Cascade Concrete Industries, Inc. v. Central Washington Asphalt, Inc

CourtCourt of Appeals of Washington
DecidedDecember 23, 2025
Docket40429-3
StatusUnpublished

This text of Cascade Concrete Industries, Inc. v. Central Washington Asphalt, Inc (Cascade Concrete Industries, Inc. v. Central Washington Asphalt, Inc) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cascade Concrete Industries, Inc. v. Central Washington Asphalt, Inc, (Wash. Ct. App. 2025).

Opinion

FILED DECEMBER 23, 2025 In the Office of the Clerk of Court WA State Court of Appeals, Division III

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION THREE

CASCADE CONCRETE INDUSTRIES, ) INC., A WASHINGTON ) No. 40429-3-III CORPORATION, ) ) Appellant, ) ) v. ) UNPUBLISHED OPINION ) CENTRAL WASHINGTON ASPHALT, ) INC., A WASHINGTON ) CORPORATION; SAFECO ) INSURANCE COMPANY OF ) AMERICA, BOND NO. 6425449, ) ) Respondents. )

COONEY, J. — Cascade Concrete Industries, Inc. (Cascade) entered into a contract

with Central Washington Asphalt, Inc. (CWA), a major highway contractor, to supply

sound barrier walls. The contract required CWA to pay Cascade for extra costs

associated with alterations or deviations to the walls. A 1.5 percent monthly interest

charge would be applied to any invoice that CWA failed to timely remit. No. 40429-3-III Cascade Concrete v. Central Washington Asphalt

Cascade sued after CWA refused to pay the extra costs incurred in manufacturing

the walls. A jury found CWA breached the contract and awarded Cascade $625,968.00

in damages. Thereafter, the trial court declined to award Cascade prejudgment interest

and limited postjudgment interest to the statutory rate of 12 percent rather than Cascade’s

demand for the contract rate of 18 percent.

Cascade appeals, arguing the trial court erred in: (1) failing to award prejudgment

interest at a rate of 18 percent, (2) refusing to award Cascade prejudgment interest on its

liquidated claim, and (3) refusing to award Cascade the contractual postjudgment interest

at the rate of 18 percent. Both parties seek attorney fees and costs on appeal. We

disagree with each contention and affirm.

BACKGROUND

CWA, a contractor specializing in major highway construction projects for the

state of Washington, contracted with the Washington State Department of Transportation

(WSDOT) for a significant road construction project on State Route 17 (SR 17) near

Moses Lake, Washington.

In August 2006, CWA contracted with Cascade for 4,602 lineal feet of sound

absorbing barriers, called “Whisper Wall,” for the SR 17 project. Clerk’s Papers (CP) at

73. The contract required CWA to pay extra costs incurred by Cascade for any alteration

or deviation to the walls. The contract required CWA to pay Cascade for completed

work, subject to a finance charge:

2 No. 40429-3-III Cascade Concrete v. Central Washington Asphalt

PAYMENT TERMS: CSNW/[Cascade] will invoice [CWA] for completed work/materials on the 25th day of each month. [CWA] will remit payment to CSNW/[Cascade] upon the 10th day of the following month. Full payment will be paid within thirty (30) days of completion of the retaining wall. Late payments bear a finance charge of one and one-half percent (1-1/2%) per month.

Ex. 13 at 2.

CWA repeatedly directed Cascade to deviate from its standard method for

precasting the Whisper Wall. One directive prohibited the use of accelerators in the

concurring curing process, a standard component of Cascade’s method for constructing

the Whisper Wall. Another directive required Cascade to refrain from lifting the panels

from the molds until the concrete reached 70 percent of its breaking strength, rather than

the standard 50 percent. These deviations extended the curing period from 1 day to 3,

increasing the total casting time from approximately 30 days to 100 days.

On March 1, 2007, Cascade’s president, Rick Peterson, informed CWA’s

president of operations, Pamp Maiers, Jr., that the changes would result in additional

costs for which CWA would be responsible.

[Cascade] has redesigned the Whisper Wall™ system as requested, incurring considerable cost in doing so. .... If we are required to cast without an accelerator and achieve 70% strength prior to removing the panels from the forms it would greatly increase the Whisper Wall™ panel casting time, and add unnecessary cost to the project.

3 No. 40429-3-III Cascade Concrete v. Central Washington Asphalt

Ex. 52 at 1-2. The requests for alterations and deviations extended to the issue of edge

picking. 1 On October 3, 2007, Cascade formally contested CWA’s rejection of its edge

pick submittal. Mr. Peterson wrote to CWA:

The added work and new conditions rendered the original schedule useless together with making it impossible to complete the project at our agreed purchase order price. .... This has substantially increased our manufacturing cost and delayed our production. A preliminary completion of added cost to meet the requirements is outlined in Appendix “A”. These costs should not be considered final as the work and added costs are ongoing.

Ex. 103 at 1 (emphasis added).

On January 30, 2008, Cascade sued CWA for breach of contract, damages under

the Uniform Commercial Code, quantum meruit, and cardinal change. CWA filed

counterclaims irrelevant to this appeal.

