Irwin Concrete, Inc. v. Sun Coast Properties, Inc.

653 P.2d 1331, 33 Wash. App. 190, 1982 Wash. App. LEXIS 3337
CourtCourt of Appeals of Washington
DecidedOctober 27, 1982
Docket5090-1-II
StatusPublished
Cited by31 cases

This text of 653 P.2d 1331 (Irwin Concrete, Inc. v. Sun Coast Properties, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Irwin Concrete, Inc. v. Sun Coast Properties, Inc., 653 P.2d 1331, 33 Wash. App. 190, 1982 Wash. App. LEXIS 3337 (Wash. Ct. App. 1982).

Opinion

Worswick, J.

This litigation arose out of an unfortunate but familiar occurrence: a grand plan for real estate development gone awry.

In 1972, Olympic Mall Co. borrowed $350,000 from Continental, Inc., to purchase and develop 179 acres of land near Gig Harbor. A deed of trust secured the note. In April 1973, Olympic conveyed 7 of the 179 acres to Sun Coast Properties, Inc., to build a shopping center. The sale contract required Olympic to install a water system on its remaining 172 acres to provide water for the center. The water system was also intended to service additional development on the remaining property. Sun Coast then borrowed $1.5 million from Continental for completion of the center. In October 1973, Sun Coast sold the center site to Gig Harbor Properties, Inc., but continued active in construction of the center. Two months later, Sun Coast, Continental, and Traveler's Insurance Company entered into an agreement whereby Traveler's agreed to pay off Continental's construction loan and make a permanent loan to Sun Coast for $1.5 million upon completion of the center and Sun Coast agreed to prosecute completion of the center diligently.

By April 1974, Olympic was in default on its $350,000 loan from Continental and Continental notified the trustee of default. In September 1974, Continental gave notice of the trustee's sale of the 172 acres to all whose liens were then of record. While these foreclosure proceedings were in progress, Sun Coast, through its president, Michael Fizzolio, continued to let subcontracts for completion of the water system on the 172 acres. In December 1974, Irwin Concrete, Inc., began work pursuant to a contract with Fizzolio and on January 7, 1975, Fox Automatic Sprinkler *193 Systems, Inc., started work under a contract with Sun Coast Water Co., a corporation formed by Sun Coast Properties to complete the water system. David Davis performed work for Fox pursuant to an oral contract. All work pursuant to these contracts was done on various phases of the water system installed on the 172 acres.

At the trustee sale on January 24, 1975, Continental bid in and bought Olympic's interest in the 172 acres. Four days later the shopping center was finished and Traveler's paid off Continental's $1.5 million construction loan. In February 1975, Irwin, Fox, and Davis filed liens on all the land. A fourth claimant, Hernando Chaves and Associates, engineered the water system, working first for Olympic and later for Sun Coast. Chaves filed a lien on all the land on December 5, 1974. The fifth claimant, Active Construction, worked on the water system early in 1974 at the instance of Olympic.

By summary judgment, the trial court dismissed all liens but, after trial, awarded judgment in varying amounts in favor of all five claimants against Continental. Continental appeals. The claimants 1 cross-appeal dismissal of their liens. Primarily at issue is whether the trial court erred in awarding judgment against Continental based on unjust enrichment, in dismissing the liens, in denying prejudgment interest and in dismissing Chaves' promissory estoppel claim. Other satellite issues are also raised. We find no error and affirm.

Unjust Enrichment

Although the liens , were dismissed, the trial court nevertheless allowed a recovery to all claimants on the theory of unjust enrichment. Continental assigns error to this arguing that it did not request any work, that whatever specific benefit it might have received from completion of the shopping center was not proved and that the water system on which claimants worked operates at a loss and therefore *194 constitutes no benefit. We disagree.

Under the doctrine of unjust enrichment, one who receives a benefit must pay for it only if the circumstances of its receipt or retention make it unjust for him to keep the benefit without paying. Chandler v. Washington Toll Bridge Auth., 17 Wn.2d 591, 137 P.2d 97 (1943). A benefit includes any form of advantage. Chandler, 17 Wn.2d at 603. The trial court found that the claimants' work on the water system helped complete the shopping center thereby enabling Continental to close out its $1.5 million construction loan to Sun Coast, and also that the water system increased the value of the 172 acres Continental now owns. 2 These findings are supported by substantial evidence and will not be disturbed on appeal. Hudson House, Inc. v. Rozman, 82 Wn.2d 178, 509 P.2d 992, 61 A.L.R.3d 1163 (1973). Plainly, Continental received a substantial benefit because of the work. Would it be unjust to allow Continental to retain this benefit without paying? The trial court concluded it would be and we agree.

