Creative Builders, Inc. v. Avenue Developments, Inc.

715 P.2d 308, 148 Ariz. 452, 1986 Ariz. App. LEXIS 423
CourtCourt of Appeals of Arizona
DecidedJanuary 23, 1986
Docket1 CA-CIV 7537
StatusPublished
Cited by15 cases

This text of 715 P.2d 308 (Creative Builders, Inc. v. Avenue Developments, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Creative Builders, Inc. v. Avenue Developments, Inc., 715 P.2d 308, 148 Ariz. 452, 1986 Ariz. App. LEXIS 423 (Ark. Ct. App. 1986).

Opinion

OPINION

HAIRE, Judge.

The primary issue in this appeal is whether the trial court erred in modifying an arbitration award by including preaward interest in the judgment confirming the award.

Avenue Developments, Inc. (Avenue) entered into a construction contract with Creative Builders, Inc. (Creative) to build a mini-storage and office facility for Avenue. A dispute arose prior to completion of the building and Avenue ordered Creative off the job and refused to pay the balance of the contract. Creative filed a lien against the property as did various materialmen and subcontractors who had not been paid.

Creative filed suit against Avenue on November 27, 1979 for monies due and foreclosure of its lien. Avenue filed a motion to dismiss or in the alternative to compel arbitration according to the arbitration clause contained in the contract. The trial court granted the motion to compel arbitration and arbitration proceedings were commenced in September of 1981. Other actions which had been filed by various materialmen or subcontractors against Avenue relating to the building project -were not stayed during the pendency of the arbitration proceedings. As a result, various judgments were entered and liens were foreclosed against Avenue prior to the issuance of the arbitrators’ award concerning the claims asserted by Creative against Avenue.

On March 23, 1982 the arbitrators issued an award which provided in part:

“1. Respondent [Avenue] shall pay to claimant [Creative] the sum of Forty-four thousand three hundred and ninety-eight dollars and 95 cents. ($44,398.95). “2. Claimant shall pay the AZCO, Dean Steel, R & K and any other liens out *454 standing and shall deliver to Respondent a full and complete release of said liens and a dismissal of all lawsuits relating to the property.
“3. The administrative fees and expenses of the American Arbitration Association shall be borne by the parties equally. Said fees and expenses shall be paid as directed by the Association.
“4. The fees for the remuneration of the arbitrators shall be borne by the parties equally.
“5. Each party shall bear its own attorney’s fees and costs.
“THIS AWARD IS IN FULL SETTLEMENT OF ALL CLAIMS SUBMITTED TO THIS ARBITRATION.”

Based upon questions raised by the parties, the trial court twice remanded this matter to the arbitrators for clarification of the award. 1 On November 2,1982 the arbitrators handed down a supplement to the award which said in part:

“Respondents, Avenue Developments, Inc., aka North American Development Corp., et al, shall receive credit for the Dean Steel lien which has been paid by them.”

The trial court again referred this matter back to the arbitrators on March 21, 1983 for a clarification of whether Avenue was entitled to a credit for a Deansteel lien which had already been paid or whether credit should also be allowed for an additional Deansteel judgment which had previously been paid by Avenue. 2 The arbitration panel then issued an additional supplement to the award which provided in part:

“It was the intention of the Arbitrators in the original Award of March 23, 1982 and the Amended Award of November 2, 1982, that the Respondent, Avenue Development, shall receive credit for the Deansteel lien and the Deansteel judgment paid by them.”

Both Avenue and Creative then filed motions for confirmation of the award. See A.R.S. § 12-1514. Although the parties differed as to the appropriate language to be included in the judgment confirming the award, neither party suggested in its motion or included in its proposed form of judgment any provision for the awarding of any interest, pre-award or otherwise, on the amount awarded by the arbitrators.

