Ahtna, Inc. v. Ebasco Constructors, Inc.

894 P.2d 657, 1995 Alas. LEXIS 48, 1995 WL 283530
CourtAlaska Supreme Court
DecidedMay 12, 1995
DocketS-5841
StatusPublished
Cited by34 cases

This text of 894 P.2d 657 (Ahtna, Inc. v. Ebasco Constructors, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ahtna, Inc. v. Ebasco Constructors, Inc., 894 P.2d 657, 1995 Alas. LEXIS 48, 1995 WL 283530 (Ala. 1995).

Opinion

ORDER

On consideration of the petition for rehearing, filed on March 17, 1995, and the corrected petition for rehearing, filed on March 20, 1995,

IT IS ORDERED:

1. The petition for rehearing is DENIED.

■2. However, the opinion is modified to overrule the approach taken in Anchorage Medical & Surgical Clinic v. James, 555 P.2d 1320, 1828 (Alaska 1976). Accordingly, Opinion No. 4178, issued on March 10, 1995, is WITHDRAWN, and Opinion No. 4199 is issued today in its place. The modification is found at page 11 of Opinion No. 4199.

Entered by direction of the court at Anchorage, Alaska on May 12, 1995.

MOORE, Chief Justice.

I. INTRODUCTION

In this appeal from an arbitration proceeding, the superior court vacated Ahtna’s arbitration award after concluding that the arbitrator exceeded his power by resolving a non-arbitrable dispute. We reverse.

II. FACTS AND PROCEEDINGS

In 1988 the U.S. Air Force was considering locating the Alaska Radar System Over-the-Horizon Backscatter Radar Project (“the Project”) on lands owned by Ahtna, Inc. (“Ahtna”). A leading general contractor candidate on this project was General Electric Co. (“GE”). In February 1988 Ensereh Alaska Services, Inc. (“Ensereh”), a predecessor to Ebasco Constructors, Inc. (“Ebas-co”), entered into an agreement (“the Teaming Agreement”) with GE. The Teaming Agreement called for Ensereh to assist GE in securing the Project’s prime contract for GE, which would then enter into a subcontract with Ensereh.

In May 1989 Ahtna and Ensereh entered into a joint venture agreement (“JVA”). The purpose of the Joint Venture was to obtain, perform, and receive payment for “contracting opportunities in the design, construction, testing, and operations maintenance” of the Project. Section 22 of the JVA provided that: “All disputes arising out of this Agreement shall be resolved by arbitration under the Commercial Rules of the American Arbitration Association and subject to the provisions of Alaska’s Uniform Arbitration Act, AS 09.43.010, et seq.”

At the time the JVA was executed, the Project was still in its preliminary stages: the Air Force had not yet selected a project site or a general contractor and it was uncertain whether the Project would actually be built; additionally, GE had the option to subcontract with parties other than the Aht-na/Ensereh Joint Venture. However, in an attempt to secure a Project sub-contract, the Joint Venture submitted to GE three construction proposals and two revisions. In so doing, it incurred significant expenses.

In November 1990 Ebasco notified GE that the Joint Venture intended to submit a claim for compensation, based upon implied contract, seeking remuneration for the extraordinary costs incurred in the proposal and design work. The letter stated that Ebasco would submit “a claim for impact and proposal costs, to include those of our Joint Venture partner, Ahtna.” Two months later, GE advised Ebasco that the government had canceled the Project.

*659 Ebasco directed Ahtna to prepare a claim reflecting the losses and expenses incurred in the creation of the construction proposals. In March 1991 Ahtna submitted to Ebasco its claim for costs and expenses in the amount of $1.7 million. Ebasco did not submit Ahtna’s claim for many months, however, despite a number of unsuccessful inquiries by Ahtna aimed at speeding up the process. According to Ahtna, Ebasco’s inaction eventually doomed the claim by “inexplicably fail[ing] to submit the claim ... within ... one year,” as required by federal regulations. In January 1992 Ahtna filed a demand for arbitration.

The parties stipulated to $1.7 million in damages and arbitrated only the issue of liability. In a July 1992 arbitration, Ahtna prevailed on its claim for $1,700,003 plus costs and fees. As he later explained in supplemental findings, the arbitrator held that Ebasco had breached the JVA in two ways.

