Norcon Builders, LLC v. GMP Homes VG, LLC

254 P.3d 835, 161 Wash. App. 474
Court of Appeals of Washington·Decided February 28, 2011·No. No. 65251-6-I·Published·Cited by 141 cases

Opinion

Lau, J.

¶1 — Following escrow agent First American’s failure to secure the release of secondary construction lender Liberty Capital’s deed of trust on the sale of five condominium units, Liberty gave notice of intent to nonjudicially foreclose its deed of trust on those units. The unit owners (UOs) appeal the trial court rulings (1) dismissing the quiet title action, (2) dissolving the preliminary injunction, and (3) authorizing nonjudicial foreclosure against their units. They argue (1) title to their units should be quieted in them based on equitable estoppel; (2) a constructive trust should be imposed for the value of their units based on unjust enrichment; and (3) in the alternative, both the UOs and their lenders should be equitably subrogated to the primary lender’s first priority position for the purchase price of their units. Because the UOs fail to establish relief under equitable estoppel and unjust enrichment and because equitable subrogation would result in material prejudice to Liberty, we affirm the trial court rulings.

FACTS

¶2 Owner/developer GMP Homes developed the Starpoint Condominiums in 2006 and 2007 on two parcels of land in Issaquah. To finance construction, GMP borrowed $26 million from Frontier Bank. Norcon Builders LLC, the prime contractor, began construction on the project in the first half of 2006. By July 2006, GMP needed additional construction financing and borrowed $1.9 million from Liberty.1 After [479]*479selling 88 of the 98 units (including the five units that are the subject of this appeal), GMP became insolvent. Frontier, Norcon, and Liberty were each left unpaid.

¶3 The Frontier, Norcon, and Liberty loans were all secured by liens against the project property and units. Except for the five units at issue in this appeal, the creditors’ priority was as follows:

•First-place priority — Frontier, with a claim against all unsold units based on its partial deed that was released with each sold unit.

•Second-place priority — Norcon, based on its mechanic’s lien with a claim against all sold or unsold units.

•Third-place priority — Liberty, as a secondary lender with a claim against all unsold units based on its deeds of trust.

Finding of Fact (FF) 3-4, 12-13, 59-60.

¶4 Liberty’s 2006 loan agreement 2 contemplated that it would receive a “zero payout” on the sales of the first 75 units, with most of the sale price going to pay down Frontier’s superior deed of trust. The agreement allowed for such a procedure “[p]rovided Borrower is not in default.. . and the obligation in favor of Frontier Bank is being reduced at a rate that will amortize such indedebtedness over the course of the first seventy-five (75) Condominium Unit closings.” Ex. 107, at 1. This arrangement would leave proceeds from the final 23 sales available to pay Liberty.

¶5 “Beginning with the first Starpoint unit sale on or about July 30, 2007 . . . First American . . . implemented a standard practice for securing Liberty Capital’s approval [480]*480for each unit sale.” FF 22.3 In order to close a sale at Starpoint, escrow agent First American would “ask[ ] Liberty Capital’s [manager] David Dammarell to ‘email or fax me a notice that you’re collecting $0.00 on this payoff.’ ” FF 22 (quoting Ex. 223); Report of Proceedings (RP) (Jan. 12, 2010) at 31. And First American “needed Liberty Capital’s approval on each closing [and] to confirm that Liberty was in agreement regarding how [the closing agent] would distribute the sale proceeds from each closing.” FF 24. That agreement was required to be in writing. FF 31. Liberty describes the process:

(1) prior to sale closing, (2) First American requested in writing Liberty’s approval of the sale and provided Liberty with a written HUD [Department of Housing and Urban Development] statement indicating the proposed disposition of sale proceeds, (3) which disposition Liberty either conditionally or unconditionally (or, alternatively, not at all) approved, (4) in writing by a confirmatory email sent prior to sale closing.

Br. of Resp’t at 3 (footnote omitted). This description is consistent with Dammarell’s testimony describing the closing process:

“Ms. Warthan [of First America[4] would email me a HUD 1 statement, or I would be cc’d on a HUD 1 statement, and we would review, and if we approved the financial terms of that, then I would email back and say, we are owed zero on this transaction.”

RP (Jan. 13, 2009) at 153.

