Farwest Steel Corp. v. Mainline Metal Works, Inc.

741 P.2d 58, 48 Wash. App. 719
CourtCourt of Appeals of Washington
DecidedAugust 3, 1987
Docket18295-1-I; 18369-9-I
StatusPublished
Cited by36 cases

This text of 741 P.2d 58 (Farwest Steel Corp. v. Mainline Metal Works, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farwest Steel Corp. v. Mainline Metal Works, Inc., 741 P.2d 58, 48 Wash. App. 719 (Wash. Ct. App. 1987).

Opinion

Walterskirchen, J. *

The court has consolidated these cases for the issuance of its opinion.

Nature of the Case

Farwest Steel Corporation appeals from the dismissal by summary judgment of all its claims against Hensel Phelps Construction Company and its surety, Aetna Casualty & Surety Company. Farwest assigns error to the granting of Hensel's motion for summary judgment dismissing Far-west's claims against the project's retainage fund, against the public works bond, and for dismissing its claim for quantum meruit or unjust enrichment.

Valley Welding Supply Company appeals from the dismissal by summary judgment of its claim against Hensel and the University of Washington on the public works retainage fund.

*721 Statement of the Facts

Hensel is the prime contractor on a $34,275,000 addition to the University of Washington Hospital. Hensel contracted with Mainline Metal Works, Incorporated to fabricate and furnish to Hensel metal items for $225,000. All materials supplied by Mainline came from its Oregon facility and were delivered to the jobsite. Mainline did the fabricating in Oregon, and did no on-site labor, installation, or supervision. Mainline contracted with Farwest to supply its steel requirements for the Hensel contract. Valley supplied welding materials and other supplies to Mainline for the same contract. Upon its first delivery to Mainline, Farwest notified Hensel that it was commencing deliveries to Mainline for the Hensel project.

Mainline went into bankruptcy before completing its contract with Hensel. By that time Mainline had accumulated an unpaid balance of $150,000 due to Farwest and $16,520 to Valley. Mainline was required to provide Hensel a certified statement listing any significant debts incurred by Mainline in manufacturing the contract items before Hensel would pay Mainline for them. To obtain its periodic payments from Hensel Mainline falsely certified that it owed nothing to Farwest and Valley. Neither Farwest nor Valley had ever given notice to Hensel that they were not being paid by Mainline.

Farwest and Valley filed their respective suits, each claiming that since Mainline had not paid them, they had a valid claim against the public works retainage fund pursuant to RCW 60.28.010. In addition, Farwest also claimed it was entitled to recover from the public works bond required by RCW 39.08.030. Farwest also claimed it was entitled to recover on the basis of quantum meruit and unjust enrichment. Hensel denied all claims in both suits. Farwest also sued Mainline and secured a judgment for the full amount Mainline owed it. Mainline has not paid the judgment.

On October 28, 1985, Superior Court Judge Gerard M. Shellan granted summary judgment dismissing Farwest's *722 bond and retainage claims against Hensel and Aetna, Hensel's surety. On December 9, 1985, Superior Court Judge Stephen M. Reilly granted summary judgment dismissing Farwest's quantum meruit and unjust enrichment claims. On March 25, 1986, Superior Court Judge James McCutcheon granted summary judgment dismissing Valley's suit.

Issue I

Was Mainline a materialman for Hensel under Hensel's prime contract with the University of Washington where Mainline fabricated materials in its own plant in Oregon, but did no on-site labor, installation, or supervision, and the value of Mainline's contract was less than 1 percent of the total project?

The trial court did not err in characterizing Mainline as a materialman of the prime contractor rather than as a subcontractor, and therefore dismissing Farwest's claim under Washington's public works bond, RCW 39.08.010, and Far-west's and Valley's public works retainage claims under RCW 60.28.010. These statutes cover material suppliers of subcontractors but not material suppliers of materialmen. In order for Farwest and Valley to recover under these statutes Mainline must be found to be a subcontractor.

