Al & Paulette Jansen, V. Peoples Bank, Et Ano.

CourtCourt of Appeals of Washington
DecidedJune 20, 2023
Docket83994-2
StatusUnpublished

This text of Al & Paulette Jansen, V. Peoples Bank, Et Ano. (Al & Paulette Jansen, V. Peoples Bank, Et Ano.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Al & Paulette Jansen, V. Peoples Bank, Et Ano., (Wash. Ct. App. 2023).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

AL and PAULETTE JANSEN, No. 83994-2-I

Appellants, DIVISION ONE v.

PEOPLE’S BANK, a Washington Bank UNPUBLISHED OPINION Corporation; and CRAIG CAMMOCK, an individual,

Respondents.

SMITH, C.J. — Al and Paulette Jansen obtained financing from Peoples

Bank to build a home. As a condition of the loan agreement, the Jansens

needed to obtain the Bank’s approval before making any material or substantial

changes to the construction plans, such as changing contractors. After the

Jansens terminated their contractor without notice to the Bank, the Bank sent the

Jansens a letter declaring them to be in default. In response, the Jansens sued

the Bank, alleging breach of contract, breach of the duty of good faith and fair

dealing, and violations of the Consumer Protection Act, chapter 19.86 RCW.

They also sued the Bank’s lawyer for tortious interference with the contract. The

trial court dismissed all the Jansens’ claims in consecutive summary judgment

motions. The Jansens appeal, asserting that the trial court erred in concluding

that the Bank did not breach the contract and that no issues of material fact

existed. We disagree and affirm. No. 83994-2-I/2

FACTS

In October 2019, Al and Paulette Jansen obtained a $935,000 loan from

Peoples Bank to build a home in Bow, Washington. The parties executed a

Construction Loan Agreement and an Adjustable Rate Note. The latter

contained an addendum allowing the Jansens the option of converting their

construction loan into a permanent loan. Several provisions of the loan

agreement are relevant to this appeal.

Section 3 is entitled “The Work” and provides general guidelines for the

construction. It provides that any changes to the work must be in a written

agreement, signed by the Jansens and their contractor, and approved by the

Bank.

Section 4 concerns the loan and addresses disbursements, use of funds,

and the construction loan account. It makes clear that the Bank has no

obligation to disburse any loan proceeds during any period of default. It also

provides that the Bank may disburse funds in a matter and at a rate that the Bank

deems consistent with construction progress. Lastly, section 4 provides that the

borrower, in conjunction with the contractor, is responsible for providing invoices

and lien waivers to the Bank—the Bank has no affirmative duty to verify any of

that information.

Section 6 covers events of default and the Bank’s available remedies. It

defines what constitutes a default and authorizes the Bank to declare a default

and to cancel permanent financing in the case of a default.

2 No. 83994-2-I/3

Issues began shortly after construction started. The Jansens, unhappy

with the work being done by their contractor, asked their son Grant, himself a

construction professional, to investigate the contractor’s performance. Grant

reported to his parents that the Bank “had administered payments to the

contractor in numerous improper ways” and that both the Bank and contractor

had breached their agreements with the Jansens.

In March 2020, the Jansens parted ways with their contractor and hired

Grant to finish the construction. In early April, Grant sent an e-mail to the Bank

explaining the new arrangement. Grant told the Bank: “As you know the contract

with [the contractor] is terminated. We are completing the project ourselves

personally so there is no new contract to give you.” Grant also told the Bank that

it was no longer authorized to make further payments to the contractor and that

the Jansens would “reconcile any final payment to or refund from [the contractor]

on [their] own.”

A few days later, the Bank sent the Jansens a letter acknowledging receipt

of Grant’s e-mail and alerting them that termination of the contractor constituted

default because it was “a substantial and material change to conditions of the

loan.” The Bank advised the Jansens to “promptly and adequately address this

substantial change of circumstance in compliance with the provisions of the Loan

Documents” and execute a termination document. The Jansens did not do so.

Instead, in June 2020, the Jansens sued the Bank and its lawyer, Craig

Cammock. Against the Bank, the Jansens alleged breach of contract, breach of

the duty of good faith and fair dealing, and a Consumer Protection Act violation.

3 No. 83994-2-I/4

Against Cammock, the Jansens alleged tortious interference with a contract. The

Bank promptly moved to dismiss under CR 12(b)(6), but the court denied its

motion. However, the court noted that it had “significant question as to some of

the breaches alleged in the Complaint, particularly those subsequent to the

termination of the contractor” and “invite[d] these issues to be brought back

before the [sic] it on a motion for summary judgement [sic].” Cammock then

individually moved for summary judgment on the tortious interference claim and

the court granted his motion and dismissed the claim.

