Prier v. Refrigeration Engineering Co.

442 P.2d 621, 74 Wash. 2d 25, 1968 Wash. LEXIS 726
CourtWashington Supreme Court
DecidedJune 20, 1968
Docket38859
StatusPublished
Cited by234 cases

This text of 442 P.2d 621 (Prier v. Refrigeration Engineering Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prier v. Refrigeration Engineering Co., 442 P.2d 621, 74 Wash. 2d 25, 1968 Wash. LEXIS 726 (Wash. 1968).

Opinion

Neill, J.

This is an action for damages arising out of the construction of an ice rink known as the Burien Ice Chalet. Plaintiff Chalet employed an architect and a general contractor to design and construct the building, and employed defendant to design and install the ice arena portion of the project. The architect had no experience in the design of refrigeration installations, so plaintiff directed him to consult with Mr. Frost, defendant’s supervisor, on all details of this portion of the project. The architect and Mr. Frost consulted with each other, and defendant presented specifications for the refrigeration system and the base upon which the ice sheet would rest.

The base for the ice sheet as specified by defendant consisted of 2 feet of gravel covered by a plastic sheet under which dual purpose (ventilating and drainage) tiles were installed. Defendant was to install a system for forcing heated air through the tile, but failed to do so.

Plaintiff opened the ice rink for business on December 29, 1962. Within a short time heaving and unevenness of the ice surface was noted. Pools of water began to collect on the ice sheet. Investigation for the cause of this condition disclosed that freezing of the gravel and soil under the *27 ice sheet had occurred to a depth of 4 feet. Corrective action was necessary to prevent damage to the foundations of the building.

Plaintiff closed the business on July 31, 1963, and engaged soils engineers to determine the cause of the failure of the ice sheet and to recommend corrective measures. These engineers recommended that the gravel and tile be replaced with an insulated floor constructed on piers 2 feet above the ground surface and that positive heated air ventilation be provided in the air space. The engineers further found that, due to moisture condition in the soil, the ventilation system promised by defendant, but never installed, would have been inadequate, or only marginally effective.

The cost of the original project was approximately $157,000, of which some $36,000 was for defendant’s services. Plaintiff arranged for defendant to make the suggested modifications. The following costs were incurred in completing the modification:

Soils Engineers $ 1,085.53
Defendant’s new contract 10,345.92
General contractor’s new contract 24,662.17
Miscellaneous 96.09
Total $ 36,189.71

No issue is raised as to the amount of these costs or as to the necessity for modification, but at trial defendant strenuously resisted the claim that it was liable therefor.

This action was originally brought against the architect, the general contractor, and defendant. The trial court dismissed the action as to the architect and general contractor, and plaintiff has not appealed that order.

The trial court found defendant liable in tort for negligently advising plaintiff that the ice sheet and base it designed would be suitable, and entered judgment against defendant in the sum of $20,000, computed as follows:

General damages (the cost of the original project plus the cost of the repairs, minus the cost of the project had it been constructed properly) $ 17,500
Consequential damages (losses due to closure of the business) $ 2,500

*28 Interest was allowed from the date of judgment.

Defendant’s liability is not at issue upon this appeal, except as to the theory upon which liability should be based. Plaintiff argues that it was error to base liability on tort rather than contract and that the trial court erred in failing to find that defendant made express and implied warranties that the ice sheet and designed base would be reasonably fit for its intended function.

Plaintiff asks for $36,189.71 general damages (the total cost of corrective measures), and $17,200 consequential damages for the following:

Losses prior to closing because of unsatisfactory ice surface and resultant loss of business $ 1,200
Losses during closure $ 6,600
Losses after closure due to business interruption and necessity of re-establishing clientele $ 9,400

Plaintiff also urges that interest should be awarded on the amount of general damages from October 17, 1963, the date repairs were completed.

We will discuss the general damages, consequential damages, and interest issues separately.

General Damages

We agree that plaintiff’s recovery is properly based upon the full cost of tearing out the faulty ice sheet and base and installing the properly designed system. The original contract provided that defendant would install:

(a) Complete refrigeration cycle serviced by a 75 HP compressor. System to he complete per service intended.
(b) Complete condensing water system with cooling tower sized for maximum summer design for this area.
(c) Complete brine system utilizing plastic piping to adequately maintain the ice sheet. (70' x 146'). (Italics ours.)

The following items of labor and materials were to be furnished by others than defendant:

(a) Base floor, pipe trench, equipment room and general construction including all building construction.
*29 (b) Electrical and control wiring.
(c) Water and drains to area of cooling tower.

The evidence shows that defendant designed the base upon which the ice sheet rested, and that the base was an inseparable part of the refrigeration system. Where a person holds himself out as qualified to furnish, and does furnish, specifications and plans for a construction project, he thereby impliedly warrants their sufficiency for the purpose in view. See Hoye v. Century Builders, Inc., 52 Wn.2d 830, 329 P.2d 474 (1958).

The trial court erred in the measure of damages it used and in failing to find that defendant made warranties, implied in law if not express, that it would construct an ice sheet upon a base designed by it, which would reasonably function as an ice skating arena. See Hoye, supra, at 833.

The trial court reasoned that plaintiff received something more than he originally bargained for, and therefore required him to absorb the additional cost of making the structure a workable skating arena. We believe this to be incorrect. The expenditures for the modifications were necessary to give plaintiff what he contracted to receive in the first place, namely, a usable ice rink at a fixed price. The modified structure was no more elaborate than would have had to be provided in the first instance if plaintiff was to have a usable ice rink on that site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mal Icious, Llc, V Random Erik Vaughn
Court of Appeals of Washington, 2025
Jammeh v. HNN Associates LLC
W.D. Washington, 2020
Bryan W. McLelland, DDS, et ux v. Mark C. Paxton, DDS, et ux
453 P.3d 1 (Court of Appeals of Washington, 2019)
Sarah Gosney, Res/cross-apps. v. Fireman's Fund Ins. Co., Apps/cross-res.
419 P.3d 447 (Court of Appeals of Washington, 2018)
Heidi Rachael Silver v. Matthew Benjamin Silver
Court of Appeals of Washington, 2017
Cory Newingham v. John Newingham
Court of Appeals of Washington, 2017
Kassa Ins. Services v. Ryan Pugh, et ux
Court of Appeals of Washington, 2014
Rekhter v. Dep't of Soc. & Health Servs.
Washington Supreme Court, 2014
Cummings v. Budget Tank Removal & Environmental Services, LLC
260 P.3d 220 (Court of Appeals of Washington, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
442 P.2d 621, 74 Wash. 2d 25, 1968 Wash. LEXIS 726, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prier-v-refrigeration-engineering-co-wash-1968.