Ebasco Constructors, Inc. v. Ahtna, Inc.

932 P.2d 1312, 1997 Alas. LEXIS 32, 1997 WL 85139
CourtAlaska Supreme Court
DecidedFebruary 28, 1997
DocketS-7476
StatusPublished
Cited by13 cases

This text of 932 P.2d 1312 (Ebasco Constructors, Inc. v. Ahtna, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ebasco Constructors, Inc. v. Ahtna, Inc., 932 P.2d 1312, 1997 Alas. LEXIS 32, 1997 WL 85139 (Ala. 1997).

Opinion

OPINION

MATTHEWS, Justice.

This is an appeal of the superior court’s confirmation of an arbitration proceeding and of its decision to add prejudgment interest to the arbitrator’s award. We affirm in part and reverse in part.

I. FACTS & PROCEEDINGS

The arbitration proceeding at issue involved a dispute concerning a joint venture agreement (“JVA”) between Ahtna and En-serch, a predecessor to Ebasco Constructors, Inc. (Ebasco). The JVA was formed as part of an effort by Ebasco to win a subcontract with General Electric Company for work on an Air Force project. The project eventually was canceled. The JVA provided that “[a]ll disputes arising out of this Agreement shall be resolved by arbitration under the Commercial Rules of the American Arbitration Association and subject to the provisions of Alaska’s Uniform Arbitration Act_” Aht-na submitted for arbitration a claim against Ebasco for proposal costs it incurred in connection with the JVA. The arbitrator determined that Ebasco was liable to Ahtna.

*1314 We have already decided some issues relating to the validity of the arbitration proceeding. In Ahtna v. Ebasco Constructors, Inc., 894 P.2d 657 (Alaska 1995) (hereinafter “Ahtna I ”), we reversed the superior court’s determination that the dispute was not arbi-trable. We remanded the case to allow the superior court to determine whether

under 09.43.120(a)(4) ... the award should be vacated (1) because the arbitrator refused to postpone the hearing after sufficient cause had been shown; and (2) because Ebasco did not receive a specific explanation of Ahtna’s complaint until approximately one month before the arbitration.

Id. at 660 n. 4. On remand, the superior court decided that the arbitrator’s award should not be vacated. The superior court also awarded “Pre- and Post-Judgment Interest on Ahtna’s claim ... from March 4,1991 [the date of Ahtna’s claim] through August 25, 1995 [the date of the superior court’s judgment confirming the arbitration award].” Finally, the superior court awarded “Post-Judgment Interest on the Arbitration Award of Attorneys Fees ... from September 1, 1992 through August 25, 1995.” Ebasco appeals all three rulings of the superior court.

A. Facts Related to the Claim that the Arbitrator’s Refusal to Postpone the Hearing Was Improper

On February 13, 1992, the American Arbitration Association issued an order confirming that Wayne White, senior counsel for Ebasco, would be “representing Ebasco” in the arbitration proceeding. White participated in a number of pre-arbitration proceedings. On April 1, 1992, the arbitrator scheduled the arbitration proceedings to begin on July 13,1992.

Ebasco had a long relationship with the law firm of Burr, Pease & Kurtz and consulted with the firm on various matters related to the arbitration. On May 29,1992, Ebasco asked J.W. Sedwick of Burr, Pease & Kurtz to serve as its trial counsel for the arbitration. Burr, Pease & Kurtz undertook the representation of Ebasco the same day.

On June 19, Burr, Pease & Kurtz advised Ebasco that, because a conflict of interest had arisen, it would withdraw as Ebasco’s trial counsel for the arbitration. The same day, Burr, Pease & Kurtz moved to postpone the arbitration. Shortly thereafter, Ebasco retained John Conway as substitute trial counsel for the arbitration.

