Elcon Construction, Inc. v. Eastern Washington University

273 P.3d 965, 174 Wash. 2d 157
CourtWashington Supreme Court
DecidedMarch 29, 2012
Docket83690-6
StatusPublished
Cited by216 cases

This text of 273 P.3d 965 (Elcon Construction, Inc. v. Eastern Washington University) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elcon Construction, Inc. v. Eastern Washington University, 273 P.3d 965, 174 Wash. 2d 157 (Wash. 2012).

Opinions

C. Johnson, J.

¶1 This case involves a claim for damages relating to a drilling contract between petitioner Eicon Construction and respondent Eastern Washington University. In the suit, tort and contract claims were alleged by Eicon. The contract claims were resolved by arbitration. In dismissing the tort claims, the trial court applied the independent duty rule, formerly known as the economic loss rule, which the Court of Appeals similarly applied in affirming.1 We hold the economic loss rule has no application under the facts of this case but affirm the Court of Appeals on different grounds.

Facts

f 2 Eastern relies on two on-campus wells for its water supply (wells 1 and 2), both of which draw from what is called the Wanapum Aquifer. Beginning in 1987, Eastern requested approval from the Department of Ecology (DOE) [161]*161to consolidate its water rights. In 2003, the DOE approved Eastern’s request, thereby allowing Eastern to “refurbish” its two existing on-campus wells to increase their individual yields.2 Under DOE rules, refurbishment could include drilling replacement wells in close proximity to the existing wells. Eastern decided to drill replacement wells near wells 1 and 2 and began accepting bids for the job. Eastern’s “Instructions to Bidders” contained an “Examination of Site and Conditions” section, which stated in relevant part that by submission of a proposal, the bidder acknowledges:

1. That it has taken steps reasonably necessary to ascertain the nature and location of the Work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the Work or its cost, including . . . (d) the conformation and conditions of the ground; and (e) the character of equipment and facilities needed preliminary to and during the performance of the Work.
2. That it has satisfied itself as to the character, quality and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by Owner ....

D. No statement made by any officer, agent, or employee of the Owner or [Architeet/Engineer] in relation to the physical conditions pertaining to the site of the work will be binding on the Owner or [Architeet/Engineer].

Clerk’s Papers (CP) at 1113-14. Prior to bidding, Eicon contacted Eastern and requested all the information it had about the project, about other wells in the area, or about the [162]*162geology relating to wells in the area of the drill site. Three years earlier, in 2000, Eastern had hired Varela & Associates to conduct a water capacity study, seeking to identify future options for expanding its water supply. Varela, in turn, hired Golder Associates to perform a hydrogeological investigation. The “Golder Report,” based primarily on published reports and selected drillers’ logs obtained from the DOE, contained information about the regional hydrology and recommended future wells be drilled into the Grande Ronde Aquifer below the Wanapum Aquifer at a depth of between 700 to 1,500 feet. CP at 338, 340. Per Eicon’s request, Eastern provided Eicon a well log for well 2 and a video of well 1 but did not provide the Golder Report. CP at 864. Eicon submitted the low bid ($1,516,635) and was awarded the contract. CP at 1106-07.

¶3 The contract required Eicon to drill two replacement wells to an “estimated” depth of 750 feet.3 CP at 357. The contract specified that “[slhould water of sufficient quantity and quality be encountered at lesser depths, drilling may be stopped by the Owner. Likewise, the Owner may direct the depth to be increased in order to obtain sufficient water.” CP at 357. In addition, the “General Provisions” of the contract placed a duty on Eicon to investigate the site and subsurface conditions. CP at 1123-24. Eicon delegated this duty to its subcontractor, Intermountain Drilling. Outside of requesting information from Eastern and looking at several DOE well logs on-line, Intermountain Drilling did not conduct an independent investigation. CP at 1211-12.

