Bellon Wrecking & Salvage Co. v. Rohlfing

81 S.W.3d 703, 2002 Mo. App. LEXIS 1630, 2002 WL 1748647
CourtMissouri Court of Appeals
DecidedJuly 30, 2002
DocketED 80127
StatusPublished
Cited by17 cases

This text of 81 S.W.3d 703 (Bellon Wrecking & Salvage Co. v. Rohlfing) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bellon Wrecking & Salvage Co. v. Rohlfing, 81 S.W.3d 703, 2002 Mo. App. LEXIS 1630, 2002 WL 1748647 (Mo. Ct. App. 2002).

Opinion

PAUL J. SIMON, Judge.

Bellon Wrecking & Salvage Company (appellant) appeals the judgment entered in favor of John Rohlfing (Rohlfing) and Keith Kalkbrenner (Kalkbrenner), doing *705 business as the St. Louis Hardwood Building Partnership (Partnership), and Saint Louis University (University) (collectively respondents), on their motion for summary judgment.

On appeal, appellant contends that the trial court erred by: (1) granting respondents’ motion for summary judgment on appellant’s quantum meruit claim for extra compensation because there existed genuine issues of material fact as to whether the work in question was contemplated by the contract or controlled by it, in that the parties to the contract each referred to the work as not anticipated; and (2) entering summary judgment against appellant for failure to provide the notice of lien in the exact manner and at the time required by section 429.012.1 RSMo (2000) (all further references herein shall be to RSMo 2000 unless otherwise noted) because there existed genuine issues of material fact in that the trial court “overlooked substantial compliance in that it mischaracterized appellant’s settlement letter as a first invoice and failed to recognize substantial compliance through the notice to owner given (sic).” We reverse and remand.

Summary judgment is a drastic remedy, bordering on a denial of due process and effectively denying the opposing party a day in court. Butler v. Hurlbut, 826 S.W.2d 90, 94 (Mo.App. E.D.1992). Therefore, when considering an appeal from an entry of summary judgment, we review the record in the light most favorable to the non-movant. Ackerman Buick v. General Motors Corporation, 66 S.W.3d 51, 53 (Mo.App. E.D.2001). The propriety of summary judgment is purely an issue of law and our review is essentially de novo. The criteria we apply in determining the propriety of summary judgment are no different from those that should be employed by the trial court in making its initial determination. Id.

The movant’s burden on its motion for summary judgment is to show a right to judgment flowing from facts about which there are no genuine disputes. Id. at 53, 54. The movant may establish its right to summary judgment by showing: (1) facts that negate any one of the non-movant’s element facts; (2) that the non-movant has not been able to produce and will not be able to produce evidence sufficient to allow the trier of fact to find the existence of any one of the non-movant’s elements; or (3) that there is no genuine dispute as to the existence of facts necessary to support the movant’s properly pleaded affirmative defense. Id. at 54.

The non-movant must show by affidavit, depositions, answers to interrogatories, or admissions on file, that one or more material facts shown by the movant to be beyond any genuine dispute is, in fact, genuinely disputed. Id. A “genuine issue” is a real, non-ffivolous dispute, which exists where the record contains competent materials showing two contradictory, plausible accounts of the essential facts. Id. Such dispute is real and not merely argumentative, imaginary, or frivolous. Id.

The record in the light most favorable to appellant, the non-movant, reveals that Rohlfing and Kalkbrenner were partners of and doing business as the Partnership, which owned property under contract for sale to the University, which in turn wanted a building located on the property demolished prior to closing.

The Partnership sought bids from several companies, including appellant, for the demolition. Appellant was experienced in demolition and examined the building on three separate occasions prior to the bidding. On one such occasion, Rohlfing took appellant and other prospective bidders on a one-hour tour of the building, during which he informed appellant that the Partnership had filled some machine pits locat *706 ed in the building floor with “rock and gravel” and then covered them with a layer of concrete, at a cost of approximately $15,000. The pits themselves could not be seen and, though it was in his possession, Rohlfing did not give appellant a copy of a schematic showing the layout of the property and location of the pits.

Thereafter, appellant and the Partnership entered into a written contract for demolition of the building, which provided, inter aha:

1) [Appellant] will make the necessary arrangements, for disconnection of electricity and gas.
2) Water taps will be destroyed and sewer will be cápped.
3) Freon from air-conditioning equipment will be removed per EPA Regulations.
4) We will obtain all necessary permits.
5) We will demolish the building hauling all combustible material to an appropriate landfill, including footings, foundations and floors.
6) The site will be fine graded to match existing grade and seeded.
7) We will remove all asphalt and concrete paving and sidewalks on said property.
* ⅜ ⅜
9) The structure will be razed in a first-class, work-man-like manner, utilizing both heavy equipment and hand-wrecking procedures as the situation requires.
[[Image here]]
13) The above will be completed at a cost of [$103,600] and the environmental portion will be completed at a cost of [$20,000]. Total cost of demolition and environmental work [$123,600],

A signed addendum to the contract provided, in pertinent part:

[[Image here]]
Contractor further agrees to demolish all buildings and improvements and underground storage tanks that are on the property and that such work will be completed in accordance with all local, state and federal regulations.
This contract is for demolition and removal of the present building that occupies the site. If underneath this building, there are other buried improvements from previous structures that removal is not included in this contract.

Pursuant to the contract, appellant began demolishing the building, after which Rohlfing delivered a copy of the schematic to appellant. Upon excavation, appellant discovered approximately twenty solid, concrete equipment bases as much as six feet thick located at the bottom of the machine pits. Appellant had not foreseen this condition and the bases were “altogether different from the pits.” Appellant began removing the bases on November 18, 1998, and informed Rohlfing that the bases were “real thick, we’ve got a problem.”

Rohlfing visited the site to review the situation. He did not instruct appellant to stop work, and told appellant that he would inform the University of the problem.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dopplick v. Ortheco LLC
E.D. Missouri, 2023
Holliday Investments, INC. v. Hawthorn Bank
476 S.W.3d 291 (Missouri Court of Appeals, 2015)
City of Cape Girardeau ex rel. Kluesner Concreters v. Jokerst, Inc.
402 S.W.3d 115 (Missouri Court of Appeals, 2013)
Guidry v. Charter Communications, Inc.
269 S.W.3d 520 (Missouri Court of Appeals, 2008)
Cornerstone Mortgage, Inc. v. Ponzar
254 S.W.3d 221 (Missouri Court of Appeals, 2008)
Lee Deering Electric Co. v. Pernikoff Construction Co.
247 S.W.3d 577 (Missouri Court of Appeals, 2008)
Olathe Millwork Co. v. Dulin
189 S.W.3d 199 (Missouri Court of Appeals, 2006)
Building Erection Services Co. v. Plastic Sales & Mfg. Co.
163 S.W.3d 472 (Missouri Court of Appeals, 2005)
Rhodes Engineering Co. v. Public Water Supply District No. 1
128 S.W.3d 550 (Missouri Court of Appeals, 2004)
Woodson v. City of Independence
124 S.W.3d 20 (Missouri Court of Appeals, 2004)
Hart v. Kupper Parker Communications, Inc.
114 S.W.3d 342 (Missouri Court of Appeals, 2003)
Wilson Ex Rel. Wilson v. Simmons
103 S.W.3d 211 (Missouri Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
81 S.W.3d 703, 2002 Mo. App. LEXIS 1630, 2002 WL 1748647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bellon-wrecking-salvage-co-v-rohlfing-moctapp-2002.