On June 21, 1983, the court issued a minute entry order providing:

“IT IS ORDERED that Defendant, Avenue deposit the sum of $3,059.50 into an interest bearing account at a bank to be disclosed to all other parties and to the court.
“FURTHER ORDERED that Creative’s lien is hereby released. The eventual judgment in this case should reflect 10% interest dating from the date of the lien, which appears to be August 21, 1979. Mr. Hill [counsel for Avenue] is requested to prepare a formal judgment for lodging consistent with the foregoing.” (Emphasis added).

The sum of $3,059.50 represented the balance of the $44,398.95 award after credit to Avenue for the payment of liens and a judgment for which Creative was responsible pursuant to the clarified award.

Avenue then prepared a judgment in compliance with the court’s directive. Creative objected to the proposed form of judgment arguing that it was entitled to interest on the full amount of $44,398.95 from August 21, 1979. Avenue objected to Creative’s request for additional interest and also expressed disagreement with the awarding of any interest. The court then entered a new order authorizing interest at 10% on the award of $44,398.95 from August 1979, and gave Avenue credit against that amount for payments it had made prior to confirmation of the award. A formal judgment was thereafter entered and Avenue filed a timely appeal.

*455 Avenue contends that the trial court’s judgment constituted an impermissible modification of the arbitration award. Avenue argues that the court could not change the amount awarded by the arbitrators and therefore the court erred in increasing that amount by awarding prejudgment interest. Alternatively, it contends that if the court could modify the award, the court erred as to the date from which the interest should run.

Before addressing the merits of these issues, we first address Creative’s contention that Avenue did not preserve these issues for appeal. Creative argues that Avenue should have objected to the form of the judgment. It asserts that Avenue approved the judgment and did not file a formal objection to the award of interest either before or after the judgment was approved. Thus, Creative contends that Avenue has waived the issue. This contention is without merit.

The record discloses that in response to Creative’s objection to the form of the judgment which had been lodged by Avenue, Avenue strongly expressed its contention that the trial court was without authority to award prejudgment interest. Although it indicated its willingness to pay interest on the amount of $3,059.50 because the amount was minimal, it did so with the express reservation that its acquiescence was not to be considered as an agreement that the award of prejudgment interest was proper. Further, it strenuously objected to the inclusion of interest on the $44,398.95 in the judgment. Given this record, we find that Avenue has preserved the issue of whether the trial court’s award of prejudgment interest constituted an impermissible modification of the award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roberts v. Del Webb
Court of Appeals of Arizona, 2015
Schmidt v. Schmidt
Court of Appeals of Arizona, 2014
Cannon General Contractors, Inc. v. Mock
302 S.W.3d 772 (Missouri Court of Appeals, 2010)
Department of Corrections v. Fluor Daniel, Inc.
160 Wash. 2d 786 (Washington Supreme Court, 2007)
STATE DEPT. OF CORRECTIONS v. Fluor Daniel, Inc.
161 P.3d 372 (Washington Supreme Court, 2007)
Duncan v. National Home Insurance Co.
36 P.3d 191 (Colorado Court of Appeals, 2001)
Arbitration Between Kalawaia v. AIG Hawai'i Insurance Co.
977 P.2d 175 (Hawaii Supreme Court, 1999)
Schilling v. Allstate Insurance
980 P.2d 1014 (Idaho Supreme Court, 1999)
National Avenue Building Co. v. Stewart
972 S.W.2d 649 (Missouri Court of Appeals, 1998)
Ebasco Constructors, Inc. v. Ahtna, Inc.
932 P.2d 1312 (Alaska Supreme Court, 1997)
Mausbach v. Lemke
866 P.2d 1146 (Nevada Supreme Court, 1994)
Sansone v. Metropolitan Property & Liability Insurance
572 N.E.2d 588 (Massachusetts Appeals Court, 1991)
Foust v. Aetna Casualty & Insurance Co.
786 P.2d 450 (Colorado Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
715 P.2d 308, 148 Ariz. 452, 1986 Ariz. App. LEXIS 423, Counsel Stack Legal Research, https://law.counselstack.com/opinion/creative-builders-inc-v-avenue-developments-inc-arizctapp-1986.