Department of Corrections v. Fluor Daniel, Inc.

160 Wash. 2d 786
CourtWashington Supreme Court
DecidedJuly 6, 2007
DocketNo. 78290-3
StatusPublished
Cited by14 cases

This text of 160 Wash. 2d 786 (Department of Corrections v. Fluor Daniel, Inc.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Department of Corrections v. Fluor Daniel, Inc., 160 Wash. 2d 786 (Wash. 2007).

Opinions

¶1 The parties before us agreed to resolve their underlying dispute in binding arbitration. Fluor Daniel, Inc., prevailed and moved to reduce the arbitration award to judgment. Concluding that the arbitration award liquidated previously nonliquidated damages, the trial court reduced that award to judgment and added prejudgment interest from the date the arbitrator rendered the award to the time it was entered into judgment. We conclude that an arbitration award does not transform an unliquidated claim into a fully liquidated sum entitling the prevailing party to prejudgment interest. Unliquidated damages accrue interest from the date of judgment, not the date of an arbitration award. We affirm the Court of Appeals and remand to the trial court for entry of judgment without prejudgment interest.

Chambers, J.

FACTS

¶2 The Department of Corrections (Department) contracted with Fluor to build a prison. Clerk’s Papers (CP) at 3. The parties tell us that “major disputes developed,” leading to “extremely expensive” litigation. CP at 3.1 Shortly before the scheduled trial, Fluor and the Department negotiated and signed a partial settlement and dispute resolution agreement, agreeing to resolve their dispute through binding arbitration. The dispute proceeded to arbitration, and the arbitrator found in favor of Fluor for $5,997,645.

¶3 Twenty-one days later, Fluor reduced the award to judgment. Fluor asked, over the Department’s objection, for prejudgment interest from the date of the arbitration until [789]*789judgment. Fluor’s request for prejudgment interest was based on the theory that the amount of damages became liquidated by virtue of the arbitration award. The trial judge agreed and awarded Fluor prejudgment interest of $43,380.22. The Department appealed only the award of prejudgment interest.2 The Court of Appeals reversed. Dep’t of Corr. v. Fluor Daniel, Inc., 130 Wn. App. 629, 126 P.3d 52 (2005). Fluor sought and we granted review. Dep’t of Corr. v. Fluor Daniel, Inc., 158 Wn.2d 1005, 143 P.3d 829 (2006).

ANALYSIS

¶4 Only questions of law are presented. Our review is de novo. Parents Involved in Cmty. Sch. v. Seattle Sch. Dist. No. 1, 149 Wn.2d 660, 670, 72 P.3d 151 (2003).

¶5 A party is entitled to prejudgment interest if the damages awarded are liquidated. Historically, contract damages were considered “liquidated” if they could be determined by “reference to a fixed standard contained in the contract, without reliance upon opinion or discretion,” and interest has long been available from the moment of breach. Mall Tool Co. v. Far W. Equip. Co., 45 Wn.2d 158, 176, 273 P.2d 652 (1954) (emphasis omitted); see also Wright v. City of Tacoma, 87 Wash. 334, 353, 151 P. 837 (1915) (same); 14A Karl B. Tegland, Washington Practice: Civil Procedure § 35.13, at 434 (2003). It is comparatively easy to determine whether damages are liquidated when the parties’ own contract so provides. E.g., Trompeter v. United Ins. Co., 51 Wn.2d 133, 316 P.2d 455 (1957) (claim was liquidated where the amount due was specifically provided for in the insurance policy). Sometimes statutory law will provide fixed standards that will allow damages to be liquidated. E.g., Egerer v. CSR W., LLC, 116 Wn. App. 645, 653-56, 67 [790]*790P.3d 1128 (2003) (claim was liquidated where measure of damages to be used was fixed by statute as the difference between the contract price and the prevailing market price at the time of the breach). This court has recently found a claim for overtime was liquidated when we could determine the amount precisely. Bostain v. Food Express, Inc., 159 Wn.2d 700, 723, 153 P.3d 846 (2007) (claim for overtime was liquidated where objective evidence indicated the overtime due with exactness). These principles have been applied even occasionally in the tort context. E.g., Hansen v. Rothaus, 107 Wn.2d 468, 473-75, 730 P.2d 662 (1986). However, damages that cannot be calculated without the use of discretion are not liquidated. E.g., Safeco Ins. Co. v. Woodley, 150 Wn.2d 765, 773, 82 P.3d 660 (2004) (claim for legal fees could not be considered liquidated where the amount of expenses lay within the discretion of the trial judge); Weyerhaeuser Co. v. Commercial Union Ins. Co., 142 Wn.2d 654, 687, 15 P.3d 115 (2000) (claim for damages from an environmental clean-up project was unliquidated where determining the amount required testimony allocating certain clean-up bills between areas covered and not covered by insurance); Maryhill Museum of Fine Arts v. Emil’s Concrete Constr. Co., 50 Wn. App. 895, 903, 751 P.2d 866 (1988) (museum’s claim for damages resulting from water leaks was unliquidated where the museum was unique and thus lacked a market value and the measure of damages was consequently left to the trial court’s discretion).

