Ozark Mountain Granite & Tile Co. v. Dewitt & Associates, Inc.

372 S.W.3d 556, 2012 WL 3143830, 2012 Mo. App. LEXIS 960
CourtMissouri Court of Appeals
DecidedAugust 3, 2012
DocketNo. SD 31529
StatusPublished

This text of 372 S.W.3d 556 (Ozark Mountain Granite & Tile Co. v. Dewitt & Associates, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ozark Mountain Granite & Tile Co. v. Dewitt & Associates, Inc., 372 S.W.3d 556, 2012 WL 3143830, 2012 Mo. App. LEXIS 960 (Mo. Ct. App. 2012).

Opinion

NANCY STEFFEN RAHMEYER, Judge.

DeWitt & Associates, Inc. (“DeWitt”), brings this appeal from a judgment against it and in favor of Ozark Mountain Granite & Tile Co. (“Ozark Mountain”), on its claims for breach of contract and for quantum meruit. DeWitt claims trial court error in failing to enforce an article of the subcontract. It further claims that the judgment was against the weight of the evidence on both claims. We find no error and affirm the judgment.

In the light most favorable to the judgment, the following evidence was adduced.1 DeWitt, a general contractor, had a contract with Missouri State University for the carpentry package of Construction Issue No. 4, a phase of the construction of JQH Arena. The contracted Architect/Engineer on the project was Ellerbe Becket, Inc., an arena designer architect.2 In order to complete its work, DeWitt entered into a Subcontract Agreement (“the Subcontract”)3 with Ozark Mountain for the sum of $145,470.00 for granite fabrication and installation in the JQH Arena luxury suites. Ozark Mountain is a company that sells, fabricates, and installs granite in both commercial and residential construction.

Article 1.1 of the Subcontract states:

1.1 The Contractor employs the Subcontractor as an independent Contractor, to perform the following part of the Work that the Contractor has contract with the Owner to provide on the project:
Specification 07900-Joint Sealants, as applicable to your Sections: scope of work;
09380 — Cut Natural Stone Tile. Including Alternate No. 9.
The Subcontractor agrees to perform such part of the Work (hereinafter called “Subcontractor’s Work”) under the general direction of the Contractor and subject to the final approval of the Architect/Engineer or other specified representative of the Owner, in accordance with the Contract Documents. Subcontractor will furnish all of the labor and materials, along with competent supervision, shop drawings and samples, tools, equipment, scaffolding, and permits, which are necessary for such performance.

Listed as a Contract Document in the Subcontract was Addendum No. 5, which modified the scope of work to “Granite Countertops and drinkrails per Specification Section 09380, including, but not limited to granite tops, aprons, substrates, sealants, and adhesives.” The Subcontract also required Ozark Mountain to submit shop [559]*559drawings, which were to be given to De-Witt to ensure that both parties were “on the same page.” DeWitt requested shop drawings from Ozark Mountain on more than one occasion and Ozark' Mountain prepared the drawings by highlighting areas of the architectural drawings that would be receiving granite, and delivered those drawings to DeWitt. These shop drawings4 were delivered about three months before the contract was signed and about a year before Ozark Mountain actually began performing work on the arena. In the shop drawings, certain areas were identified as “countertops” and “drink rails.” Ozark Mountain cut, fabricated, and installed every granite countertop and every drink rail that was specified in the shop drawings.

During the course of Ozark Mountain’s performance under the Subcontract, a dispute arose as to whether certain work was part of the scope of work under the Subcontract. The work included all of the granite located on the divider walls between the suites at JQH Arena as well as the granite that is placed at the bottom of the suites in front of the seats.5 The work that is in dispute (“the Disputed Work”) is horizontal from a wall, drops at an angle down the divider following the staircase down to the bottom of the stairs, and then extends across in front of the seats with glass attached to its top.

The areas labeled “drink rail” in the architectural drawings are 42 inches from the floor and 12 inches wide. In contrast, the Disputed Work is 22.5 inches from the floor and between 2.5 and 5.5 inches wide.

Once it became apparent that the Disputed Work had not been installed, DeWitt requested a bid from Ozark Mountain for the remaining work. Ultimately, Ozark Mountain offered to cut and install the granite trim and wall caps for approximately $72,000.00. DeWitt hired a different company to complete the work and paid $93,896.96 to have the Disputed Work completed.

In addition to the Disputed Work, Ozark Mountain made a claim for additional work it performed on the project. During the project, Ozark Mountain did a mock-up of a suite, which included the fabrication and installation of a vanity or sink top and the installation of a wet bar. Despite being constructed according to the plans, there was a problem with the location of the bowl on the vanity due to the way the cabinets were made and the location of the plumbing. The problem was not a problem with the fabrication but with the plans in terms of where the plans indicated the bowl was supposed to be. Ozark Mountain had to redo the granite on the countertop in the mock-up. Ozark Mountain claimed this redo of the granite countertop cost $2,700.00 in additional materials and services rendered as required by the Subcontract.

Prior to the dispute that is the subject of this suit, DeWitt paid Ozark Mountain [560]*560$81,000.00 under the Subcontract for installing countertops and drink rails. Ozark Mountain filed suit against DeWitt to recover damages per the contract. Count I of the Petition claimed that Ozark Mountain completed the work required under the Subcontract and claimed DeWitt breached the Subcontract by failing to pay $64,470.00 (the difference between the Subcontract price of $145,470.00 and the $81,000.00 already paid by DeWitt). Count II sought recovery under a quantum meruit theory for the $2,700.00 Ozark Mountain claimed it was owed for the additional materials and services related to the redo of the mock-up suite. DeWitt filed its Answer and Counterclaim, alleging that Ozark Mountain “failed and refused to install the granite drink rail, including the apron and tops inside the glass rails at the suites” and demanding $23,427.00 in damages. DeWitt amended its Counterclaim to demand $29,426.00 in damages (the difference between the amount which remained owing under the Subcontract, $64,470.00, and the cost incurred by De-Witt to have the Disputed Work completed, $93,896.00). The court found in favor of Ozark Mountain on both counts, awarding $64,470.00 and $2,700.00, respectively, plus prejudgment interest and taxable court costs. The court also found against DeWitt on its counterclaim. DeWitt appeals; it also seeks recovery of expenses incurred on appeal, including reasonable attorney’s fees, pursuant to Articles 9 and 10 of the Subcontract.

Point I

In its first point, DeWitt argues that the Subcontract contained a specific provision, Article 1.3, which defined the Architect/Engineer on the project as the arbiter of any disputes relating to the interpretation of the drawings and specifications and that the trial court erred by ignoring the testimony of Cheryl Doran that the Disputed Work consisted of tops and aprons. Article 1.3 of the Subcontract reads:

Should questions arise with respect to the interpretation of the drawings and specifications, such questions shall be submitted to the Architect/Engineer and his decision shall be final and binding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wisch & Vaughan Construction Co. v. Melrose Properties Corp.
21 S.W.3d 36 (Missouri Court of Appeals, 2000)
Houston v. Crider
317 S.W.3d 178 (Missouri Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
372 S.W.3d 556, 2012 WL 3143830, 2012 Mo. App. LEXIS 960, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ozark-mountain-granite-tile-co-v-dewitt-associates-inc-moctapp-2012.