River House Development, Inc. v. Integrus Architecture

272 P.3d 289, 167 Wash. App. 221
CourtCourt of Appeals of Washington
DecidedMarch 15, 2012
Docket29889-2-III
StatusPublished
Cited by53 cases

This text of 272 P.3d 289 (River House Development, Inc. v. Integrus Architecture) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
River House Development, Inc. v. Integrus Architecture, 272 P.3d 289, 167 Wash. App. 221 (Wash. Ct. App. 2012).

Opinion

*224 Siddoway, J.

¶1 A contractual right to mediate or arbitrate a dispute may be waived, including by pursuing litigation. River House Development Inc. appeals the trial court’s determination that it waived its right to mediate and then arbitrate a construction dispute with its architect by filing what River House contends was a protective lawsuit, engaging in discovery and discovery motion practice, and participating in and complying with the court’s scheduling procedures.

¶2 We hold that whether the right to arbitrate has been waived by litigation conduct is an issue to be resolved by the court, not the arbitrator, as urged by River House. While arbitration is favored under Washington law and River House clearly asserted its right to arbitrate in its complaint, it thereafter took too many steps down the path of litigation and too few down the path of arbitration to reasonably claim that its conduct was consistent with a continuing right to arbitrate. We affirm.

FACTS AND PROCEDURAL BACKGROUND

¶3 River House Development Inc. engaged Integras Architecture PS to provide architectural services for a condominium project, using an American Institute of Architects (ALA) standard form agreement. 1 The contract included alternative dispute resolution (ADR) provisions providing for mediation, and then arbitration, of disputes arising out of or related to the agreement.

¶4 The project reached substantial completion in the summer and fall of 2008. River House took issue with the *225 quality and timeliness of the construction. When its general contractor commenced arbitration against River House, it responded with a counterclaim against the general contractor for the asserted problems and deficiencies. It resolved its dispute with the general contractor through mediation. In the process of mediating that dispute, River House came to believe that many of the problems with construction were a result of Integrus’s failure to meet its contractual obligations.

¶5 In February 2010, River House sent a six-page demand letter to Integras, outlining its claims and an estimated $3.2 million in resulting damages, and stating its intent to pursue mediation and arbitration. 2 It followed up with correspondence to Integras expressing concern that limitations periods for some claims might run shortly and requesting a tolling agreement, a draft of which it forwarded to Integras in early March. On March 17, after Integras refused to enter into the proposed agreement, River House served, but did not file, a complaint styled for filing in the Spokane County Superior Court. The complaint alleged that the parties’ contract “provides that INTEGRUS and RHD [River House] agree to mediate and/or arbitrate disputes arising under the Contract prior to completing litigation.” Clerk’s Papers (CP) at 11 (Compl. ¶ 3.6). It prayed for judgment in its favor awarding damages, costs, and fees, but at the same time “[f]or an order staying this litigation and compelling the parties to engage in alternative dispute resolution as provided in the Contract.” Id. at 13-14.

¶6 The parties corresponded frequently in the several months that followed. River House proposed an informal, agreed discovery process in early April. Integras responded that it intended to serve formal interrogatories and requests for production. River House ultimately served formal discovery first, dispatching its first set of interrogato *226 ries and requests for production in late April. Integras served its first set of interrogatories and requests for production in June.

¶7 On June 1, River House filed its complaint, apparently in light of the tolling statute at RCW 4.16.170 and a continuing concern about limitations issues. If arbitration was intended, filing suit in superior court was unnecessary and potentially insufficient; statutes of limitation apply to arbitration proceedings only if and as provided by the arbitration agreement. Broom v. Morgan Stanley DW, Inc., 169 Wn.2d 231, 243, 236 P.3d 182 (2010); City of Auburn v. King County, 114 Wn.2d 447, 450, 788 P.2d 534 (1990). But River House argues that this was not entirely clear until our Supreme Court’s decision in July 2010 in Broom. After the lawsuit was filed, both River House and Integras continued to express a desire to mediate the dispute.

¶8 The first step toward actually staying the litigation was suggested by River House in August. A status report was due to be filed with the court before September 10, the date set by the court for a status conference with the assigned judge. Among the information required by the court’s report form was whether “the parties agree to go through mediation/alternative dispute resolution.” CP at 286. The form also asked whether there were any “unique issues requiring special preparation by the court.” Id. River House proposed to answer “yes” to the inquiry about mediation/alternative dispute resolution and to advise the court, with regard to “unique issues requiring special preparation,” that

[t]he parties’ contract requires mediation and arbitration. The parties will be pursuing those dispute resolution methods precedent to continued litigation in this Court and may request that the Court stay the matter until such time as those methods have been exhausted.

Id. At the same time, however, River House proposed indicating a two-week estimated “length of trial” and that a 12-person jury would be demanded. Id. at 286-87.

*227 ¶9 Integrus’s response to the proposed joint case status report signaled that it remained committed to mediation but did not acknowledge any continuing duty to arbitrate. It struck River House’s proposed language indicating that arbitration was required and would be pursued. A September 8 letter from Integrus’s lawyer transmitting the revised report to River House stated:

In regard to paragraph 2.d., I recommend that your inserted language be deleted. There is no need for this inclusion at this time as it does not affect scheduling for the case. There is ample time for the parties to mediate, as we have all agreed to do, long before any trial date in this case. Likewise, the language is not accurate as RHD has not filed an arbitration claim. Finally, the question on paragraph 2.d. asks about special “issues requiring preparation by the court.” The issue of mediation does not require special court preparation or court intervention.
With regard to your proposed stipulation to stay the case, we do not agree to the same. We have always said that Integras will mediate this dispute with River House Development, Inc. The sole issue has been the timing of mediation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert W. Cooney, V. Hillary A. Brooks
Court of Appeals of Washington, 2025
Brialle Engelhart, V. Wren Hansen
Court of Appeals of Washington, 2025
Siddharth Jha, V. Varisha Mahmood Khan
Court of Appeals of Washington, 2024
Roy D. Cheesman, V. Ford Motor Company
Court of Appeals of Washington, 2024
In The Receivership Of: Applied Restoration, Inc.
Court of Appeals of Washington, 2023
Purvi Gandi-Kapoor v. Hone Capital LLC
Court of Chancery of Delaware, 2023
In Re The Donna Clark Irrevocable Trust
Court of Appeals of Washington, 2023
Biochron, Inc. v. Blue Roots, LLC
529 P.3d 464 (Court of Appeals of Washington, 2023)
Tammy Dietrich, V. Bruce Neely M.d.
Court of Appeals of Washington, 2023
King County, V. Abdulhafid Tahraoui, Et Ano
Court of Appeals of Washington, 2022
Lorena Keisling, V. Rite Aid, Corp.
Court of Appeals of Washington, 2022
In the Matter of the Parentage of: E.S.
Court of Appeals of Washington, 2022
Kevin P. Clare v. Telquist McMillen Clare PLLC
501 P.3d 167 (Court of Appeals of Washington, 2021)
Melissa Newman v. Michael Martinek
Court of Appeals of Washington, 2020
Pagecom, Inc. v. Sprint Solutions, Inc.
Court of Appeals of Washington, 2020
In the Matter of the Parentage of: G.N.M.-B.
Court of Appeals of Washington, 2020

Cite This Page — Counsel Stack

Bluebook (online)
272 P.3d 289, 167 Wash. App. 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/river-house-development-inc-v-integrus-architecture-washctapp-2012.