While construction on the project and litigation continued, on February 20, 2008,

Cascade submitted a 78-page document to CWA. The first pages of the document are

titled “INITIAL BID” and state “BID PRICE $1,209,432.44.” Ex. 145 at 1-2. The next

four pages are titled “OVERRUNS” and state “BID PRICE $1,365,052.23.” Ex. 145 at

3-6. The remaining 72 pages contain hundreds of entries consisting of names of

individuals and businesses, each with a corresponding dollar amount. Following project

Edge picking refers to potential damage to the edges of precast elements during 1

removal from molds or while being handled and stored.

4 No. 40429-3-III Cascade Concrete v. Central Washington Asphalt

completion, Mr. Peterson prepared a comprehensive billing statement for the additional

costs. However, the record contains no evidence that this final bill was ever submitted to

CWA. Cascade’s accountant, Dale Huffman, later conducted an audit and determined the

actual cost overrun to be $902,275.86. CWA refused to pay the amount.

Cascade first asserted that the extra costs associated with CWA’s requested

alterations and deviations to the walls amounted to $1,365,052.23, as listed in exhibit

145. Cascade’s president testified about the genesis of exhibit 145:

[DEFENSE]: Now, taking a look at the first six pages of Exhibit 145, I guess my—my main two questions are who drafted it and what’s— what’s its purpose? ....

[PETERSON]: You know, I’m not sure who drafted it. I certainly didn’t do all this typing because I’m not a typist person, but I did have input into it. And it was an estimate—a guesstimate. .... [DEFENSE]: Page 6 of [Exhibit] 145. It says 1,000,000—it’s highlighted, but it says $1—

[PETERSON]: Right.

[DEFENSE]: —365,052.23. What does that number represent to you?

[PETERSON]: I can’t read it on my copy.

[DEFENSE]: Okay. I’ll represent to you that his shaded-in number is $1,365,052.23.

[PETERSON]: Yes.

5 No. 40429-3-III Cascade Concrete v. Central Washington Asphalt

[DEFENSE]: What does that number represent to you?

[PETERSON]: I think that was the cost overrun number. That’s what it represents. This was preliminary to the final cost occurring that the auditor, CPA, accountant did when we filed the claim.

Rep. of Proc. (RP) (July 12, 2023) at 131-32.

The jury ultimately found CWA had breached the contract and awarded Cascade

$625,968.00 in damages. Thereafter, Cascade successfully moved the trial court for an

award of attorney fees and costs. It also moved for postjudgment interest and

prejudgment interest under two theories.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Best
950 P.2d 1 (Washington Supreme Court, 1998)
Hansen v. Rothaus
730 P.2d 662 (Washington Supreme Court, 1986)
Xebek, Inc. v. Nickum & Spaulding Associates, Inc.
718 P.2d 851 (Court of Appeals of Washington, 1986)
Prier v. Refrigeration Engineering Co.
442 P.2d 621 (Washington Supreme Court, 1968)
Lee v. Lozier
945 P.2d 214 (Court of Appeals of Washington, 1997)
CKP, Inc. v. GRS Construction Co.
821 P.2d 63 (Court of Appeals of Washington, 1991)
Kiewit-Grice v. State
895 P.2d 6 (Court of Appeals of Washington, 1995)
Queen City Farms, Inc. v. Central Nat'l Ins. Co. of Omaha
882 P.2d 703 (Washington Supreme Court, 1995)
State v. Hill
870 P.2d 313 (Washington Supreme Court, 1994)
Bellon Wrecking & Salvage Co. v. Rohlfing
81 S.W.3d 703 (Missouri Court of Appeals, 2002)
Farm Credit Bank v. Tucker
813 P.2d 619 (Court of Appeals of Washington, 1991)
Boeing Co. v. Aetna Casualty & Surety Co.
784 P.2d 507 (Washington Supreme Court, 1990)
Shovel Transfer & Storage, Inc. v. Pennsylvania Liquor Control Board
739 A.2d 133 (Supreme Court of Pennsylvania, 1999)
In the Matter of Aurora Fed. Sav. & Loan Assoc.
162 A.2d 739 (Court of Appeals of Maryland, 1960)
Wright v. DAVE JOHNSON INS. INC.
275 P.3d 339 (Court of Appeals of Washington, 2012)
Hearst Communications v. Seattle Times Co.
115 P.3d 262 (Washington Supreme Court, 2005)
Kitsap County v. Allstate Ins. Co.
964 P.2d 1173 (Washington Supreme Court, 1998)
Keystone Masonry, Inc. v. GARCO CONST.
147 P.3d 610 (Court of Appeals of Washington, 2006)
SCOCCOLO CONST. v. City of Renton
145 P.3d 371 (Washington Supreme Court, 2006)
Umpqua Bank v. Shasta Apartments, LLC
378 P.3d 585 (Court of Appeals of Washington, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Cascade Concrete Industries, Inc. v. Central Washington Asphalt, Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cascade-concrete-industries-inc-v-central-washington-asphalt-inc-washctapp-2025.