Swenson v. Lowe

486 P.2d 1120, 5 Wash. App. 186, 1971 Wash. App. LEXIS 1023
CourtCourt of Appeals of Washington
DecidedJune 28, 1971
Docket659-41393-1
StatusPublished
Cited by15 cases

This text of 486 P.2d 1120 (Swenson v. Lowe) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swenson v. Lowe, 486 P.2d 1120, 5 Wash. App. 186, 1971 Wash. App. LEXIS 1023 (Wash. Ct. App. 1971).

Opinion

*187 Horowitz, C.J.

Plaintiff contractor sued to foreclose a materialmen’s lien for an unpaid balance owing under a written residence construction contract. The owner defendants counterclaimed for damages for breach of contract. The case was tried to the court sitting without a jury. From a judgment in favor of plaintiff and dismissing defendants’ counterclaim for damages, defendants appeal.

On March 24, 1967, defendants Lowe entered into a written contract with the plaintiff for the construction of a residence on defendants’ property for the total price of $20,148.10, plus sales tax. The contract fixed no specific completion date. The contract contained a 1-year guarantee from date of completion against defective or faulty workmanship or materials. The contract further provided (paragraph third):

No alterations shall be made in the work shown or described by the drawings and specifications except by written memorandum agreed to by Owner and the Contractor and when so made value the work added or omitted shall be computed at that time and the amount so ascertained will be added to or deducted from the contract price.

Shortly after construction was commenced, defendant husband by letter notified the contractor that the contract be performed in accordance with its terms and that deviations be made only after defendant’s written approval. Nevertheless, various departures from the contract specifications were made thereafter without the owner’s written approval. Furthermore, defendant husband, who was watching the job from time to time, made progress payments without protest in sums totalling $18,795.77, the last payment being made on August 15, 1967. There is additional evidence that the requirement of a writing was waived by defendant husband’s oral consent and conduct, and the court found the existence of such a waiver. The contractor ceased performance on August 15, 1967. Shortly thereafter, either in the last week of August or the first week of September, the defendants took possession of the *188 residence and continued in possession up to and during the time of trial which commenced in May of 1969. Meanwhile, on September 12, 1967, the contractor submitted his final billing of $3,165.65, which after certain additions' and deletions from the contract price to reflect changes allegedly agreed to, represented a net increase in the contract price of $904.80, plus the sales tax.

On October 5, 1967, defendant husband wrote a letter to the contractor asking that various defects in the construction be remedied, whereupon the billing rendered would be paid. The contractor did not take the remedial action requested. Instead, on November 6, 1967, he filed a lien claim of $3,165.65, and then brought the instant action below to foreclose his claim. Defendants counterclaimed for damages on account of claimed unauthorized extras and deficiencies in performance in the sum of $5,000. At trial, the amount of damages claimed was raised to $8,309.50. After trial, the court, after making certain offsetting allowances of $625, entered judgment in favor of the contractor in the sum of $3,040.65 and ordered foreclosure of his lien. The amount of the judgment was arrived at by deducting “allowances” in the sum of $625 from the sum of $3,165.65 claimed by the contractor, and then adding a $500 attorney’s fee awarded to the contractor.

A proper understanding of the assignments of error requires a short statement of applicable legal principles. A building contract provision requiring a written order for alterations or extras will be enforced. 13 Am. Jur. 2d Building and Construction Contracts § 22 (1964). However, the requirement of a writing is for the benefit of the owner, and the owmer, either expressly or by conduct, may waive such a requirement. American Sheet Metal Works, Inc. v. Haynes, 67 Wn.2d 153, 407 P.2d 429 (1965); Davis v. Altose, 35 Wn.2d 807, 215 P.2d 705 (1950); Eggers v. Luster, 32 Wn.2d 86, 200 P.2d 520 (1948). As stated in Annot., 2 A.L.R.3d 620, 661 (1965), “where . . . the work was orally ordered, requested, directed, authorized, or consented to by the owner . . .” the requirement is deemed *189 waived. Morango v. Phillips, 33 Wn.2d 351, 205 P.2d 892 (1949); Eggers v. Luster, supra; Bjerkeseth v. Lysnes, 173 Wash. 229, 22 P.2d 660 (1933); Crowley v. United States Fid. & Guar. Co., 29 Wash. 268, 69 P. 784 (1902). See 13 Am. Jur. 2d Building and Construction Contracts § 24 (1964).

The subject of waiver of a writing in the case of extras and alterations is, of course, to be distinguished from the subject of deficiencies in performance of the contract specifications. Notwithstanding the obligation to perform his contract, the contractor is not necessarily precluded from recovering the contract price called for by reason of his failure to fully perform the contract in accordance with its terms. If his performance is at least not deliberately deficient (see Schmidt v. North Yakima, 12 Wash. 121, 40 P. 790 (1895); Golob v. George S. May Int’l Co., 2 Wn. App. 499, 468 P.2d 707 (1970)), and is substantial, he may recover the contract price less the reasonable cost of making good the deficiencies in performance. The last mentioned cost is sometimes called the cost of repair rule. Odgers v. Held, 58 Wn.2d 247, 362 P.2d 261 (1961); Baldwin v. Alberti, 58 Wn.2d 243, 362 P.2d 258 (1961); Forrester v. Craddock, 51 Wn.2d 315, 317 P.2d 1077 (1957); Bernbaum v. Hodges, 43 Wn.2d 503, 261 P.2d 968 (1953); White v. Mitchell, 123 Wash. 630, 213 P. 10 (1923); Annot, 76 A.L.R.2d 805 (1961). Such rule, as pointed out in Baldwin v. Alberti, supra, means the reasonable cost of correcting the defects is chargeable to defendant when such correction would cause no “unreasonable economic waste.”

Substantial performance and cost of repair rules are defined in White v. Mitchell, supra at 637, as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skanska Usa Building Inc., V. 1200 Howell Street, Llc
Court of Appeals of Washington, 2025
Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
Ducolon Mechanical, Inc. v. Shinstine/Forness, Inc.
893 P.2d 1127 (Court of Appeals of Washington, 1995)
Absher Construction Co. v. Kent School District No. 415
890 P.2d 1071 (Court of Appeals of Washington, 1995)
Panther Lake Homeowner's Ass'n v. Juergensen
76 Wash. App. 586 (Court of Appeals of Washington, 1995)
PANTHER LAKE ASS'N v. Juergensen
887 P.2d 465 (Court of Appeals of Washington, 1995)
CKP, Inc. v. GRS Construction Co.
821 P.2d 63 (Court of Appeals of Washington, 1991)
Toyota of Puyallup, Inc. v. Tracy
818 P.2d 1122 (Court of Appeals of Washington, 1991)
State v. Hendrickson
730 P.2d 88 (Court of Appeals of Washington, 1986)
Modern Builders, Inc. v. Manke
615 P.2d 1332 (Court of Appeals of Washington, 1980)
Foster v. Foster
364 A.2d 65 (Court of Special Appeals of Maryland, 1976)
Hos Bros. Bulldozing, Inc. v. Hugh S. Ferguson Co.
508 P.2d 1377 (Court of Appeals of Washington, 1973)
Meeker v. Howard
499 P.2d 53 (Court of Appeals of Washington, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
486 P.2d 1120, 5 Wash. App. 186, 1971 Wash. App. LEXIS 1023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swenson-v-lowe-washctapp-1971.