on the building filed by the defendant for terra cotta furnished in its construction under a contract. On July 19, 1911, the parties entered into a contract, in which the plaintiff is designated as the owner, and the defendant as the contractor. It is, in substance, a? follows:

“(1) The contractor, under the direction, and to the satisfaction of specified architects, shall provide all materials and perform all work for the terra cotta required for the building, according to specifications and drawings prepared by the architects, and color as selected by owner and architects. The contractor guarantees the same to be of even color, of square and even bed, and to be and remain free from checks and cracks, and to replace without cost to the owner any defective terra cotta furnished.
“(2) The architects shall furnish further details, explanations and illustrations as necessary, to which contractor shall conform, so far as consistent with the original drawings and specifications.
“(3) No alterations shall be made except upon written order of architects and the value of work added or omitted thereby shall be computed by the architects and be added to, or deducted from, the contract price. In case of dissent from such award by either party, such valuation shall be referred to three disinterested arbitrators, one to be appointed by each of the parties and the third by the two thus chosen, the decision of any two of whom shall be final.
“(4) The contractor shall, within 24 hours after notice from the architects, remove from the grounds or buildings [190]*190all materials condemned, and take down portions of work condemned by written notice from the architects.
“(6) All terra cotta required for first story, up to and including second story sill course, must be delivered within seven weeks from date of contract; balance as required by general contractor, so as not to delay the work. In case of failure in this regard causing loss to the owner, the contractor agrees to reimburse the owner for any loss or damage caused by such failure, which loss or damage shall be estimated and certified by the architects as provided in the eighth article.
“(7) Should contractor be delayed by any delay or neglect of the owner or architects or any other contractor employed upon the work, through no fault of the contractor, the time for completion shall be extended correspondingly, but no allowance shall be made unless claim in writing therefor be presented to the architects within 24 hours of such delay. Such extension shall be certified by the architects, but an appeal may be made to arbitration as provided in third section.
“(8) The owner shall provide the other materials in such manner as not to delay material progress of the work, and, in the event of failure so to do causing loss to the contractor, he shall reimburse the contractor for such loss, and if the contractor delay the material progress of the work causing damage to the owner, he shall make good such damage. The amount of such loss to either party shall, in every case, be determined by the architects or by arbitration, as provided in section 3.
“(9) The contract price for the work and materials shall be $2,165, subject to additions and deductions as provided, such price to be paid as follows: $500 when all terra cotta to top of second story windows is delivered, $500 when all terra cotta to top of third story windows is delivered, $500 when all terra cotta is delivered on the ground, and the balance when placed in position and accepted by architects, final payment to be made within ten days after contract is fulfilled. All payments shall be made upon written certificates of the architects that they have become due.
“(10) No certificate given or payment made, except the final certificate or final payment, shall be conclusive evidence of performance either in whole or in part, and no payment [191]*191shall be construed an acceptance of defective work or materials.
“(11) The owner shall maintain full insurance during the progress of the work in his own name and that of the contractor against loss or damage by fire, payable to the parties as their interests appear.

Plaintiff’s complaint sets up two causes of action: The first, claims, for delay in furnishing the terra cotta, damages in the sum of $6,036.11 as certified by the architects, less the contract price of the material, $2,165, making a net damage of $3,871.11, and alleges that the defendant in no manner dissented from the award of the architects. The second, sets up damages in the sum of $750 because of delivery of defective terra cotta, objected to by the architects on delivery, and thereupon guaranteed as fit by the defendant, but not conforming to the guaranty when placed in the building.

The defendant’s answer consists of a general denial and two affirmative defenses. The first, sets up an agreement that defendant, instead of the architects, should prepare the necessary detailed plans, which it did, and manufactured all terra cotta for the first story ready for delivery on order of the architects within the period of seven weeks, and that delay in delivery was due to the fact that the building was not ready for the material and there were no facilities for storing it on the ground; that, after the defendant had proceeded with the manufacture of the terra cotta for the rest of the building, it was notified by the architects that they desired to furnish the details for the rest of the building; that defendant was compelled to suspend work till such details were furnished, and that the delay was caused by the fault of plaintiff and its architects. The second affirmative defense alleged that the architects’ certificate of damage was made without right or authority, without the exercise of any judgment, and without knowledge of the facts, fraudulently and with the purpose and intent of cheating and defrauding the defendant, and included items not the proper subject of damages.

[192]*192By way of cross-complaint, the defendant alleged full performance of the contract on its part, and sought to establish and foreclose a lien upon the building for the contract price, $2,165, and $500 attorney’s fee. The reply traversed the affirmative defenses, and for answer to the cross-complaint, admitted delivery of certain terra cotta which was used in the construction of the building, but denied the manufacture and delivery of the material as required by the contract, and denied that the contract had been performed. For an affirmative defense to the cross-complaint, it re-pleaded, by reference, the matters set up in the first and second causes of action in the plaintiff’s complaint, omitting the paragraph referring to the architects’ certificate, and alleged delay in the performance of the contract to the plaintiff’s damage in the sum of $6,036.11, setting forth the items of damage in detail, and alleged that the architects had refused to issue certificates for the contract price or any part of it because such damage exceeded the contract price. No reply was interposed by the defendant to this affirmative defense to its cross-complaint. The architects’ certificate, which is in evidence, is as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dally v. Isaacson
245 P.2d 200 (Washington Supreme Court, 1952)
School District No. 1 v. Howard
52 P.2d 421 (Wyoming Supreme Court, 1935)
Sloane v. State
297 P. 194 (Washington Supreme Court, 1931)
Lovell v. Potts
207 P. 1006 (Oregon Supreme Court, 1924)
Odell v. Colmor Irrigation & Land Co.
280 P. 398 (New Mexico Supreme Court, 1924)
Spokane County v. Pacific Bridge Co.
213 P. 151 (Oregon Supreme Court, 1923)
Sheldon v. Chicago Bonding & Surety Co.
190 Iowa 945 (Supreme Court of Iowa, 1921)
Stocking v. Fouts
169 P. 593 (Washington Supreme Court, 1918)
School District No. 75 v. Qualls
163 P. 761 (Washington Supreme Court, 1917)
Colby v. Interlaken Land Co.
152 P. 994 (Washington Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
144 P. 68, 82 Wash. 187, 1914 Wash. LEXIS 1517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bavaria-investment-co-v-washington-brick-lime-sewer-pipe-co-wash-1914.