In The Receivership Of: Applied Restoration, Inc.

CourtCourt of Appeals of Washington
DecidedDecember 4, 2023
Docket84320-6
StatusPublished

This text of In The Receivership Of: Applied Restoration, Inc. (In The Receivership Of: Applied Restoration, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In The Receivership Of: Applied Restoration, Inc., (Wash. Ct. App. 2023).

Opinion

NOTICE: SLIP OPINION (not the court’s final written decision)

The opinion that begins on the next page is a slip opinion. Slip opinions are the written opinions that are originally filed by the court. A slip opinion is not necessarily the court’s final written decision. Slip opinions can be changed by subsequent court orders. For example, a court may issue an order making substantive changes to a slip opinion or publishing for precedential purposes a previously “unpublished” opinion. Additionally, nonsubstantive edits (for style, grammar, citation, format, punctuation, etc.) are made before the opinions that have precedential value are published in the official reports of court decisions: the Washington Reports 2d and the Washington Appellate Reports. An opinion in the official reports replaces the slip opinion as the official opinion of the court. The slip opinion that begins on the next page is for a published opinion, and it has since been revised for publication in the printed official reports. The official text of the court’s opinion is found in the advance sheets and the bound volumes of the official reports. Also, an electronic version (intended to mirror the language found in the official reports) of the revised opinion can be found, free of charge, at this website: https://www.lexisnexis.com/clients/wareports. For more information about precedential (published) opinions, nonprecedential (unpublished) opinions, slip opinions, and the official reports, see https://www.courts.wa.gov/opinions and the information that is linked there. For the current opinion, go to https://www.lexisnexis.com/clients/wareports/.

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

In the Matter of the Receivership of: No. 84320-6-I APPLIED RESTORATION, INC. DIVISION ONE

ANDERSEN CONSTRUCTION PUBLISHED OPINION COMPANY,

Appellant,

v.

REVITALIZATION PARTNERS, LLC,

Respondent.

HAZELRIGG, A.C.J. — Andersen Construction Company appeals two

separate orders for turnover issued by a court commissioner in favor of receiver

Revitalization Partners, LLC, and challenges the superior court’s denial of its

motion for revision. Andersen also argues the commissioner erred when they

disallowed its claims against Applied Restoration, Inc. and entered final judgment

in favor of the receiver. Because the record establishes that Andersen repeatedly

refused to comply with the court orders pursuant to the receivership statute and

because Andersen fails to demonstrate any error arising from the decisions of

either the commissioner or judge in this matter, we affirm. For the current opinion, go to https://www.lexisnexis.com/clients/wareports/. No. 84320-6-I/2

FACTS

In May 2019, Applied Restoration, Inc. (ARI) and Andersen Construction

Company entered into an agreement (subcontract) for ARI to perform work on the

construction of the Quil Ceda Creek Casino (project), owned by the Tulalip Tribes

of Washington (owner). ARI served as a subcontractor for Andersen, the general

contractor on the project. In accordance with the agreement, ARI employed nine

to ten laborers per day who worked directly on the project and also subcontracted

with third parties (sub-tier subs) who provided further labor and materials for ARI’s

work on the project. Through March 2020, Andersen paid ARI for the work that it

had performed pursuant to the billing process and terms set out in the subcontract

and prime contract. 1 On March 31, due to ongoing financial difficulties, ARI

assigned all of its assets to Revitalization Partners, LLC and, on April 2, the trial

court entered an order appointing Revitalization as the general receiver of ARI’s

property and assets. At the time of the assignment, ARI had not paid all sub-tier

subs for their work on the project, in violation of the subcontract. On April 6,

Revitalization contacted Andersen, explained that ARI had been placed into

receivership and identified itself as the receiver. 2 Revitalization assured Andersen

that it would continue to operate ARI and fulfill its obligations on the project as

previously agreed.

1 The subcontract expressly incorporated various terms and provisions set out in the prime

contract between Andersen and the owner. 2 “Receivership” simply means “the case in which the receiver is appointed.” RCW 7.60.005(11). A “general receivership” is “a receivership in which a general receiver is appointed” and a “custodial receivership” is “a receivership in which a custodial receiver is appointed.” Id.

