Chemical Bank v. Washington Public Power Supply System

691 P.2d 524, 102 Wash. 2d 874
CourtWashington Supreme Court
DecidedNovember 6, 1984
Docket49868-7
StatusPublished
Cited by120 cases

This text of 691 P.2d 524 (Chemical Bank v. Washington Public Power Supply System) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chemical Bank v. Washington Public Power Supply System, 691 P.2d 524, 102 Wash. 2d 874 (Wash. 1984).

Opinions

Rosellini, J.

This case first came before our court in Chemical Bank v. WPPSS, 99 Wn.2d 772, 666 P.2d 329 (1983) (Chemical Bank I) for resolution of the issue of whether 28 municipalities and public utility districts (PUD's) had statutory authority to enter into agreements to build Washington nuclear plants (WNP) 4 and 5. We held that no statutory authority, express or implied, existed and remanded the case for action in accordance with the opinion.

The trial court entered summary judgment in favor of all 88 participants (respondents) in WNP 4 and WNP 5. On appeal, appellants Washington Public Power Supply System (WPPSS) and the bondholders' trustee, Chemical Bank, raise multiple challenges to the trial judge's order of summary judgment.

Appellants also seek review of our decision in Chemical Bank I under the terms of Rule of Appellate Procedure 2.5(c)(2).

This factual and legal background, discussed in Chemical Bank I, is exceedingly complex. The primary legal issues [879]*879discussed at length in this opinion can be summarized as follows:

Procedural Questions

1. Should this court reconsider its decision in Chemical Bank I?

2. Did the trial judge's order granting summary judgment in favor of all defendants exceed the proper scope of the declaratory judgment action initiated by Chemical Bank?

3. Are any bondholders entitled to intervene in this action at this stage in the proceeding?

Contractual Obligation

4. Do the Washington municipalities and PUD's have statutory authority, either express or implied, to enter into contracts which impose the risk of dry holes on their ratepayers?

5. If the Washington municipalities and PUD's did not initially have statutory authority to enter into these contracts, did the Legislature subsequently ratify the agreements?

6. Did the trial judge err in holding that, because the contracts were unenforceable as to the Washington municipalities and PUD's, they were also unenforceable as to the remaining defendants under any of these three theories: (a) indivisibility of contract? (b) mutual mistake? (c) commercial frustration and impracticability?

Availability of Equitable Remedies

7. If the participants are not contractually obligated to the bondholders, are they nonetheless estopped from denying the obligation under either common law notions of estoppel or article 8 of the Uniform Commercial Code?

8. If the contracts are invalid, are the bondholders nonetheless entitled to restitution from the participants?

Constitutional Claims

9. Did the release of the participants' contractual obligation violate the bondholders' constitutional rights?

Our resolution of this case is as follows:

[880]*880I

Procedural Preliminaries

For the reasons discussed below, we believe reconsideration of our decision in Chemical Bank I is appropriate. We find the summary judgment order did not exceed the scope of the declaratory judgment action and conclude the bondholders' motion to intervene should be denied.

II

Contractual Obligations

We herein affirm our decision in Chemical Bank I and reject appellants' arguments that the Legislature ratified the ultra vires contracts. We also affirm the trial judge's release of the 60 remaining participants' obligation on the grounds of commercial frustration and mutual mistake.

III

Equitable Obligations

Our review of the historical origins of equitable estoppel convinces us that the doctrine should not be applied to the facts of this case. We find that the statutory equivalent of equitable estoppel under the Uniform Commercial Code, RCW 62A.8-202, is inapplicable.

IV

We find no violation of appellants' state or federal constitutional rights.

Statement of the Case

Procedurally, this case comes before the court following the trial judge's decision to grant summary judgment in favor of all defendants/participants in WNP 4 and WNP 5. Chemical Bank I contains an extensive factual recitation. In addition, the following information pertains to the present action.

WPPSS is a joint operating agency and municipal corporation composed of 19 Washington public utility districts and four cities. It was formed in 1957 under the provisions of RCW 43.52.360. That statute allows cities or public util[881]*881ity districts and combinations thereof to form an operating agency "for the purpose of acquiring, constructing, operating and owning plants, systems and other facilities . . . for the generation, and/or transmission of electric energy and power." The statute further provides that after such an agency is formed, any other city or PUD may become a member upon application and affirmative vote of a majority of its members. A member may withdraw provided "[t]hat all contractual obligations incurred while a member shall remain in full force and effect." The agency may be dissolved upon the unanimous agreement of its members and "the members, after making provisions for the payment of all debts and obligations, shall thereupon hold the assets thereof as tenants in common."

In the early 1970's, WPPSS started construction of three nuclear power plants, WNP 1, WNP 2, and WNP 3. The projects were developed in conjunction with the Bonneville Power Administration. Although those plants also ran into financial trouble, it is the fate of two subsequent plants, WNP 4 and WNP 5, which concerns us here. Plans for these plants were developed when the 88 participants, respondents, joined with WPPSS and Pacific Power and Light Company (WNP 5 only) to obtain financing.1 Each participant signed an identical 63-page participants' agreement (PA) dated July 14, 1976.

WPPSS then adopted a bond resolution which provided for the construction of both plants and the issuance of revenue bonds. As many of the parties' claims stem from interpretation of the PA, a detailed analysis of this document is necessary.2

As noted in Chemical Bank I, the PA provided that each participant purchase a "share of the Project Capability" [882]*882and "a right to purchase a share of the capability of any other generating plants undertaken by [the] Supply System ..." PA, at 2. Project capability was defined as

the amounts of electric power and energy, if any, which the Projects are capable of generating at any particular time (including times when either or both of the Plants are not operable or operating or the operation thereof is suspended, interrupted, interfered with, reduced or curtailed, in each case in whole or in part for any reason whatsoever), less Project station use and losses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Htp, Inc. v. Jc Aviation Investments, Llc
Court of Appeals of Washington, 2021
Robert Repin v. State of Washington and Washington State University
392 P.3d 1174 (Court of Appeals of Washington, 2017)
In re Det. of Anderson
Washington Supreme Court, 2016
In re the Detention of Anderson
368 P.3d 162 (Washington Supreme Court, 2016)
South Tacoma Way, LLC v. State
169 Wash. 2d 118 (Washington Supreme Court, 2010)
Paopao v. STATE, DSHS
185 P.3d 640 (Court of Appeals of Washington, 2008)
Paopao v. Department of Social & Health Services
145 Wash. App. 40 (Court of Appeals of Washington, 2008)
Paxton v. City of Bellingham
129 Wash. App. 439 (Court of Appeals of Washington, 2005)
Guillen v. Pierce County
110 P.3d 1184 (Court of Appeals of Washington, 2005)
Motley-Motley, Inc. v. Pollution Control Hearings Board
127 Wash. App. 62 (Court of Appeals of Washington, 2005)
Casey v. Chapman
98 P.3d 1246 (Court of Appeals of Washington, 2004)
Carrillo v. City of Ocean Shores
122 Wash. App. 592 (Court of Appeals of Washington, 2004)
Treyz v. Pierce County
76 P.3d 292 (Court of Appeals of Washington, 2003)
Lybbert v. Grant County
1 P.3d 1124 (Washington Supreme Court, 2000)
Cotton v. City of Elma
998 P.2d 339 (Court of Appeals of Washington, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
691 P.2d 524, 102 Wash. 2d 874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chemical-bank-v-washington-public-power-supply-system-wash-1984.