Once the parties completed initial discovery, the Bank moved for summary

judgment on all remaining claims. The court granted the Bank’s motion. The

Jansens appealed.

Shortly after the Jansens filed their notice of appeal, the Bank petitioned

the trial court for attorney fees and costs and Cammock moved for sanctions

under CR 11. Following oral argument, the court denied Cammock’s motion for

sanctions, but granted the Bank’s petition for fees and awarded it $92,142.50.

ANALYSIS

We are presented with three issues on appeal. First, whether the court

erred in granting summary judgment for the Bank on the Jansens’ seven breach

of contract claims. We conclude that it did not. On each of the seven breach

claims, the Jansens fail to demonstrate either the existence or breach of a

contractual duty. Second, whether the court erred in granting summary judgment

for the Bank on the Jansens’ breach of duty of good faith and fair dealing claim.

Because the duty of good faith and fair dealing must be connected to a valid

4 No. 83994-2-I/5

breach of contract claim—which the Jansens do not have—we affirm this

dismissal. Third, whether the court erred in granting summary judgment for the

Bank on the Jansens’ Consumer Protection Act (CPA) claim. We affirm the

court’s dismissal of the CPA claim because the Jansens do not identify any unfair

or deceptive practice by the Bank.

Finally, both parties request fees on appeal. Because the Jansens do not

provide a legal basis for fees, we deny their request. And because the Bank

does provide a legal and contractual basis for fees, we award them fees.

Standard of Review

We review de novo an order granting summary judgment and engage in

the same inquiry as the trial court. Assoc. General Contractors of Wash. v.

State, 200 Wn.2d 396, 403, 518 P.3d 639 (2022). “Summary judgment is

appropriate when there are no genuine issues of material fact and the moving

party is entitled to judgment as a matter of law.” Lakehaven Water & Sewer Dist.

v. City of Federal Way, 195 Wn.2d 742, 752, 466 P.3d 213 (2020) (citing

CR 56(c)). We consider the evidence and reasonable inferences from it in the

light most favorable to the nonmoving party. Kim v. Lakeside Adult Family

Home, 185 Wn.2d 532, 547, 374 P.3d 121 (2016). If reasonable minds could

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Olympic Steamship Co., Inc. v. Centennial Ins. Co.
811 P.2d 673 (Washington Supreme Court, 1991)
Hartley v. State
698 P.2d 77 (Washington Supreme Court, 1985)
Hangman Ridge Training Stables, Inc. v. Safeco Title Insurance
719 P.2d 531 (Washington Supreme Court, 1986)
Silverdale Hotel Associates v. Lomas & Nettleton Co.
677 P.2d 773 (Court of Appeals of Washington, 1984)
Redford v. City of Seattle
602 P.2d 717 (Court of Appeals of Washington, 1979)
Badgett v. Security State Bank
807 P.2d 356 (Washington Supreme Court, 1991)
Elcon Construction, Inc. v. Eastern Washington University
273 P.3d 965 (Washington Supreme Court, 2012)
Hearst Communications v. Seattle Times Co.
115 P.3d 262 (Washington Supreme Court, 2005)
Ranger Ins. Co. v. Pierce County
192 P.3d 886 (Washington Supreme Court, 2008)
Owen v. Burlington Northern and Santa Fe RR Co.
108 P.3d 1220 (Washington Supreme Court, 2005)
Panag v. Farmers Ins. Co. of Washington
204 P.3d 885 (Washington Supreme Court, 2009)
State Of Washington, Resp/x-app v. The Mandatory Poster Agency Inc, Apps/x-resps
199 Wash. App. 506 (Court of Appeals of Washington, 2017)
Keodalah v. Allstate Ins. Co.
449 P.3d 1040 (Washington Supreme Court, 2019)
Rekhter v. Department of Social & Health Services
323 P.3d 1036 (Washington Supreme Court, 2014)
Owen v. Burlington Northern Santa Fe Railroad
153 Wash. 2d 780 (Washington Supreme Court, 2005)
Hearst Communications, Inc. v. Seattle Times Co.
154 Wash. 2d 493 (Washington Supreme Court, 2005)
Ranger Insurance v. Pierce County
164 Wash. 2d 545 (Washington Supreme Court, 2008)
Department of Social & Health Services v. Luak
271 P.3d 234 (Washington Supreme Court, 2012)
Condon v. Condon
298 P.3d 86 (Washington Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Al & Paulette Jansen, V. Peoples Bank, Et Ano., Counsel Stack Legal Research, https://law.counselstack.com/opinion/al-paulette-jansen-v-peoples-bank-et-ano-washctapp-2023.