Both statutes use the terms "subcontractor" and "materialman," but neither statute defines them. Absent statutory definition the terms must be given their plain and ordinary meanings. Garrison v. State Nursing Bd., 87 Wn.2d 195, 196, 550 P.2d 7 (1976). A subcontractor is "one who takes from the principal contractor a specific part of the work, and the term does not include laborers or materialmen." Baker v. Yakima Vly. Canal Co., 77 Wash. 70, 74, 137 P. 342 (1913). Black's Law Dictionary (4th ed. 1951) defines a materialman as a person "who has furnished materials used in the construction or repair of a building, structure, or vessel." There is no Washington case defining materialmen. Cf. J.D. English Steel Co. v. Tacoma Sch. Dist. 10, 57 Wn.2d 502, 358 P.2d 319 (1961) (court expressly declined to review the trial court's finding that a *723 party was a materialman).

There is, however, extensive authority from federal and other jurisdictions distinguishing subcontractors and materialmen in which two basic tests are set forth. Some courts distinguish the two roles by whether there has been any on-site installation or supervision. Other courts use the 2-part substantial relationship test, first articulated in Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102, 88 L. Ed. 1163, 64 S. Ct. 890 (1944), and refined in subsequent cases, which defines a subcontractor as one who (1) performs or takes from the prime contractor a specific part of the labor or material requirements of the original contract and (2) has a substantial and important relationship with the prime contractor. It appears that a substantial and important relationship does not exist where the value of the contract is less than 10 percent of the value of the prime contract.

Most of the cases involving the "substantial relationship” test concern the Miller Act, 47 Stat. 793 (current version at 40 U.S.C. § 270a et seq. (1982)). The Miller Act requires that federal contractors furnish a payment bond for the protection of all persons supplying labor and materials, 40 U.S.C. § 270a (1982), to the prime contractor or subcontractors, 40 U.S.C. § 270b (1982). The act's purpose parallels that of Washington's bond statute, i.e.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monica Arreola-martinez V. State Of Washington
Court of Appeals of Washington, 2026
Kristen Abendroth, V John Ryan Bays
Court of Appeals of Washington, 2022
Puget Sound Security Patrol, Inc. v. William Bates And Kathryn Bates
389 P.3d 709 (Court of Appeals of Washington, 2017)
C. Szabo Contracting, Inc. v. Lorig Construction Company
2014 IL App (2d) 131328 (Appellate Court of Illinois, 2014)
C. Szabo Contracting, Inc. v. Lorig Construction Company
2014 IL App (2d) 131328 (Appellate Court of Illinois, 2014)
CC&H Investments v. Rcs Northwest, LLC
Court of Appeals of Washington, 2013
First American v. Liberty Capital Starpoint
254 P.3d 835 (Court of Appeals of Washington, 2011)
Norcon Builders, LLC v. GMP Homes VG, LLC
254 P.3d 835 (Court of Appeals of Washington, 2011)
Davenport v. Washington Education Ass'n
147 Wash. App. 704 (Court of Appeals of Washington, 2008)
Davenport v. Washington Educ. Ass'n
197 P.3d 686 (Court of Appeals of Washington, 2008)
Dragt v. Dragt/DeTray, LLC
139 Wash. App. 560 (Court of Appeals of Washington, 2007)
Haselwood v. Bremerton Ice Arena, Inc.
137 Wash. App. 872 (Court of Appeals of Washington, 2007)
Better Financial Solutions, Inc. v. Caicos Corp.
117 Wash. App. 899 (Court of Appeals of Washington, 2003)
Geo Exchange Systems, LLC v. Cam
65 P.3d 11 (Court of Appeals of Washington, 2003)
Goel v. Jain
259 F. Supp. 2d 1128 (W.D. Washington, 2003)
Better Financial Solutions, Inc. v. Transtech Electric, Inc.
51 P.3d 108 (Court of Appeals of Washington, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
741 P.2d 58, 48 Wash. App. 719, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farwest-steel-corp-v-mainline-metal-works-inc-washctapp-1987.