-2- For the current opinion, go to https://www.lexisnexis.com/clients/wareports/. No. 84320-6-I/3

Thereafter, Andersen stopped paying ARI and did not pay Revitalization for

the work performed post-assignment. Revitalization demanded assurance from

Andersen that it would pay ARI for the work, but Andersen refused absent certain

conditions: “If the Receiver cannot guarantee that it will pay all pre-receivership

claims related to this Project, then Andersen cannot issue April’s payment, the

Receiver must reject the subcontract agreement and Andersen will find another

subcontractor.” According to Andersen, Revitalization was not entitled to payment

from Andersen because the “unequivocal language of the Subcontract between

Andersen and ARI . . . control[led] the terms of payment to ARI and/or the

Receiver.” Revitalization had paid sub-tier subs $42,467.25 for post-assignment

work and ARI extended over $200,000.00 on work and materials for the project

during that time.

Between May and July 2020, Revitalization filed three motions against

Andersen for turnover of the subcontract funds pursuant to RCW 7.60.005(9) and

.070. On May 15, Revitalization filed its first motion, seeking $157,342.97, but that

motion was denied as the project owner had not yet paid Andersen, accordingly it

had neither possession or control of the funds. The statute requires either

possession or control of funds as a prerequisite to turnover. RCW 7.60.070.

Roughly two weeks later, the owner issued payment to Andersen for work ARI had

completed in April 2020. Revitalization then requested confirmation from

Andersen that it would pay ARI for post-assignment work but, on June 3, Andersen

again refused to do so unless Revitalization guaranteed that it would pay all pre-

assignment claims related to the project.

-3- For the current opinion, go to https://www.lexisnexis.com/clients/wareports/. No. 84320-6-I/4

On June 4, Revitalization told Anderson that ARI’s employees would not be

working on the project that day due to “Andersen’s unwillingness to commit to

paying [ARI] for the work being done, as well as the completed work.” That same

day, Andersen forwarded a letter to Revitalization from the owner to demand return

of its $113,480.89 payment to Andersen for the work on the project in April. On

June 5, Revitalization demanded Andersen turn over the subcontract funds for the

May billing and provided notice of another action for turnover, but Andersen

refused and, further, remitted the April funds to the owner.

On June 11, Revitalization filed a second motion for turnover for the April

billing. On July 7, after reviewing the motion, accompanying declarations, and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Streater v. White
613 P.2d 187 (Court of Appeals of Washington, 1980)
Tapper v. Employment Security Department
858 P.2d 494 (Washington Supreme Court, 1993)
Olsen Media v. Energy Sciences
648 P.2d 493 (Court of Appeals of Washington, 1982)
Lovric v. Dunatov
567 P.2d 678 (Court of Appeals of Washington, 1977)
SAC Downtown Ltd. Partnership v. Kahn
867 P.2d 605 (Washington Supreme Court, 1994)
CKP, Inc. v. GRS Construction Co.
821 P.2d 63 (Court of Appeals of Washington, 1991)
Allen v. American Land Research
631 P.2d 930 (Washington Supreme Court, 1981)
Wallace Real Estate Investment Inc. v. Groves
881 P.2d 1010 (Washington Supreme Court, 1994)
River House Development, Inc. v. Integrus Architecture
272 P.3d 289 (Court of Appeals of Washington, 2012)
Kinney v. Cook
208 P.3d 1 (Court of Appeals of Washington, 2009)
Friend v. Friend
964 P.2d 1219 (Court of Appeals of Washington, 1998)
TS v. Boy Scouts of America
138 P.3d 1053 (Washington Supreme Court, 2006)
Yurtis v. Phipps
181 P.3d 849 (Court of Appeals of Washington, 2008)
United States v. William Aubrey
800 F.3d 1115 (Ninth Circuit, 2015)
Per & Melody Westerdal v. Name Intelligence, Inc.
195 Wash. App. 170 (Court of Appeals of Washington, 2016)
Jose Maldonado v. Noemi Lucero Maldonado
391 P.3d 546 (Court of Appeals of Washington, 2017)
Wenatchee Sportsmen Ass'n v. Chelan County
4 P.3d 123 (Washington Supreme Court, 2000)
T.S. v. Boy Scouts of America
157 Wash. 2d 416 (Washington Supreme Court, 2006)
Faciszewski v. Brown
386 P.3d 711 (Washington Supreme Court, 2016)
Mony Life Insurance v. Cissne Family, L.L.C.
148 P.3d 1065 (Court of Appeals of Washington, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
In The Receivership Of: Applied Restoration, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-the-receivership-of-applied-restoration-inc-washctapp-2023.