[481]*481¶6 In all of the Starpoint sales, except those involving the UOs’ condominiums,5 First American requested and received the agreement of Frontier and Liberty to a partial reconveyance of their deeds of trust prior to the closing on each unit. But in the sales of the UOs’ condominiums,6 in August and September 2007, First American failed to ask for or obtain Liberty’s consent to reconvey their deed of trust. The trial court found “by a preponderance of the evidence that First American closed the five disputed closings without receiving any prior approval from Liberty Capital.” FF 53.

¶7 On October 9, 2008, Liberty sent an e-mail to First American asking that it provide a full list of sold units because it did not have complete and accurate records. FF 50 (citing Ex. 237). After reviewing First American’s list of sold units, Dammarell informed First American that there were discrepancies between Liberty’s list of approved sales and First American’s. FF 51. The trial court found that the “earliest time at which [Liberty] understood that it had not provided approvals for the five unit sales” was October 2008.7 FF 45. Liberty maintained that it had not approved a deed reconveyance for the five units and it therefore asked First American to purchase its note. FF 54.

¶8 Meanwhile, on July 18, 2008, Norcon filed this lawsuit to foreclose on its mechanic’s lien against Starpoint.8 Clerk’s Papers (CP) at 1-33. On September 19,2008, Norcon obtained an $821,270.39 default judgment against GMP. CP at 76-78 (Ex. 116). In August 2009, to protect its priority position, Liberty borrowed money to pay off the [482]*482balance on the Frontier loan. FF 46; Ex. 253, 255. Thus, after Liberty paid off Frontier’s outstanding loan balance, the creditors’ priority for the UOs’ condominiums was (1) Norcon, (2) Liberty, (3) the UOs’ mortgage lenders, and (4) the UOs. In October 2009, First American agreed to pay Norcon $670,000.00 to release its lien against 72 sold units, including the UOs’ five units. Ex. 146. Seeking again to protect its position, Liberty agreed to purchase the Norcon lien through a May 26, 2009 settlement agreement that provided for an up-front lump sum payment of $300,000.00 and monthly payments of $50,000.00 beginning in July 2009. FF 56; Ex. 114, at ¶¶ 3.1,3.3. On March 18,2010, after crediting First American’s payment and other monies received, the court entered a $174,870.72 foreclosure judgment on Norcon’s lien. CP at 1870-75.

Free access — add to your briefcase to read the full text and ask questions with AI

Norcon Builders, LLC v. GMP Homes VG, LLC, 254 P.3d 835, 161 Wash. App. 474 (Wash. Ct. App. 2011).

254 P.3d 835 (Norcon Builders, LLC v. GMP Homes VG, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sarah May Allbaugh, V. Benjamin Allbaugh
Court of Appeals of Washington, 2025
Sara Lea Hallin, V. Brian Scott Hallin
Court of Appeals of Washington, 2025
Katherine Dawn Brown, V. Geoffrey Bryan Thomas
Court of Appeals of Washington, 2025
Donald Hoth, V. Edward Hoth
Court of Appeals of Washington, 2024
In Re: Chad A. Schaefer, V. Heather M. Kier
Court of Appeals of Washington, 2024
Steve Hailey, V. Wa State Executive Ethics Board
Court of Appeals of Washington, 2024
2400 Elliott Llc, V. Vp Elite Construction Llc
Court of Appeals of Washington, 2024
In The Receivership Of: Applied Restoration, Inc.
Court of Appeals of Washington, 2023
Elizabeth Settles, V. Dustin Gnewuch And Jamie Gnewuch
Court of Appeals of Washington, 2023
In the Matter of the Dependency of: S.B.
Court of Appeals of Washington, 2023
Wendy Li, V. Roland Ma
Court of Appeals of Washington, 2023
Kenneth Ridout And Erica Ridout, V. Hedgerow, Llc
Court of Appeals of Washington, 2023
Laurence Coates Bateman, V. Phavy Pel
Court of Appeals of Washington, 2023
In Re: Alexi Mikele Turner, And Michael Matthew Turner
Court of Appeals of Washington, 2023
Raymond Budd & Vickie Budd, V. Kaiser Gypsum Co., Inc.
505 P.3d 120 (Court of Appeals of Washington, 2022)
State of Washington v. Gustavo Rodriguez Tapia
Court of Appeals of Washington, 2022
Wellspring Family Service, V. Nancy R. Owen
Court of Appeals of Washington, 2021