Modern Builders, Inc. v. Manke

615 P.2d 1332, 27 Wash. App. 86, 1980 Wash. App. LEXIS 2214
CourtCourt of Appeals of Washington
DecidedAugust 7, 1980
Docket3690-II
StatusPublished
Cited by25 cases

This text of 615 P.2d 1332 (Modern Builders, Inc. v. Manke) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Modern Builders, Inc. v. Manke, 615 P.2d 1332, 27 Wash. App. 86, 1980 Wash. App. LEXIS 2214 (Wash. Ct. App. 1980).

Opinion

Reed, C.J.

Lennard and Kathleen Manke appeal a judgment foreclosing a labor and materialmen's lien in favor of plaintiff upon defendants' real property. We reverse.

In March 1976 defendants purchased an older house in need of remodeling near Gig Harbor. Prior to purchasing the house, they asked Duane Anderson, vice president of Modern Builders, Inc. of Tacoma (Modern Builders), to estimate the cost of remodeling. Anderson responded that it could not be done for under $50,000. Both parties agreed that extensive remodeling was necessary in order to make *88 the house level and that extensive demolition and rebuilding of the interior would be necessary to modernize the house. Defendants purchased the house and asked Anderson to provide a written bid for the work. Anderson had plans drawn and on May 3, 1976 delivered a written, itemized estimate stating a total price of $57,077.43. Included in this estimate was $4,300 which was earmarked for leveling the interior floors by pouring concrete. Defendants applied to Puget Sound National Bank for financing, and the bank agreed to lend $57,804.16 for the remodeling. 1

After receipt of the estimate and approval of the loan, defendants authorized plaintiff to begin work. Shortly thereafter, plaintiff's workmen discovered that the floors were out of level much more than originally estimated by Anderson. Specifically, after measuring, plaintiff's carpenters discovered that the lower floor was approximately 7 inches out of level, as opposed to the 11/2 inches originally contemplated, and that the upper story was also out of level. After the concrete was poured to achieve the desired leveling, much additional work was necessary to insure that the entire house appeared to be level. This required adjustment of walls, windows, fireplaces, siding, decks and porches so that they appeared level in relation to the floors. The record also shows that Mr. Manke requested many changes from the original plans, such as enlarging the kitchen work areas, using more expensive floor tiles, moving a window, changing stains used on the kitchen cabinets and other miscellaneous changes which required extra work and often required the substitution of more expensive materials than those included in the original estimate.

Puget Sound National Bank disbursed funds to plaintiff as work progressed. Reports certifying job progress were *89 prepared by employees of plaintiff under Anderson's direction showing 40 percent completion on July 30, 1976, 61 percent completion on September 23, 1976, 78 percent completion on October 28, 1976, and 98 percent completion on December 15, 1976. All progress reports stated the contract price to be $57,804.16, and the amounts disbursed by the bank as work progressed were all computed in reference to this total price. The only claim for amounts sought in excess of the contract price was a claim for $2,100 on the last three reports which apparently represented excess expenses incurred by plaintiffs in hauling away debris from the jobsite, something defendants had originally agreed to do.

After work was completed and funds were disbursed by the bank, plaintiff presented defendants with a bill for an additional $66,327.59. This billing computed the amount owed by (1) adding material costs of $56,203.47, labor costs of $44,844.60, profit and overhead at 15 percent of cost, and sales tax for a total job price of $122,131.75; and (2) deducting amounts paid by the bank. On April 5, 1977, plaintiff filed a labor and materialmen's lien and eventually sued to foreclose the lien.

At trial Anderson explained the increased billing by claiming that the parties never agreed to a firm contract price of $57,804.16 in May 1976. He asserted that the figure set forth in his letter of May 3, 1976 was only a "guesstimate," not a bid to be accepted, and that it was used only to submit to the bank to obtain financing and to obtain building permits. Anderson maintained that the parties agreed that the job was to be done on a "cost-plus" basis by which the total price would be computed by adding the cost of labor and materials plus an allowance for overhead at 15 percent of these costs. In support, he argued that contractors never do extensive remodeling on a firm price basis and that, if a bid is used as a contract price and substantial changes in conditions occur, the contract is automatically converted to a cost-plus contract. Anderson also testified that he had done other smaller jobs for the *90 Mankes on a cost-plus basis in the past and presented expert testimony from another general contractor who maintained that remodeling jobs are universally done on a cost-plus basis.

