Schmidt v. City of North Yakima

40 P. 790, 12 Wash. 121, 1895 Wash. LEXIS 133
CourtWashington Supreme Court
DecidedJune 19, 1895
DocketNo. 1713
StatusPublished
Cited by23 cases

This text of 40 P. 790 (Schmidt v. City of North Yakima) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schmidt v. City of North Yakima, 40 P. 790, 12 Wash. 121, 1895 Wash. LEXIS 133 (Wash. 1895).

Opinion

The opinion of the court was delivered by

Dunbar, J.

The appellant entered into a written contract with respondent for the construction of a system of sewerage in the city of North Yakima. Contract and specifications are set forth in the pleadings. The work was to be done to the satisfaction of [123]*123and under the direction of the city engineer, and to be testified by his certificate. Under the contract, in case the contractor, at any time during the progress of the work, refused or neglected to supply a sufficiency of material, workmen, or implements to complete the system within the timé, the city reserved the right to provide the same, after five days’ notice in writing first being given the contractor, to finish the work, and the expense to be deducted from the amount of the contract price. The contractor was to provide at his own costs and charges, all manner of material, labor, and implements of every description for the due performance of the contract. It was further provided that, should any dispute arise respecting the construction or meaning of the drawings or specifications, the same should be decided by the city engineer of the party of the first part, which decision should be final and conclusive. The contract was to be completed according to the specifications on or before the 1st day of June, 1892. The specifications required that the pipe should be of the best quality of vitrified ironstone, salt-glazed;'that it should have a true circular bore, should be straight, and free from warps or other imperfections; also, that the material used around the pipe for not less than twelve inches above the pipe should be free from stone or other hard, coarse substance; that, where the excavation was through coal or gravel, the material used around the pipe should be screened through a sieve, and such as the engineer might approve of, each joint to be well and thoroughly cemented with best Portland cement one part, and two parts clean, sharp sand. They provide that the cement should be put in the joints by the hands, and not by trowels or sticks; that great care should be taken not to force the [124]*124cement through the joints to the inside of the pipe. The specifications were lengthy and definite.

During the fore part of the month of June, the city council of the city of North Yakima passed an ordinance provided for in the contract, that they would take charge of the work, and did take charge of the same, and finish the same; whereupon the contractor (the appellant herein) brought an action against the city for damages, alleging the making, execution, and delivery of the contract; that, under the contract, he entered upon the construction of the said sewerage system, and provided necessary, suitable, and sufficient material for the' construction of the same, and was proceeding to complete the same, until he was interfered with and stopped by the respondent; that in undertaking to carry out the contract, he incurred a large expenditure, to wit, the sum of $30,372; that he would have fully completed said system in accordance with said contract, plans, specifications and drawings at a further expenditure of not more $4,000; but that the defendant, by its officers and servants, hindered, delayed and prevented the complete performance of said contract by sundry wrongful acts, setting them forth specifically.

Among the facts which were necessary to the determination of the questions involved in this cause, the most pertinent ones were that the defendant, by its city engineer and others, wrongfully rejected large quantities of pipe furnished by the plaintiff, and refused to permit the plaintiff to lay or use the same, notwithstanding all such pipe fully complied with the contract and specifications; that the defendant, by its officers, on sundry occasions capriciously refused to allow the use by the plaintiff of suitable materials, and, after causing said delay, allowed the same mate[125]*125rials to be used, and approved the same, and capriciously interfered with the plaintiff’s labors on said work; that on or about the 16th day of June, 1892, the defendant, by its officers, wrongfully and forcibly prohibited and prevented the plaintiff from further working on said contract; that plaintiff has fully performed all the conditions of said contract, except in so far as he has been prevented by the wrongful acts on the part of the defendant; and that, by such reason, he is damaged in the sum of $10,000, and alleges damages for extra work, etc., which swell the amount claimed to $29,918.33, for which sum he asks judgment.

