Dally v. Isaacson

245 P.2d 200, 40 Wash. 2d 574, 1952 Wash. LEXIS 359
CourtWashington Supreme Court
DecidedMay 29, 1952
Docket31935
StatusPublished
Cited by12 cases

This text of 245 P.2d 200 (Dally v. Isaacson) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dally v. Isaacson, 245 P.2d 200, 40 Wash. 2d 574, 1952 Wash. LEXIS 359 (Wash. 1952).

Opinion

Mallery, J.

C. F. Dally and E. J. Beslow, doing business as Dally Construction & Engineering Co., hereafter referred to as Dally, were the successful bidders for the construction of a housing project for the army engineers at the Chief Joseph dam near Bridgeport, Washington.

A. B. Isaacson, doing business as Modern Manufacturing Company, hereafter referred to as Isaacson, was engaged in the business of manufacturing millwork.

Isaacson had studied the plans and specifications of the army engineers, and, upon learning that Dally was low bidder on the entire job, sent his bid on the millwork to Dally. A contract for the millwork resulted.

Daily’s contract required the construction to be completed in stages, upon specified dates, and called for certain quality of material and workmanship.

*576 The trial court found that Isaacson was at all times aware of these specifications. This situation, therefore, is not comparable with the mere sale of goods where the seller is not informed and not concerned with the specific use the buyer has in mind.

Very shortly after the work began, trouble arose between Dally and Isaacson over the rate of delivery of the millwork and its quality. These difficulties were many and frequent, and, on September 25, 1950, Dally elected to terminate the contract, on the basis of breaches in these matters on Isaac-son’s part. Thereupon, Dally brought this action for damages arising out of the claimed breaches.

At the trial, the testimony was in conflict, and was sufficient to sustain a judgment for either party whose version of the facts found acceptance by the trial court.

The trial court did not find for either party completely. It found that Isaacson had substantially performed his contract so that he was entitled to his agreed compensation, but with offsets to the amount of Daily’s damages. Evers v. Broadview Dairy Co., 147 Wash. 570, 266 Pac. 726.

The trial court, on the other hand, found that some, although by no means all, of the damages sought by Dally were substantiated. For a number of reasons, it did not allow damages based on the penalties imposed for noncompletion of the project on schedule. Some of the penalties assessed were remitted by the government. The bulk of those not remitted, after extensions of time had been granted, was assessed for noncompletion of street improvements and parts of the contract having nothing to do with millwork. The trial court’s finding that Dally had ample time to complete the work will not be disturbed.

The trial court did find that some of the material was defective and below the specifications that Isaacson was obliged to meet. This damaged Dally by necessitating extra labor on the job in preparing it for installation.

The trial court also found that tardy delivery of some of the material made extra labor necessary.

*577 Isaacson made a .strong showing, which the trial court could have believed, that Daily’s damage was not due to defective material or delay, but was due to bad workmanship and management on Daily’s part.

From our examination of the record, we find ourselves in the same frame of mind as the trial court in being unable to reconcile the testimony to the extent that an exact computation of the damage is possible.

The trial court allowed $12,000 damage to Dally for the delays in delivery and defective materials, based upon his showing of the extra labor costs these had caused. This amount, being well within the evidence, is sustained, plus $1,777 for additional supervisory overhead expenses incurred after the termination of the contract, which would not have been necessary had the proper quality of materials been timely furnished.

The appellant Isaacson contends that an erroneous measure of damages was allowed by the trial court. It is his position that he substantially performed the contract. He argues that title to the millwork passed when it was accepted at the job site, and that no claim can now be made for defects in the materials which were not rejected at the time of delivery. He relies upon RCW 63.04.490 [cf. Rem. Rev. Stat., § 5836-48], which reads: .

“The buyer is deemed to have accepted the goods when he intimates to the seller that he has accepted them, or when the goods have been delivered to him and he does any act in relation to them which is inconsistent with the ownership of the seller, or when, after the lapse of a reasonable time, he retains the goods without intimating to the seller that he has rejected them.”

This contention is answered by the next section of the uniform sales act, RCW 63.04.500 [cf. Rem. Rev. Stat., § 5836-49], which reads:

“In the absence of express or implied agreement of the parties, acceptance of the goods by the buyer shall not discharge the seller from liability in damages or other legal remedy for breach of any promise or warranty in the contract to sell or the sale. But if after acceptance of the goods, *578 the buyer fails to give notice to the seller of the breach of any promise or warranty within a reasonable time after the buyer knows, or ought to know, of such breach, the seller shall not be liable therefor.”

Timely notice of defects in the millwork and delays in its delivery was evidenced by voluminous correspondence and oral communications between the parties.

We cannot sustain appellant Isaacson’s contention in this regard.

The real gravamen of appellant’s appeal, however, is that consequential damages should not have been allowed, and that the trial court should have limited the amount of damage to the difference between the value of the material according to the specifications and the value of the material as delivered. He contends that the consequential damages were speculative and too remote.

The general rule as to damages growing out of a breach of contract is stated in the early English case, Hadley v. Baxendale (1854), 9 Ex. 341, 354, 156 Eng. Rep. 151, as follows:

“Where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, i. e., according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it. Now, if the special circumstances under which the contract was actually made were communicated by the plaintiffs to the defendants, and thus known to both parties, the damages resulting from the breach of such a contract, which they would reasonably contemplate, would be the amount of ■ injury which would ordinarily follow from a breach of contract under these special circumstances so known and communicated.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

King Logging Co. v. Scalzo
561 P.2d 206 (Court of Appeals of Washington, 1977)
Burkheimer v. Thrifty Investment Co.
533 P.2d 449 (Court of Appeals of Washington, 1975)
Thompson v. Hanson
491 P.2d 1065 (Court of Appeals of Washington, 1971)
Larsen v. Walton Plywood Co.
390 P.2d 677 (Washington Supreme Court, 1964)
Forrester v. Craddock
317 P.2d 1077 (Washington Supreme Court, 1957)
Pettaway v. Commercial Automotive Service, Inc.
306 P.2d 219 (Washington Supreme Court, 1957)
Winslow v. Mell
295 P.2d 319 (Washington Supreme Court, 1956)
Lidral v. Sixth & Battery Corp.
290 P.2d 459 (Washington Supreme Court, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
245 P.2d 200, 40 Wash. 2d 574, 1952 Wash. LEXIS 359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dally-v-isaacson-wash-1952.