Wisch & Vaughan Construction Co. v. Melrose Properties Corp.

21 S.W.3d 36, 2000 Mo. App. LEXIS 734, 2000 WL 626722
CourtMissouri Court of Appeals
DecidedMay 16, 2000
Docket22768
StatusPublished
Cited by8 cases

This text of 21 S.W.3d 36 (Wisch & Vaughan Construction Co. v. Melrose Properties Corp.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wisch & Vaughan Construction Co. v. Melrose Properties Corp., 21 S.W.3d 36, 2000 Mo. App. LEXIS 734, 2000 WL 626722 (Mo. Ct. App. 2000).

Opinion

JAMES K. PREWITT, Judge.

Defendant Melrose Properties Corporation appeals from a judgment in accordance with a jury verdict in favor of Plaintiff. Plaintiff sued Defendant for breach of contract for Defendant terminating Plaintiff as the contractor for the construction of a motel.

Defendant contracted with Plaintiff to build a two-story, sixty-unit motel in St. James, Missouri, for which Defendant would pay Plaintiff the sum of $1,534,-218.00. A provision for price adjustments was included, in the event that any changes or additions to the plans increased the scope of the work and resulted in an increase in cost or labor for Plaintiff.

The contract between the parties, dated April 15, 1994, included that the motel be substantially complete within 142 calendar days after a “Notice to Proceed” was issued by Defendant. The project was to be “fast tracked,” meaning that construction would begin prior to the completion of final architectural plans and specifications.

In the event of Plaintiffs default due to failure to perform diligently, abandonment or cessation of work, or failure “in any way to perform the conditions,” the contract provided that Defendant could, after providing seven days’ notice, terminate the contract, take over the construction or any part thereof, and finish the project. Under such default, any unpaid balance would be withheld pending completion of the project. If the unpaid balance exceeded the expense of completion, the excess would be paid to Plaintiff, but if the expense of completion exceeded the unpaid balance, such excess would be paid by Plaintiff to Defendant, in addition to remedies for liquidated damages.

“Retainage,” as provided for in the contract, was to be withheld from payments to Plaintiff, at the rates of: 10% until architect’s notification that work is at least 50% complete; 5% from the time work is 50% complete until substantially complete; and finally, two times the amount of the cost of all items on Defendant’s “punch list” (essentially clean-up and debris removal) from the time of substantial completion until total completion. Final payment to Plaintiff would be made when hen releases were provided to Defendant.

Notice to proceed with construction was issued June 21, 1994. Plaintiff had commenced excavation and other site preparation as early as May, 1994. Final plans were received from Defendant’s architect on July 23, 1994. The 142-day “substantially complete” provision would have required completion by November 10, 1994. Three change orders were ultimately “approved,” which resulted in an increase of $120,695.98 ($1,654,913.98 total contract price after adjustment).

Plaintiff continued with the construction after the expected completion date of November 10, 1994. On January 5, 1995, it requested an additional 51 days to complete the project. On February 3, 1995, Plaintiff predicted the construction would be completed by April 6, 1995. When Defendant requested that Plaintiff work *40 weekends and schedule double shifts (without an increase in the contract price), Plaintiff refused. Defendant then gave seven days’ notice of termination, allowing an additional seven days at Plaintiffs request for negotiations. Defendant terminated Plaintiff and took over the construction on February 24, 1995. The motel opened May 29,1995.

Plaintiff brought its action, alleging breach of contract in Defendant’s termination of Plaintiff as contractor and in preventing Plaintiff from completing the project. Defendant counterclaimed, alleging breach of contract in that Plaintiff failed to complete the project in the time required under the contract.

Defendant filed a motion for a directed verdict following the close of the evidence, which the court denied. The jury returned a verdict of $170,288.00 for Plaintiff. There was no verdict returned on Defendant’s counterclaim, and the trial court dismissed the counterclaim with prejudice. 1

In its first point, Defendant asserts that the trial court erred in denying its motion for directed verdict with respect to Plaintiffs claim for extra work for three reasons:

A. [Plaintiff] was not entitled to such damages, in that such work was additional work included within the contract, rather than extra work not contemplated by the contract;
B. If such damages were extra work, [Plaintiff] was not entitled to collect them, in that [Plaintiff] faked to comply with the contract conditions to obtaining additional compensation;
C. [Plaintiff] is not entitled to quantum meruit damages, in that it neither pleaded nor proved such damages

When reviewing a failure to grant a directed verdict for the defendant, the evidence is viewed in the light most favorable to the plaintiff, the plaintiff is afforded all reasonable inferences from the evidence, and any of the defendant’s evidence that contradicts the plaintiffs claim is disregarded. Crabtree v. Bugby, 967 S.W.2d 66, 70 (Mo.banc 1998).

We first discuss Plaintiffs claim for extra work. Defendant contends that “[v]ir-tually all of’ what Plaintiff claimed was extra work was work “either within ‘the general scope’ of its component list, or covered by Change Order No. 2.” Further, Defendant contends Plaintiffs only remedy would have been to submit a change order.

“Extra work in the context of building contracts refers to work not contemplated by the parties at the time of contract and entirely independent of what is required in performance of the contract.” Waddington v. Wick, 652 S.W.2d 147, 150 (Mo.App.1983). “A distinction is sometimes made between extra work, additional work, and alterations. Additional work is work necessarily required in the performance of the contract, but the necessity of which arises from unanticipated conditions. Alterations are changes in the form of the work which do not destroy its identity.” Id., at 150 n. 5. Generally, determination of whether item or activity is “extra” and not something already contemplated under the contract, is question for finder of fact. Gilmartin Bros., Inc. v. Kern, 916 S.W.2d 324, 331 (Mo.App.1995).

Plaintiff sought damages for twelve items of “extra work,” denominated in the jury’s verdict as “change of scope work.” The jury awarded damages for eleven of the twelve items. It is apparent that if Plaintiff made a submissible case on any of the twelve items, then the motion for directed verdict for the extra work was properly denied. Neither the motion for directed verdict nor the points relied on presented here alleged error as to any of the specific twelve items.

Defendant emphasizes that under the contract Plaintiff was to construct the mo *41 tel in accordance with the architect’s detailed drawings without additional compensation if they were within “the general scope” of the component list or written change orders.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ozark Mountain Granite & Tile Co. v. Dewitt & Associates, Inc.
372 S.W.3d 556 (Missouri Court of Appeals, 2012)
Metzler Contracting Co. LLC v. Stephens
774 F. Supp. 2d 1073 (D. Hawaii, 2011)
Cornejo v. Crawford County
153 S.W.3d 898 (Missouri Court of Appeals, 2005)
Spirtas Co. v. Division of Design & Construction
131 S.W.3d 411 (Missouri Court of Appeals, 2004)
Bellon Wrecking & Salvage Co. v. Rohlfing
81 S.W.3d 703 (Missouri Court of Appeals, 2002)
Enos v. Ryder Automotive Operations, Inc.
73 S.W.3d 784 (Missouri Court of Appeals, 2002)
Jones v. State
10 S.W.3d 449 (Supreme Court of Arkansas, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
21 S.W.3d 36, 2000 Mo. App. LEXIS 734, 2000 WL 626722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wisch-vaughan-construction-co-v-melrose-properties-corp-moctapp-2000.