On June 26, the arbitrator held a hearing on the motion to postpone, and rendered a decision denying the motion the same day. The arbitrator found that

there was no notification to the Arbitrator that the firm of Burr, Pease & Kurtz was involved in this case on behalf of Ebasco until June 10, 1992 and that substitute counsel, John Conway has sufficient time to familiarize himself with the case as Alaska counsel before July 13, 1992 given the fact that Wayne White has been primary counsel for Ebasco throughout these proceedings since the initial hearing on April 1,1992.
B. Facts Related to the Claim that the Arbitration Award Should Be Vacated because Ebasco Did Not Receive a Sufficiently Specific Explanation of Ahtna’s Complaint Prior to the Arbitration Proceeding

In a letter dated November 15, 1990, Ebasco requested that General Electric reimburse Ebasco for its proposal costs. The letter stated:

We feel that recovery of our proposal costs is justified due to the unreasonable delays and changes in the program and because we devoted extensive resources to the ... proposal effort based on the anticipation of receiving a sole source contract for the work and in accordance with the various GE RFQ requests.

On January 17,1992, Ahtna filed a demand for the arbitration proceeding at issue in this case. Ahtna indicated on the demand for arbitration form that the “nature of the dispute” was “Breach of Contract” and that the relief sought was “[i]n an amount to be proven at the time of arbitration.”

In a letter dated April 1,1992, the arbitrator stated that Ahtna had agreed to “file a statement of ... [its] claim within seven (7) days.” The same day, Ahtna filed a claim for proposal costs totaling 1.7 million dollars. It also filed certain supporting materials.

*1315 These documents did not explain the legal theory underlying Ahtna’s claim against Ebasco.

On June 10, 1992, the arbitrator ordered Ahtna to provide, by June 18, 1992, a brief written statement outlining its claim. On June 18, Ahtna provided a “statement of issues.” The statement of issues asserts, among other things, that “[t]he issues of this arbitration concern, in general, the failure of Ebasco to fulfill its partnership duties to Ahtna since cancellation of ... [the Air Force project] and, in particular, Ebasco’s failure to properly forward the Ahtna/Ebasco Joint Venture claim to General Electric.” (Emphasis supplied.) Ahtna later submitted a memorandum in opposition to Ebasco’s motion to reschedule the hearing. That document was dated June 22, 1992. It stated, in part, that “[e]ither Ebasco passed the claim through or they did not_ Further, provided Ebasco passed this claim through to the government as they have repeatedly asserted, the Contract Disputes Act requires that such a claim be certified.” (Emphasis supplied.)

On July 13, 1992, the first day of the arbitration hearing on the merits, Ahtna asserted that it was entitled to an award from Ebasco on the basis of a previously unartieu-lated theory of liability:

Notwithstanding some cautionary language in the Ebasco/GE Teaming Agreement and the Ebaseo/Ahtna Joint Venture, Ahtna was never advised that the Project would not be awarded. In fact, Ahtna was repeatedly assured that things were on track and that it should continue to work to assist Ebasco to provide GE and the Air Force with proposals and to prepare for an imminent award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moore v. Olson
351 P.3d 1066 (Alaska Supreme Court, 2015)
State v. ALASKA PUBLIC EMPLOYEES ASS'N
199 P.3d 1161 (Alaska Supreme Court, 2008)
State v. Alaska State Employees Ass'n
190 P.3d 720 (Alaska Supreme Court, 2008)
Department of Corrections v. Fluor Daniel, Inc.
160 Wash. 2d 786 (Washington Supreme Court, 2007)
STATE DEPT. OF CORRECTIONS v. Fluor Daniel, Inc.
161 P.3d 372 (Washington Supreme Court, 2007)
Duncan v. National Home Insurance Co.
36 P.3d 191 (Colorado Court of Appeals, 2001)
Joseph D. Pike v. Brian M. Freeman
266 F.3d 78 (Second Circuit, 2001)
Pike v. Freeman
266 F.3d 78 (Second Circuit, 2001)
Hart v. McChristian
36 S.W.3d 357 (Court of Appeals of Arkansas, 2000)
Arbitration Between Kalawaia v. AIG Hawai'i Insurance Co.
977 P.2d 175 (Hawaii Supreme Court, 1999)
Marathon Oil Co. v. ARCO Alaska, Inc.
972 P.2d 595 (Alaska Supreme Court, 1999)
Porush v. Lemire Ex Rel. Estate of Lemire
6 F. Supp. 2d 178 (E.D. New York, 1998)
EEC Property Co. v. Kaplan
578 N.W.2d 381 (Court of Appeals of Minnesota, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
932 P.2d 1312, 1997 Alas. LEXIS 32, 1997 WL 85139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ebasco-constructors-inc-v-ahtna-inc-alaska-1997.