Auburn Mechanical, Inc. v. Lydig Construction, Inc.

951 P.2d 311, 89 Wash. App. 893
CourtCourt of Appeals of Washington
DecidedFebruary 17, 1998
Docket37764-7-I
StatusPublished
Cited by33 cases

This text of 951 P.2d 311 (Auburn Mechanical, Inc. v. Lydig Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Auburn Mechanical, Inc. v. Lydig Construction, Inc., 951 P.2d 311, 89 Wash. App. 893 (Wash. Ct. App. 1998).

Opinion

Ellington, J.

Pilchuck Mechanical, Inc. undertook to perform excavation work on a Boeing project. 1 Alleging that the job bore little resemblance to the project that was bid, Pilchuck brought a claim against Boeing for breach of an “implied-in-law duty” and asserted a right “to recover under the theory of quantum meruit/unjust enrichment for the amount that it deserves, a reasonable amount for work performed.”

*896 The sole question presented on appeal is whether the trial court erred in striking Pilchuck’s jury demand. Since Pilchuck’s claims were legal, not equitable, denial of a jury trial was error.

Procedure

Pilchuck Mechanical, Inc. performed work under a subcontract with Ellis-Don Construction, Inc., the general contractor on a fuel dock construction project at Boeing’s plant in Everett. Pilchuck notified Boeing and Ellis-Don that extra work was required to complete the job.

Pilchuck filed a claim of lien against Boeing’s property for labor and materials supplied on the project, then sought foreclosure of the lien and recovery of money due for work performed outside the contract, in the amount of $900,000. Ellis-Don also sued Boeing, in part for moneys due under the contract. Ellis-Don assigned the contract claim to Pilchuck before trial, and was no longer a party at the time of trial. Boeing asserted that the work was performed under the contract. Pilchuck filed a jury demand.

The trial court granted Boeing’s motion to strike Pilchuck’s request for a jury trial. Pilchuck then voluntarily dismissed its claim for foreclosure of its lien, and again requested a trial by jury. Concluding Pilchuck’s claims were primarily equitable, the trial court denied the request. Discretionary review in this court and in the Supreme Court was denied.

Following trial, the court awarded judgment to Pilchuck on contract claims, dismissed Pilchuck’s claims for unjust enrichment and recovery in quantum meruit, and dismissed Boeing’s counterclaim. Pilchuck appeals, claiming the trial court erred by denying its request for a jury trial.

Discussion

The Washington Constitution in article I, section 21, provides that “the right to a jury trial shall remain *897 inviolate.” 2 This right has been “jealously guarded by the courts.” 3 In a landmark decision under the seventh amendment, 4 the United States Supreme Court confirmed the centrality of the right to trial by jury: “Maintenance of the jury as a fact-finding body is of such importance and occupies so firm a place in our history and jurisprudence that any seeming curtailment of the right to a jury trial should be scrutinized with the utmost care.” 5

The basic rule in interpreting article I, section 21 of the Washington Constitution is to look to the right as it existed at the time the constitution was adopted in 1889. 6 We look both to the scope of the right and the nature of the action to which it applies. 7 Thus, our constitution has been held to guarantee a right to a jury trial where the civil action is purely legal in nature, but not where the action is purely equitable in nature. 8

Washington follows the historical test in determining whether claims sound in equity or at law. Thus, we look to *898 see whether the claims in question were within the exclusive jurisdiction of the equity courts when the state constitution was adopted in 1889. 9

Where an action is neither purely legal nor purely equitable in nature, the trial court must determine whether it is primarily legal or equitable in nature, and has wide discretion in this exercise. 10 Any doubt should be resolved in favor of a jury trial, in deference to the constitutional nature of the right. 11 For the purpose of determining the primary character of an action, our courts have set forth several factors to be considered:

Such discretion should be exercised with reference to many factors including, but not necessarily limited to the following: (1) who seeks the equitable relief; (2) is the person seeking the equitable relief also demanding trial of the issues to the jury; (3) are the main issues primarily legal or equitable in their nature; (4) do the equitable issues present complexities in the trial which will affect the orderly determination of such issues by a jury; (5) are the equitable and legal issues easily separable; (6) in the exercise of such discretion, great weight should be given to the constitutional right of trial by jury and if the nature of the action is doubtful, a jury trial should be allowed; (7) the trial court should go beyond the pleadings to ascertain the real issues in dispute before making the determination as to whether or not a jury trial should be granted on all or part of such issues.[ 12 ]

It is thus apparent that the preliminary task is to determine whether the various claims are equitable or legal, for if all the claims are legal, the “primary” character *899 of an action is not in question and the right to a jury trial is clear.

The distinction between legal and equitable claims is based on the nature of the action, not the form of the action. 13 The court must examine the pleadings on file at the time the court rules on the motion to strike the jury demand, 14 and “ ‘should go beyond the pleadings to ascertain the real issues in dispute before making the determination as to whether or not a jury trial should be granted on all or part of such issues.’ ” 15 More importantly, courts must examine the remedy sought. 16

The gist of Pilchuck’s claim was that it incurred additional costs because Boeing mismanaged the project, failed to disclose jobsite conditions, and failed to provide a complete set of plans, all of which was outside Pilchuck’s contemplation when it submitted its bid and executed the subcontract. This is commonly referred to as a claim for extra work. For this claim Pilchuck sought money damages.

The subcontract between Pilchuck and Ellis-Don incorporated the prime contract between Ellis-Don and Boeing Commercial Airplane Group. The prime contract provided that if extra work were requested and performed, the parties were to amend the contract to incorporate such extra work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Of Washington, V. Julius Booth
Court of Appeals of Washington, 2022
State Of Washington v. Joel Zellmer
Court of Appeals of Washington, 2020
Pierce County v. Richard E. Sorrels
Court of Appeals of Washington, 2020
Lucas Price v. Daniel Price
Court of Appeals of Washington, 2018
Larry D. Christensen v. Jennifer Roach
Court of Appeals of Washington, 2015
Jones v. MacKey Price Thompson & Ostler
2015 UT 60 (Utah Supreme Court, 2015)
James Waltz v. Tanager Estates Homeowners Association
Court of Appeals of Washington, 2014
Shepler Construction, Inc. v. Leonard
306 P.3d 988 (Court of Appeals of Washington, 2013)
Shepler Construction v. Gary And Susan Leonard
Court of Appeals of Washington, 2013
Pauline B. Schneider v. Jonathan P. Ross
Court of Appeals of Washington, 2013
Foster v. Gilliam
165 Wash. App. 33 (Court of Appeals of Washington, 2011)
Blackmon v. Blackmon
230 P.3d 233 (Court of Appeals of Washington, 2010)
Davenport v. Washington Education Ass'n
147 Wash. App. 704 (Court of Appeals of Washington, 2008)
Davenport v. Washington Educ. Ass'n
197 P.3d 686 (Court of Appeals of Washington, 2008)
Stieneke v. Russi
145 Wash. App. 544 (Court of Appeals of Washington, 2008)
Pierce County v. State
185 P.3d 594 (Court of Appeals of Washington, 2008)
McDowell Welding & Pipefitting, Inc. v. United States Gypsum Co.
149 P.3d 173 (Court of Appeals of Oregon, 2006)
Kim v. Dean
135 P.3d 978 (Court of Appeals of Washington, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
951 P.2d 311, 89 Wash. App. 893, Counsel Stack Legal Research, https://law.counselstack.com/opinion/auburn-mechanical-inc-v-lydig-construction-inc-washctapp-1998.