Lennard Manke vigorously disputed that the parties had agreed to a cost-plus contract. He claimed that defendants and Anderson agreed to a firm price of $57,804.16 in May 1976 when plaintiff submitted the written bid which defendants accepted by authorizing work to begin. Manke admitted that he orally authorized extra work and the substitution of certain materials as the job progressed. He maintained, however, that defendants were assured by Anderson that this would not result in extraordinary extra costs, and that neither party contemplated that these extras would exceed $10,000. He also stated that, other than the $2,100 referred to on the progress reports, plaintiff did not present an itemized bill for costs in excess of the contract price, and further that defendants had no indication that the total cost of the job would depart radically from the $57,804.16 contract price until they received plaintiff's total bill for $122,131.75 on March 31, 1977. Anderson responded that he did not document the extra costs because he assumed that the parties had agreed to a cost-plus contract.

Throughout the proceedings the Mankes contended that the great majority of plaintiff's costs in excess of the original contract resulted from the need for more extensive work after plaintiff's workmen discovered that the floors were much more out of level than contemplated in the original estimate. Defendants argued that such additional costs necessary to carry out the contract were clearly foreseeable by plaintiff prior to setting the original contract price. As such, defendants contended that plaintiff was not entitled to additional compensation for such foreseeable costs. Expert witnesses who testified on behalf of both plaintiff and defendants gave the opinion that the leveling *91 problem which occurred on this job should have been foreseen by a reasonably prudent contractor prior to submission of the estimate. The Mankes also contended that the floors were not level after work was completed and filed a counterclaim for damages incurred because of this alleged defect in workmanship. They also asserted that the heating system was defective and that plaintiff failed to complete all the work contained in the initial estimate. A conflict of testimony was presented at trial between the expert witnesses of plaintiff and defendants concerning whether pouring concrete was the proper method to level the floors in this particular house, as opposed to jacking up the house, and whether the heating system functioned properly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert Akhtar And Gulnoor Akhtar, V. TTG, LLC
Court of Appeals of Washington, 2023
Mastaba, Inc. v. Lamb Weston Sales, Inc.
23 F. Supp. 3d 1283 (E.D. Washington, 2014)
Top Line Builders, Inc. v. Bovenkamp
320 P.3d 130 (Court of Appeals of Washington, 2014)
QHG of Lake City, Inc. v. McCutcheon
600 S.E.2d 105 (Court of Appeals of South Carolina, 2004)
J.A. Jones Construction Co. v. Lehrer McGovern Bovis, Inc.
89 P.3d 1009 (Nevada Supreme Court, 2004)
Avemco Insurance Co. v. Northern Colorado Air Charter, Inc.
38 P.3d 555 (Supreme Court of Colorado, 2002)
Basin Paving Co. v. Mike M. Johnson, Inc.
107 Wash. App. 61 (Court of Appeals of Washington, 2001)
Auburn Mechanical, Inc. v. Lydig Construction, Inc.
951 P.2d 311 (Court of Appeals of Washington, 1998)
Bunting v. State
943 P.2d 347 (Court of Appeals of Washington, 1997)
Bouten Construction Co. v. M & L Land Co.
877 P.2d 928 (Idaho Court of Appeals, 1994)
Schumacher Painting Co. v. First Union Management, Inc.
850 P.2d 1361 (Court of Appeals of Washington, 1993)
CKP, Inc. v. GRS Construction Co.
821 P.2d 63 (Court of Appeals of Washington, 1991)
Bailie Communications, Ltd. v. Trend Business Systems, Inc.
810 P.2d 12 (Court of Appeals of Washington, 1991)
Clevco, Inc. v. Municipality of Metropolitan Seattle
799 P.2d 1183 (Court of Appeals of Washington, 1990)
Pfeifer v. DME Liquidating, Inc.
789 P.2d 266 (Court of Appeals of Oregon, 1990)
Schoneman v. Wilson
785 P.2d 845 (Court of Appeals of Washington, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
615 P.2d 1332, 27 Wash. App. 86, 1980 Wash. App. LEXIS 2214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/modern-builders-inc-v-manke-washctapp-1980.