¶4 In July 2003, work started on replacement well 1. Drilling stopped soon after it started, however, when an unforeseen layer of sand disrupted the work. Then, upon learning that it may have to drill significantly deeper than 750 feet, Eicon insisted upon payment for increased costs. Eastern terminated the contract for convenience instead [163]*163and solicited a final pay request, which Eicon submitted to Eastern on June 4, 2004.

¶5 Upon learning of previously unknown damage to replacement well 1, Eastern issued a termination for cause letter on October 22, 2004, a copy of which was sent to Eicon’s bond surety. Elcon filed this lawsuit claiming breach of contract, in addition to various tort claims.4 The trial court, interpreting the contract’s arbitration provisions, submitted all contract claims to arbitration and stayed Eicon’s tort claims pending completion of arbitration.5 CP at 211-13.

f6 In December 2005, the arbitrator awarded Eicon $1,837,000 ($891,000 in addition to $946,000 Eastern had previously paid for work performed) and denied Eicon’s postaward motion for statutory interest. CP at 1132-33. Following arbitration, Eicon pursued its tort claims against Eastern, which included fraud in the inducement for not providing the Golder Report and interference with a business relationship for sending a copy of the termination for cause letter to Eicon’s surety. The trial court granted summary judgment dismissing Eicon’s fraud and intentional interference claims, finding the intentional interference claim factually insufficient and the fraud claims [164]*164barred by the economic loss rule.6 Relying on Alejandre v. Bull, 159 Wn.2d 674, 153 P.3d 864 (2007), the Court of Appeals affirmed, holding all Eicon’s tort claims barred by the economic loss rule.

Issues

¶7 1. Whether summary judgment was appropriate with respect to Eicon’s fraud in the inducement claim.

¶8 2. Whether summary judgment was appropriate with respect to Eicon’s intentional interference with a contractual relationship claim.

¶9 3. Whether Eicon is entitled to statutory interest on its arbitration award.

Standard of Review

110 We review summary judgment orders de novo and perform the same inquiry as the trial court, viewing all facts and reasonable inferences in the light most favorable to the nonmoving party. Hisle v. Todd Pac. Shipyards Corp., 151 Wn.2d 853, 860, 93 P.3d 108 (2004) (citing Kruse v. Hemp, 121 Wn.2d 715, 722, 853 P.2d 1373 (1993)). The grant of summary judgment is appropriate where there is “no genuine issue as to any material fact and . . . the moving party is entitled to a judgment as a matter of law.” CR 56(c). “A material fact is one that affects the outcome of the litigation.” Owen v. Burlington N. Santa Fe R.R., 153 Wn.2d 780, 789, 108 P.3d 1220 (2005) (citing Hisle, 151 Wn.2d at [165]*165861). Where no dispute as to the material facts exists, summary judgment is proper.

Analysis

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Snohomish Health District, Res. V. John Postema, Apps.
Court of Appeals of Washington, 2025
Getzels v. Kirby Ai
E.D. Washington, 2025
Taneja v. Freitas
W.D. Washington, 2023
Snyder v. Stox Technologies LTD
W.D. Washington, 2021
Busey v. Wells Fargo Bank NA
W.D. Washington, 2020
Jinni Tech Ltd v. Red.com Inc
W.D. Washington, 2020
Converse v. Vizio, Inc.
W.D. Washington, 2020
Patrick White v. Granite Falls
Court of Appeals of Washington, 2020
623 Main Street Assoc. v. John Phillip Hall
Court of Appeals of Washington, 2019
Estate Of Doris Mathews
Court of Appeals of Washington, 2019
Christine Conner v. Jeremy Meadows, D.c.
Court of Appeals of Washington, 2019
Valerie Strout v. Walmart Stores, Inc.
Court of Appeals of Washington, 2019
Kevin Scott Christian v. Thomas F. Stark
Court of Appeals of Washington, 2019

Cite This Page — Counsel Stack

Bluebook (online)
273 P.3d 965, 174 Wash. 2d 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elcon-construction-inc-v-eastern-washington-university-wash-2012.