The defendant, by its answer, admits the making of the contract, payment mentioned by the plaintiff in his complaint, and admits extra work done by the plaintiff to the amount of $824, and admits the presentation to and the disallowance of the plaintiff’s claim by the city council, but denies each and every other allegation of the complaint; and for an affirmative defense, and by way of counterclaim, alleges that plaintiff failed and refused to comply with the terms of the contract to complete such work according to the plans and specifications in many particulars, among which were that he did not properly cement the joints of the pipe, that they were laid in a defective manner, so that they leaked, and rendered the sewer systém liable to generate gas, which was liable to cause explosions, etc., by which the defendant claimed to be damaged in the sum of $2,000; alleges that the plaintiff did not furnish the quality of pipe provided for by the specifications; that the same was not the best quality, not properly vitrified, not salt-glazed, and was not of true circular bore and free from warps, but was wholly unfit for the work, and that, by reason of such failure on the [126]*126part of the plaintiff, defendant was damaged in the sum of $10,000; alleges that the plaintiff failed and refused to employ skilled mechanics to lay such pipe, to the damage of defendant in the sum of $500, and, among other failures on the part of the plaintiff to comply with the terms of the contract as alleged, that, during all the time that plaintiff was carrying on said work, he was fraudulently contriving to and did put in defective pipe, which had been rejected by the city engineer, which was unfit.for said work, and not according to the plans and specifications, and that he refused to supply skilled mechanics for laying said pipe, refused to lay the same according to the plans' and specifications, and neglected and refused to construct said system in accordance with the contract, plans, and specifications; alleges that a large number of defective joints of pipe were laid by the plaintiff, which defendant was compelled to and did excavate, and discover such defective joints, and repair the same; that, at the time defendant took charge of said work, the plaintiff was unlawfully and wrongfully, by violence and force, using pipe for said sewer which had been rejected by the city engineer, and which was unfit for use in said sewer, the same being defective, and not conforming tp the contract, plans, and specifications, which was well known to the plaintiff.

On the trial of the cause, the jury rendered a verdict for the defendant. Judgment was rendered upon the v.erdict, and from said judgment an appeal-is taken to this court.

We have with great care and much labor examined the record in this case, which comprises nearly 1,000 pages of testimony. The case was tried with great ability, both by counsel for the appellant and the respondent, and many days were consumed by the court [127]*127in the trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ducolon Mechanical, Inc. v. Shinstine/Forness, Inc.
893 P.2d 1127 (Court of Appeals of Washington, 1995)
Swenson v. Lowe
486 P.2d 1120 (Court of Appeals of Washington, 1971)
Golob v. George S. May International Co.
468 P.2d 707 (Court of Appeals of Washington, 1970)
Coyle Construction Co. v. Skagit County
32 P.2d 106 (Washington Supreme Court, 1934)
Continental Coal Co. v. United Fuel Co.
29 P.2d 395 (Washington Supreme Court, 1934)
Sloane v. State
297 P. 194 (Washington Supreme Court, 1931)
Olmstead v. Downie
248 P. 385 (Washington Supreme Court, 1926)
Harrild v. Spokane School District
192 P. 1 (Washington Supreme Court, 1920)
Berry v. Huntington Masonic Temple Ass'n
93 S.E. 355 (West Virginia Supreme Court, 1917)
Evans v. Goist
155 P. 780 (Washington Supreme Court, 1916)
Lindblom v. Mayar
142 P. 695 (Washington Supreme Court, 1914)
Mallory v. City of Olympia
134 P. 914 (Washington Supreme Court, 1913)
State ex rel. Murphy v. Coleman
127 P. 568 (Washington Supreme Court, 1912)
Morehouse v. Clerk of Edmonds
126 P. 419 (Washington Supreme Court, 1912)
Piper v. Murray
115 P. 669 (Montana Supreme Court, 1911)
Sweatt v. Bonne
110 P. 617 (Washington Supreme Court, 1910)
Dickerman v. Reeder
109 P. 1060 (Washington Supreme Court, 1910)
Mortimer v. Dirks
107 P. 184 (Washington Supreme Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
40 P. 790, 12 Wash. 121, 1895 Wash. LEXIS 133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schmidt-v-city-of-north-yakima-wash-1895.