First, the arbitrator found that Ebasco had breached sections 4 and 7.2 of the JVA by failing to timely submit Ahtna’s claim through GE to the government. Under section 4, each venturing party owed the other an obligation to “use its best efforts to carry out the purposes of [the JVA and] to cooperate fully with the other Joint Venturer.” Section 7.2 provided that the “general supervision and management of the [Joint Venture] work” along with “other matters relating thereto” were “under the ... control of the Sponsor.” Ebasco was designated the Joint Venture “Sponsor” in section 7.1. This basis for the arbitration award is hereinafter termed the “tardy claim rationale.”

Second, notwithstanding the dispute over Ebasco’s submission of Ahtna’s claim, the arbitrator found that Ebasco had breached sections 5.1, 5.2, and 11.7 of the JVA by simply failing to compensate Ahtna for the $1.7 million in expenses incurred in preparation of the Project proposals. Section 5.1 of the JVA stated that it was “expressly understood and agreed ... that Ahtna ... shall not be liable for any losses in performance of the Joint Venture work.” Section 11.7 obligated the Joint Venture “as soon as reasonably practicable ... [to] reimburse the Joint Venturers for all expenses incurred in connection with the preparation of the Proposal for ... [the Project] as determined in accordance with section 5.2.” Section 5.2 provided that “[p]roposal costs ... related to the Project ... will be submitted to the [Joint Venture] Management Committee for approval,” and “paid in accordance with Section 11.7.” 1 This basis for the arbitral award is hereinafter termed the “reimbursement rationale.”

In August 1992 Ahtna moved in superior court for confirmation of the award. Ebasco opposed the motion and moved, pursuant to Alaska’s Uniform Arbitration Act (“the Act”), to vacate the award.

The superior court ordered and received a clarification of the arbitrator’s decision and then, following two subsequent hearings, vacated the arbitrator’s award. The court’s opinion discussed only the “tardy claim rationale;” it concluded that under that theory of liability Ebasco’s obligation to submit Aht-na’s claim “arose after the [JVA] terminated.” The court found that since “[t]he claim upon which the award is based does not arise out of the [JVA],” and since “[n]o agreement existed to arbitrate claims arising out of extra-contractual promises or an implied contract,” the dispute was not arbitrable. Consequently, the court held that the arbitrator had “exceeded his power” and vacated the award under AS 09.43.120. 2

*660 III. DISCUSSION

On appeal, Ahtna argues: (1) that the lower court erred by ignoring the arbitrator’s reimbursement rationale, which Ahtna believes to be an independent basis for enforcing the arbitral award; and (2) that the court erred in rejecting the arbitrator’s tardy claim rationale. 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graham v. Municipality of Anchorage
446 P.3d 349 (Alaska Supreme Court, 2019)
Hudson v. Citibank (South Dakota) NA
387 P.3d 42 (Alaska Supreme Court, 2016)
Moore v. Olson
351 P.3d 1066 (Alaska Supreme Court, 2015)
Johnson v. The Aleut Corporation
307 P.3d 942 (Alaska Supreme Court, 2013)
State v. ALASKA PUBLIC EMPLOYEES ASS'N
199 P.3d 1161 (Alaska Supreme Court, 2008)
Gilbert v. State Farm Insurance Co.
171 P.3d 136 (Alaska Supreme Court, 2007)
Lexington Marketing Group, Inc. v. Goldbelt Eagle, LLC
157 P.3d 470 (Alaska Supreme Court, 2007)
Kinn v. Alaska Sales & Service, Inc.
144 P.3d 474 (Alaska Supreme Court, 2006)
OK Lumber Co., Inc. v. Alaska RR Corp.
123 P.3d 1076 (Alaska Supreme Court, 2005)
State Farm Mutual Automobile Insurance Co. v. Dowdy
111 P.3d 337 (Alaska Supreme Court, 2005)
Driver v. SI CORP.
80 P.3d 1024 (Idaho Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
894 P.2d 657, 1995 Alas. LEXIS 48, 1995 WL 283530, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ahtna-inc-v-ebasco-constructors-inc-alaska-1995.