¶6 If damages are liquidated, interest accrues from the time they were incurred. Hansen, 107 Wn.2d at 473 (“plaintiff should be compensated for the ‘use value’ of the money representing his damages for the period of time from his loss to the date of judgment” (emphasis added)). Nothing in our case law or the underlying jurisprudence supports the proposition that the character of damages changes from unliquidated to liquidated by virtue of being decided. See generally Weyerhaeuser Co., 142 Wn.2d at 686 (character of the claim determines whether damages are liquidated).

¶7 Generally, interest on a damage award begins to run when judgment is formally entered by a trial court, not [791]*791when a jury reaches a verdict or a trial court announces a decision. RCW 4.56.110(4), .115; Kiessling v. Nw. Greyhound Lines, Inc., 38 Wn.2d 289, 297, 229 P.2d 335 (1951). No Washington court has held that a damage award for breach of contract changed character by virtue of being decided, and every time the question has been posed, the court has decided that it did not. See, e.g., Kiessling, 38 Wn.2d at 297 (specifically rejecting argument that interest should begin to accrue when the verdict is rendered (citing Rood v. Horton, 132 Wash. 82, 231 P. 450 (1924) (verdict of jury); Phifer v. Burton, 141 Wash. 186, 251 P. 127 (1926) (award of a judge))). Instead, the moment damage claims are decided, they become subject to the civil rules and laws governing judgments.3

¶8 We turn now to Pluor’s arguments. Fluor does not argue that its damages were liquidated before the arbitrator reached his decision.4 Thus, if this case had been tried in court rather than arbitrated, no prejudgment interest would be available. See Boespflug v. Wilson, 58 Wn.2d 333, 336,

Related

Peninsula Housing Authority, V Lee Ann Daniels
Court of Appeals of Washington, 2017
Brian Fisse, App. v. Heather M. Garvie, Resp.
Court of Appeals of Washington, 2015
Kassa Ins. Services v. Ryan Pugh, et ux
Court of Appeals of Washington, 2014
Peters v. Amazon Services LLC
2 F. Supp. 3d 1165 (W.D. Washington, 2013)
Saleemi v. Doctor's Associates, Inc.
292 P.3d 108 (Washington Supreme Court, 2013)
Elcon Construction, Inc. v. Eastern Washington University
273 P.3d 965 (Washington Supreme Court, 2012)
Yakima County v. LAW ENFORCEMENT OFFICERS
237 P.3d 316 (Court of Appeals of Washington, 2010)
Yakima County v. Yakima County Law Enforcement Officers Guild
157 Wash. App. 304 (Court of Appeals of Washington, 2010)
Almquist v. City of Redmond
140 Wash. App. 402 (Court of Appeals of Washington, 2007)
Mercier v. GEICO Indemnity Co.
139 Wash. App. 891 (Court of Appeals of Washington, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
160 Wash. 2d 786, Counsel Stack Legal Research, https://law.counselstack.com/opinion/department-of-corrections-v-fluor-daniel-inc-wash-2007.