The trial court found that the claimants completed the water system at the urging and with consent of Continental, and that Continental knew about and silently acquiesced in the work when it was foreclosing its deed of trust. Substantial evidence also supports these findings. The record discloses, inter alia, that early in 1974, Continental told Chaves that he had to continue his work in order to receive loan funds. In February 1974, Walt Smith of Active Construction Co. worked on the 172 acres. Before Smith started work, David Ballaine of Continental told him that loan funds from Continental to pay for Smith's work were secure. Late in 1974, Continental knew that Chaves was still certifying work by subcontractors. Continental knew that Irwin, Fox and Davis were working on the water system because Chaves certified their completed work. We *195 conclude that under these circumstances it would be unjust for Continental to receive the benefit of the claimants' work without paying.

Damages

Continental asserts that the trial court erred in awarding damages measured by contract prices, arguing that the correct measure is the value conferred. The argument is correct as far as it goes but that is not far enough, because it simply does not follow that a contract price cannot represent that value. A claim for unjust enrichment is a quasi-contractual claim. Bill v. Gattavara, 34 Wn.2d 645, 209 P.2d 457 (1949). Quantum meruit—"a reasonable amount for the work done"—is the measure of recovery. Heaton v. Imus, 93 Wn.2d 249, 252-53, 608 P.2d 631 (1980). The only evidence presented was that of the various contract prices. It was not error, therefore, for the trial court to conclude, as it did, that the contract prices represented the value of the work in making a quantum meruit award. See Losli v. Foster, 37 Wn.2d 220, 222 P.2d 824 (1950).

Liens

Irwin, Fox, Davis and Chaves cross-appeal from a summary judgment dismissing their liens.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Park South LLC v. Denali Construction LLC
Court of Appeals of Washington, 2024
James & Angela Faire v. Richard Alan Finegold
Court of Appeals of Washington, 2019
Brian Fisse, App. v. Heather M. Garvie, Resp.
Court of Appeals of Washington, 2015
Emond Plumbing & Heating, Inc. v. BankNewport
105 A.3d 85 (Supreme Court of Rhode Island, 2014)
CalPortland Co. v. LevelOne Concrete, LLC
321 P.3d 1261 (Court of Appeals of Washington, 2014)
Calportland Company v. Levelone Concrete, Llc
Court of Appeals of Washington, 2014
CC&H Investments v. Rcs Northwest, LLC
Court of Appeals of Washington, 2013
First American v. Liberty Capital Starpoint
254 P.3d 835 (Court of Appeals of Washington, 2011)
Norcon Builders, LLC v. GMP Homes VG, LLC
254 P.3d 835 (Court of Appeals of Washington, 2011)
Haselwood v. Bremerton Ice Arena, Inc.
137 Wash. App. 872 (Court of Appeals of Washington, 2007)
Seattle Mortgage Co. v. Unknown Heirs of Daisy Gray
136 P.3d 776 (Court of Appeals of Washington, 2006)
Auburn Mechanical, Inc. v. Lydig Construction, Inc.
951 P.2d 311 (Court of Appeals of Washington, 1998)
Ducolon Mechanical, Inc. v. Shinstine/Forness, Inc.
893 P.2d 1127 (Court of Appeals of Washington, 1995)
Brooks v. Hilton Casinos Inc.
959 F.2d 757 (Ninth Circuit, 1992)
Bonneville Power Administration v. Washington Public Power Supply System v. Chemical Bank, Plaintiff-Intervenor-Appellee. Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and Portland General Electric Company Puget Sound Power and Light Company Pacificorp, D/B/A Pacific Power & Light Company Washington Water Power Company ("Wwp"), Defendants- (Two Cases) Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and Snohomish County Public Utilities District No. 1, Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and Washington Public Utilities Group, City of Tacoma, Mason County Pud 3, Benton County Pud, Pacific County Pud 2, Grays Harbor Pud, Lewis County Pud 1, Mason County Pud 1, Okanogan County Pud, City of Ellensburg, Skamania County Pud, Wahkiakum County Pud, Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and City of Richland Chelan County Public Utility District No. 1 Douglas County Public Utility District Grant County Public Utility District No. 2 Clallam County Public Utility District 1, Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and Clark County Public Utility District No. 1, Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and Ferry County Pud No. 1 Kittitas County Pud No. 1, Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and Benton Rural Electric Association, Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and Small Utilities Group, Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and Inland Utilities, Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and City of Seattle, Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and Columbia Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and Inland Power & Light Co., Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System, and Clatskanie Peoples Utility District Northern Wasco Peoples Utility District Tillamook Peoples Utility District Eugene Water & Electric Board City of McMinnville Oregon City of Forest Grove, Oregon Springfield Utility Board Central Lincoln Peoples Utility District, Bonneville Power Administration, and Chemical Bank, Plaintiff-Intervenor-Appellee v. Washington Public Power Supply System
956 F.2d 1497 (Ninth Circuit, 1992)
CKP, Inc. v. GRS Construction Co.
821 P.2d 63 (Court of Appeals of Washington, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
653 P.2d 1331, 33 Wash. App. 190, 1982 Wash. App. LEXIS 3337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/irwin-concrete-inc-v-sun-coast-properties-inc-washctapp-1982.